In February 1990, the predecessor firm of Finegold, Alexander + Associates, Inc., a Massachusetts corporation, contracted with the General Services Administration to provide architectural and engineering services for the renovation of the Veterans Administration Building in Washington, D.C. Eight months later, Setty & Associates, Ltd., a Virginia corporation, entered into a subeon- *207 tract with Finegold to provide mechanical and electrical designs for the project. During the course of the work, the government project officer requested several changes that required Setty to revise its designs. Setty submitted a certified claim in Fine-gold’s name to GSA for additional compensation for the work required by these changes. GSA opposed the claim on the ground of “accord and satisfaction,” arguing that Fine-gold had already agreed to thé amount of increased compensation GSA would pay for the additional work. The Contracting Officer denied the claim, and Setty’s administrative appeal, prosecuted in Finegold’s name, was subsequently dismissed for lack of prosecution after Finegold refused to finance the litigation.
Setty then filed a demand for arbitration before the American Arbitration Association seeking damages from Finegold. In a series of twelve claims, Setty alleged that Finegold had violated the subcontract by failing to provide timely and accurate information, failing to present Setty’s request for equitable adjustment to GSA, and failing to distribute to Setty an equitable share of the additional compensation it had received from GSA After considering briefs submitted by the parties, the arbitrators appointed to hear the case concluded that the matter was arbitra-ble. Finegold filed suit in D.C. Superior Court to stay the arbitration proceedings. Setty removed the case to federal district court, alleging diversity of citizenship. On cross motions for summary judgment, the district court concluded that most of Setty’s claims were not arbitrable. The court stayed three of Setty’s claims in part and stayed the remaining claims in full. This appeal followed.
Article 4(a) of the subcontract permitted Finegold “at any time, unilaterally” to “make changes in the general scope of this Subcontract,” in which case Setty was obligated to “perform the work as changed without delay.” Under Article 4(e), Setty could submit to Finegold a proposal for equitable adjustment to reflect the additional costs imposed by such changes. Setty’s additional compensation was limited to an “equitable share of any adjustment in [Finegoldj’s Prime Contract with GSA,” and Setty had to submit its proposal “at least five (5) working days before [Finegold] [was] required to submit such proposal to GSA under the terms of the Prime Contract.”
In the event of a dispute between Finegold and Setty “which involve[d] the Government or the terms of the Prime Contract,” Article 9(a) of the subcontract provided that Setty was bound to Finegold to the same extent that Finegold was bound to GSA On the other hand, under Article 9(c) “any dispute or any controversy between [Finegold] and [Setty] not involving the Government or the. terms of the Prime Contract” had to be resolved through binding arbitration (emphasis in original); in the interim, before the dispute was resolved, the subcontractor was bound to follow the instructions of the prime contractor “without interruption, deficiency, or delay.” The subcontract also permitted Setty to pursue claims against the government in Finegold’s name so long as Finegold had “a reasonable opportunity to monitor and participate in any such claim or dispute.”
The case turns on the meaning of Article 9(c). The district court thought the provision precluded arbitration of all claims that “require either an interpretation of the prime contract or an evaluation of the government’s behavior for their resolution.” We shall assume that this construction, which Finegold endorses,, is plausible. Whether it should carry the day is another matter. Much depends on the generosity with which arbitration clauses must be judicially interpreted. .
On this score, Setty directs us to the Supreme Court’s decision in
AT & T Technolo
gies,
Inc. v. Communications Workers,
Although in commercial disputes to which the Federal Arbitration Act applies, such as the one before us,
2
the “positive assurance” test of
Warrior & Gulf
may not control, a nearly equivalent standard does: “any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration.”
Moses H. Cone Mem. Hosp. v. Mercury Constr. Corp.,
We therefore reverse the judgment of the district court in part and direct it to permit arbitration of all of Setty’s claims.
So ordered.
Notes
.
See, e.g., National R.R. Passenger Corp. v. Boston & Maine Corp.,
. Because the subcontract is between two private parties, the Contracts Disputes Act of 1978, 41 U.S.C. §§ 601-613, is inapplicable and the Federal Arbitration Act controls.
See S & M Constructors, Inc. v. FoleyCo.,