OPINION and ORDER
This post-award bid protest case is before the court on the parties’ corresponding cross-motions for judgment on the administrative record, as well as plaintiffs request for a permanent injunction. Difficult questions pertaining to balancing the level of deference that should be afforded to military decisions with the enforcement of statutory and regulatory procurement laws are addressed herein. In this regard, the parties have raised numerous persuasive and thought provoking arguments which can be categorized into three predominate sections. First, the parties dispute whether the contracting officer
Factual Background
Throughout the opinion, repeated references are made to engine inlet barrier filter (IBF) systems and so-called “A kits” and “B kits” which comprise the bulk of the system. The Army, defendant, has been on notice for several years, and it is undisputed, that the installation of a filter system significantly reduces damage caused by the ingestion of sand and foreign particles. The Army has twice sought to develop a solution, but both attempts proved unsuccessful. In this context, the IBF is attached to the UH-60 Blackhawk helicopter engine. The UH-60 helicopters to which the filter system will be attached are primarily scheduled to head toward the harsh desert terrain in Iraq. The helicopters being replaced in the combat theater were heavily damaged by the conditions. The “A kits” and “B kits” will work in tandem to counter the corrosive and deteriorating effects of sand particles. Each helicopter is first fitted with an “A Mt,” which serves a dual purpose: (1) it is the hardware to which the filter system is mounted, and (2) it permits monitoring of the filter system. The “B kit” is the actual interchangeable filter. The filtration system, therefore, requires both an “A kit” and a “B kit.”
Pursuant to a previously awarded contract, No. DAAH23-02-C-0006 (Blackhawk Production Contract), Sikorsky Aircraft Company (Sikorsky) is responsible for designing, developing and manufacturing the UH-60 Blackhawk helicopter. On July 23, 2003, under a different contract, Sikorsky was directed to conduct an engine filtration trade study. The trade study contemplated that Sikorsky would evaluate, in addition to two concepts chosen at its discretion, a design concept developed by Aerospace Filtration Systems (AFS), a division of Westar Corporation (Westar). In August 2003, however, the trade study was suspended and Sikorsky was directed to immediately begin incorporating the AFS design.
The parties contest two factual aspects of the August 2003 decision. First, the parties dispute whether Sikorsky was specifically directed to use the AFS design. In this regard, while the December 2003 contract modification does not expressly acknowledge such a requirement, two separate statements in the administrative record lead to an opposite conclusion.
October 2003 proved to be an extremely important month in the context of this procurement. On October 9, 2003, a directive was issued in which the Army concluded that “installation of BLACK HAWK main engine barrier filters was required for ... deployment not later than [March 2004] to ensure required readiness in theater.”
The Army invoked the unusual and compelling urgency exception to full and open competition to procure the IBFs.
As these events occurred, antecedent and parallel events giving rise to plaintiffs OCI claim were also taking form. In May 2000, Westar was the recipient of an Omnibus 2000 contract (02K). Under the contract’s Statement of Work, Westar was responsible for performing systems engineering and technical direction (SETA) tasks.
In a report dated May 16, 2003, Westar noted that it had “[pjrepared for and participated in meetings to generate Propulsion-related project ideas. Explored Westar capabilities and problem areas in the Army aircraft fleet to plan future projects.”
Returning to the fall of 2003, the various COs’ actions in response to OCI concerns warrant attention. After the trade study was suspended in August 2003, a CO for the 02K apparently recognized the conflict and sought to implement precautionary measures. The extent of the CO’s actions are reflected in the administrative record through two unsigned and unapproved mitigation plans.
On December 15, 2003, the Army executed a contract modification to Sikorsky’s Black-hawk Production Contract and procured, inter alia, 183 “A kits” and 150 B kits.
