Aрpellants CIT Construction Inc. of Texas and Firemen’s Insurance Company of Newark, New Jersey (“Plaintiffs”) sued appellee Board of Regents of the University of Texas System (“UT”) for breach of contract, quantum meruit, and taking of property without compensation in violation of article I, section 17 of the Texas Constitution. UT made a plea to the jurisdiction asserting that its sovereign immunity from suit deprived the trial court of jurisdiction. The trial court аgreed and dismissed Plaintiffs’ claims for want of jurisdiction. On appeal, Plaintiffs challenge this dismissal on three grounds: legislative waiver of immunity from suit on a contract; violation of the “open courts” provision of article I, section 13 of the Texas Constitution; and proper pleading of a takings claim. We will affirm the trial-court judgment.
FACTUAL AND PROCEDURAL BACKGROUND
In a plea to the jurisdiction, the trial court must base its decision solely on the allegations in the plaintiffs pleadings.
Brannon v. Pacific Employers Ins. Co.,
In November 1986, UT contracted with CIT for cоnstruction of the Nuclear Engineering Testing Laboratory located in Austin. CIT alleges that UT frustrated completion of the building through changes to the specifications and scope of the project. Despite this interfеrence, UT certified the project as ninety-seven percent complete in October 1988. Thereafter, UT declared CIT in default and refused to pay the balance due under the contract.
Following CIT’s terminаtion, its surety, Firemen’s Insurance Company, attempted to complete the project. Firemen’s contends that UT also interfered with its work on the project through similar changes in specifications requiring additional work. Firemen’s alleges that despite completing the project, UT refused to pay it over $630,000 in contract balances and additional expenses.
CIT sued UT for breach of contract, quantum meruit, and unlawful taking of property without compensation. UT challenged the jurisdiction of the trial court on the basis of sovereign immunity from suit. Following a January 5,1993 hearing, the trial court orally denied UT’s plea to the jurisdiction. Firemen’s subsequently intervened in the case. In June 1994, UT requested a rehearing on its plea to the jurisdiction, relying on our opinion in
Green International, Inc. v. State,
On appeal, Plaintiffs challenge the trial court’s dismissаl on three grounds. Initially, Plaintiffs argue that the trial court erred because the Texas Legislature has waived UT’s immunity from suit by authorizing UT *542 to enter into contracts. Additionally, Plaintiffs contend that dismissal of the breach of contract and quаntum meruit claims on immunity grounds violates the open courts provision of article I, section 18 of the Texas Constitution. Finally, Plaintiffs assert that sovereign immunity does not bar a takings claim under article I, section 17 of the Texas Constitution and that they properly pleaded a takings claim.
DISCUSSION
A. Sovereign Immunity from Suit
Plaintiffs first assert that the trial court erred in dismissing the breach of contract and quantum meruit causes of action because sovereign immunity does not bar such claims. They contend that whenever the state enters a contract it waives both immunity from liability and immunity from suit. We disagree.
Plaintiffs’ position runs squarely against our recent holding in
Green
that while the state waives its immunity from liability when it enters into a contract, it retains its immunity from suit.
Confronted with this controlling authority, Plaintiffs lоdge two arguments. First, Plaintiffs argue that their ease is distinguishable from Green because they allege it was “impossible” for them to obtain legislative consent to sue. Plaintiffs contend that, because this is a plea to the jurisdiction of the trial court, we must accept this conclusion of impossibility as true. Plaintiffs are incorrect.
In a jurisdictional challenge we accept the
factual
allegations as true. But we are bound neither by the legal conclusions nor by any illogical factual conclusions that Plaintiffs draw from the facts pleaded.
See Salazar v. Morales,
Unable to distinguish their situation from Green, Plaintiffs next contend that Green was wrongly decided. We recognize that the supreme court has granted the application for writ of error in Green. Nonetheless, until we receive guidance to the contrary, we stand by our holding that the statе’s waiver of immunity from liability on a contract does not waive its immunity from suit. Plaintiffs did not seek and do not have legislative consent to sue the state. Consequently, the trial court lacked jurisdiction over the contract and quantum meruit claims. Point of error one is overruled.
