102 Ky. 111 | Ky. Ct. App. | 1897
delivered the opinion op the court.
'Chapter 79, Kentucky Statutes, title of which is “Liens,” governs this case, and according to section 2463, being part thereof, “a person who performs labor or furnishes materials in the erection, altering or repairing a house, building or other structure, or for any fixture or machinery therein, or for the excavation of cellars, cisterns, vaults, wells, or for the improvement in any manner of real estate, by contract with or by the written consent of the owner, shall have a lien thereon and upon the land upon which said improvements shall have been made, or on any interest such owner has in the same, to secure the amount thereof, with costs; and said lien on the lands or improvements shall be superior to any mortgage or encumbrance created subsequent to the beginning of the labor or the furnishing of the materials; and said lien, if asserted as hereinafter provided, shall relate back and take effect from the time of the commencement of the labor or the furnishing of the materials.”
The notice required by that section was intended to protect the owner, who might, without it and in ignorance of the claim of a subcontractor or material man, pay the whole amount due to the principal contractor. Nevertheless such lien, though not actually attaching, so as to bind the owner until the required notice is given, has a potential existence, even as to him, and, if asserted within sixty days, like the lien of the principal contractor, relates back and takes effect from the time of the commencement of the labor or the furnishing of the materials, so as to exclude and take precedence of any other lien created in the meantime.
The notice was given by the material man in this case before the iowner had fully paid the principal contractor and while he was still indebted to him; indeed the owner does, not contest his right. Nor is it contended that the lien has been dissolved by failure of appellee to file its claim in the clerk’s office within sixty days as provided in section 2468. But the question presented is simply whether appellant, a general creditor of the principal contractor, has, by attach
We think not, and the judgment is affirmed.
Tbe court delivered the following response to petition fof rehearing December 10, 1897:
As the lien of appellee, when notice of bis claim was given to the owner, related back and took effect front the time the materials ‘were furnished, and it does not appear from tbe record that Ms lien was ever dissolved, which it was incumbent on appellant to show, it must .prevail against Ms attachment lien especially as the owner does not dispute the claim of appellee or contest validity of his lien.
Petition for rehearing overruled.