99 Neb. 785 | Neb. | 1916
Defendant Pesha entered into a contract with the school district of Auburn for the erection of a high school building for the contract price of $39,105, and, in compliance with the provisions of section 3840', Rev. St. 1913, gave bond for the payment of claims for labor and material, defendant Equitable Surety Company executing the bond as surety. A copy of the contract, bond and technical and general specifications are attached to and made a part of the petition. The contract bears date March 5, 1912, and the bond March 12, 1912. On January 8, 1913, Pesha borrowed from plaintiff $1,500, which sum was placed to his credit on open account. As security for this loan he gave plaintiff a written order or assignment, addressed to the board of education of the school district, directing them to
A public school building cannot be subjected to a mechanic’s lien. Section 3840, Rev. St. 1913, requiring the contractor to give a bond, was doubtless enacted for the purpose of protecting mechanics and materialmen. The bond, therefore, became an essential part of the contract entered into by and between Pesha and the school district. The contract provided for estimates by the architect and for payments from time to time, and provided that “the amount to be paid to the contractor shall be eighty-five per cent. (85%) of the amount of such estimate on the presentation of the progress certificate.” It also provided : “The final estimate shall be made when the architect is satisfied that the work is. entirely and satisfactorily completed, at which time the contractor shall be entitled to the fifteen per cent. (15 %) retainer from the progress payments, as balance due him on the contract.”
The question to be determined is: Is plaintiff, by virtue of its assignment as security for money advanced, to the contractor, entitled to priority over the surety who has by the terms of its bond been required to pay for materials
In that case the court followed Prairie State Bank v. United States, 164 U. S. 227, 230, wherein it is said: “Thus the respective contentions are as follows: The Prairie Bank asserts an equitable lien in its favor, which it claims originated in February, 1890, and is therefore paramount to Hitchcock’s lien, which it is asserted arose only at the date of his advances. The claim of Hitchcock, on the other hand, is that his equity arose at the time he entered into the contract of suretyship, and therefore his right is prior in date and paramount to that of the bank. . * * * That Hitchcock, as surety on the original contract, was entitled to assert the equitable doctrine of subrogation is elementary. * * * Under, the principles thus governing subrogation, it is clear, whilst Hitchcock was entitled to subrogation, the bank was not. The former in making his payments discharged an obligation due by Sundberg for the performance of which he, Hitchcock, was bound under the obligation of his suretyship. The bank, on the contrary, was a mere volunteer, who lent money to Sundberg on the faith of a presumed agreement and of supposed rights acquired thereunder. The sole question, therefore, is whether the equitable lien, which the bank claims it has, without reference to the question' of its subrogation, is paramount to the right of subrogation which unquestionably exists in favor of Hitchcock. In other words, the rights of the parties depend upon whether Hitchcock’s subrogation must be considered as arising
It is insisted that, since the money loaned Pesha by plaintiff was used to pay expenses incurred in constructing the building, the surety company has received the benefit of such payments, liability on the bond being reduced to that extent. Plaintiff was under no obligation to advance the money, and, as shown by the above authorities, in doing so it acted voluntarily. It is not entitled to be subrogated, as against the defendant surety company, to the rights of Pesha’s creditors to whom the money was paid.
Affirmed.