B. Open Courts
Plaintiffs assert in their second point of error that the “open courts” provision of the Texas Constitution requires that they be *543 given an opportunity to litigate their contract аnd quantum meruit claims. See Tex. Const. art. I, § 13. As with the issue of immunity from suit, we directly addressed and rejected this argument in Green. After reciting the applicable test for the open-courts provision, we held:
Sovereign immunity is a common-law doctrine; it рreceded the current Texas Constitution. Thus, we must read the open-courts provision in light of the pre-existing concept of sovereign immunity. We find no authority holding that the open-courts provision was intended to abolish оr limit sovereign immunity. Accordingly, Green “cannot complain of an unconstitutional deprivation of a nonexistent common law vested right.”
Green,
C. Article I, Section 17 “Taking”
In point of error three, Plaintiffs contend the trial court erred in dismissing their takings claim because sovereign immunity does not preclude such a claim and theirs was properly pleaded. Plaintiffs are correct that sovereign immunity does not protect the state from a proper article I, section 17 takings claim.
See Steele v. City of Houston,
To establish a takings claim, Plaintiffs must allege that the state intentionally performed certain acts which resulted in a “taking” of property for public use.
Green,
A takings claim requires an intentional act of the state.
Steele,
Our supreme court has held that a takings claim must be based on intentional state action that is
within its authority. See Steele,
This distinction is also recognized by a host of federal authority interpreting the Takings Clause of the Fifth Amendment.
2
In
Adams v. United States,
the Government must have lawfully used its power in converting private property to public use. Consequently, the Government official or agency that appropriated private property must have acted within its authority. An unauthorized or unlawful taking is not compensable under the fifth amendment, but is a claim sounding in tort.
Id. (citations omitted) (emphasis added).
Similarly, in
Mac'Avoy v. The Smithsonian Institution,
A prerequisite to a claim under the Takings Clause is proof of the government’s lawful authority to take the property. Here, the plaintiff repeatedly asserts that the Smithsonian took the property unlawfully and without lawful authority. The plaintiffs claims, sounding in tort, do not fall within the scope of the Fifth Amendment’s Takings Clause.
Id.
at 70;
see also Eversleigh v. United States,
As in
Adams
and
MacAvoy,
Plaintiffs in the present case have pleaded fаcts that specifically negate a takings claim. The allegation of fraudulent inducement pleads a tort, not a taking. The trial court did not err in dismissing the claim, because Plaintiffs’ petition affirmatively negated a constitutional claim.
See Green,
CONCLUSION
Based on our holdings in Green, the trial court did not err in dismissing Plaintiffs’ contract, quantum meruit, and takings claims. Having overruled all points of error, 3 we affirm the trial-court judgment.
Notes
. We take judicial notice that on the last day of its regular session, the recently adjourned Seventy-Fоurth Legislature passed resolutions granting seven businesses permission to sue the state for breach of contract. See Tex.S.Con.Res. 41, 74th Leg., R.S. (1995) (Tenneco Power Generation Co.); Tex.S.Con.Res. 52, 74th Leg., R.S. (1995) (CW Systems, Inc.); Tex.S.Con.Res. 53, 74th Leg., R.S. (1995) (John R. Phenix & Associates, Inc.); Tex.S.Con.Res. 93, 74th Leg., R.S. (1995) (Imagents, Inc.); Tex.S.Con.Res. 104, 74th Leg., R.S. (1995) (MKK-North Star); Tex. S.Con.Res. 105, 74th Leg., R.S. (1995) (Green International, Inc.); Tex.S.Con.Res. 106, 74th Leg., R.S. (1995) (Harbert Construction Co.).
. In interpreting our state constitution, it is appropriate to borrow from wеll-reasoned and persuasive federal authority.
Davenport v. Garcia,
. Appellant CIT also raises two general points of error alleging that UT "failed to sustain its burden of proof” and that "disputed fact issues remain." Given our resolution of the three substantive points of error, these additional points leave nothing for further review and are summarily overruled.
See Green,