Prior to the December 15, 2003, contract modification being finalized, plaintiff had met with Army officials on several occasions to express its interest in providing IBF systems for the UH-60 Blackhawk helicopter. Despite the inquiries, meetings, phone calls, and emails, its efforts were to no avail. Plaintiff filed suit in this court on December 18, 2003. The court immediately placed the matter on an expedited schedule. After the parties completed their briefings, the court held oral argument on defendant’s motion to dismiss for failure to state a claim upon which relief can be granted. Given the need for an expeditious resolution of the matter, defendant filed the administrative record on January 28, 2004. On February 2, 2004, the court denied defendant’s motion to dismiss reasoning that it could exercise jurisdiction over plaintiffs allegations of procedural violations of CICA as well as OCI regulations. Defendant supplemented the administrative record on February 24, 2004. The parties filed simultaneous cross-motions for judgment on the administrative record on February 26, 2004. The parties filed their responses on March 4, 2004, and their replies on March 11, 2004. The court held oral argument on March 31, 2004.
In the interim, on March 2, 2004, plaintiff filed an amended complaint. In its prayer for relief, plaintiff, in pertinent part, asks the court for: (1) declaratory judgment that the procurement was in contravention of law and regulation; (2) permanent injunction limiting the current procurement to only the minimum amount necessary to satisfy the current emergency situation; (3) permanent injunction directing defendant to procure any amount over the minimum on a competitive basis; (4) permanent injunction preventing defendant or Sikorsky from awarding any subsequent contracts to either Westar or its affiliates for a time period no shorter than the duration of Westar’s current 02K; and (5) permanent injunction precluding AFS from participating in the re-instituted trade study.
Discussion
Motions for judgment on the administrative record are treated in accordance with the rules governing motions for summary judgment. RCFC 56.1; see Nickerson v. United States,
The party moving for summary judgment bears the initial burden of demonstrating the absence of any genuine issues of material fact. Celotex Corp. v. Catrett,
The fact that both parties have moved for summary judgment does not relieve the court of its responsibility to determine the appropriateness of summary disposition. Prineville Sawmill Co., Inc. v. United States,
Congress amended the Tucker Act in 1996 by granting this court jurisdiction to hear post-award bid protest actions. 28 U.S.C. § 1491(b)(4). The court reviews the challenged agency decisions according to the standards set out in the Administrative Procedures Act (APA), 5 U.S.C. § 706. Impresa Construzioni Geom. Domenico Garufi v. United States,
In determining whether the agency has acted arbitrarily and capriciously toward plaintiff, the court must consider four factors. Keco Indus., Inc. v. United States,
When reviewing agency action, the APA requires a “thorough, probing, in-depth review” to determine “whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment.” Citizens to Preserve Overton Park, Inc. v. Volpe,
The “disappointed bidder bears a ‘heavy burden’ of showing that the award decision ‘had no rational basis.’ ” Impresa,
I. Organizational Conflict of Interest
Plaintiff advances a litany of arguments purporting to demonstrate violations of OCI regulations. Plaintiff maintains that the CO failed to adhere to procedural requirements. Plaintiff asserts that the CO did not take any actions to address the OCI until after plaintiffs counsel brought the issue to her attention. Plaintiff contends that the CO’s determination that no significant potential OCI existed was unreasonable. Further, plaintiff avers that the CO cannot abdicate her responsibilities under the Federal Acquisition Regulations (FAR) simply because government personnel represented that the conflict had been addressed through the submission of mitigation plans. In this regard, plaintiff maintains that the mitigation plans were inadequate and that there is no evidence that the mitigation plans were executed. Building upon its argument that a significant OCI existed, plaintiff contends that the CO failed to obtain approval for a mitigation plan from the appropriate personnel.
Defendant asserts that the CO fully complied with her responsibilities under the FAR. Defendant contends that the CO was only required to act before the time of contract award, which she did. Defendant maintains that the CO properly consulted government personnel first in examining a possible conflict. Defendant also avers that because the government personnel had implemented appropriate precautionary measures, the CO’s conclusion that no significant conflict of interest existed was reasonable. Further, defendant asserts that once the CO determined that no significant OCI was present, no further action was required on her part.
The responsibility for ascertaining whether an actual or potential conflict of interest exists generally rests with the CO. 48 C.F.R. § 9.504(a). The CO is instructed to “[i]dentify and evaluate potential organizational conflict of interest as early in the acquisition process as possible ----” Id. § 9.504(a)(1) (emphasis added). For assistance in making this determination, the CO “should obtain the advice of counsel and the assistance of appropriate technical specialists ....’’Id. § 9.504(b); see also id. § 9.506(a) (explaining that the CO “first should seek the information from within the Government ...”). The CO is not required to take additional steps if there is a determination that no significant conflict exists. Id. § 9.506(b); see also id. § 9.504(d) (“The [CO’s] judgment need be formally documented only when a substantive issue concerning potential [OCIs] exists.”). If the CO determines that a significant potential OCI may be present, however, certain steps must be taken before a solicitation is issued. Id. § 9.506(b). Amongst these steps, the CO must proffer a “recommended course of action for avoiding, neutralizing, or mitigating the conflict” to the head of the contracting activity or the chief of the contracting office. Id. § 9.506(b)(1); see also id. § 9.504(c). The conflict must be resolved in the appropriate fashion prior to the contract being awarded. Id. §§ 9.506(d)(3), 9.504(a)(2); see also LeBoeuf Lamb, Greene & MacRae, LLP v. Abraham,
The identification of the OCI in this case did not occur “as early in the acquisition process as possible ____” 48 C.F.R. § 9.504(a)(1). There was no recognition of any conflict in May 2003 when the Army began its discussions with AFS, despite clear signs that AFS was a division of Westar.
The CO’s determination that a significant OCI did not exist is contradicted by the record. The CO did properly contact other government personnel to apprise her of the situation. 48 C.F.R. § 9.506(a). Those personnel informed her that they recognized the potential for a conflict of interest.
Plaintiff also maintains that Westar, through AFS, is precluded from providing the IBF kits because Westar provides SETA services under its 02K. Plaintiff contends that Westar possesses an unfair competitive advantage through its access to information not available to other bidders, in particular source selection information. Further, plaintiff avers a significant OCI exists in light of Westar’s vested interest in having AFS supply the IBF kits. Plaintiff also asserts that prejudice is presumed upon a finding of an actual OCI.
Defendant avers that there is no significant OCI because Westar never actually performed any work under either the 02K or the task orders in connection with the UH-60 Blackhawk helicopter or its propulsion system. Relying on the same line of reasoning, defendant argues that an actual OCI did not arise. Defendant also maintains that plaintiffs “unfair competitive advantage” argument is based on nothing more than speculation and borders on frivolous.
Given the “highly influential and responsible position” of contractors performing systems engineering and technical direction, 48 C.F.R. § 9.505-l(b), the FAR contains the following explicit prohibition:
A contractor that provides systems engineering and technical direction for a system but does not have overall contractual responsibility for its development, its integration, assembly, and checkout, or its production shall not (1) be awarded a contract to supply the system or any of its major*379 components or (2) be a subcontractor or consultant to a supplier of the system or any of its major components.
Id. § 9.505-l(a) (emphasis added); see also Vantage Assocs., Inc. v. United States,
The FAR prohibits a SETA contractor, as either a prime contractor or a subcontractor, from supplying any of the system’s major components, without regard to whether work was performed as to that particular component. 48 C.F.R. § 9.508(a). The FAR’s prohibition is clarified in the following illuminating example: “Company A agrees to provide systems engineering and technical direction for the Navy on the powerplant for a group of submarines____Company A should not be allowed to supply any powerplant components.” 48 C.F.R. § 9.508(a) (emphasis added). Westar agreed to provide SETA services concerning UH-60 propulsion systems under its 02K.
Plaintiff is, therefore, entitled to benefit from the presumption of harm/prejudice. Id. at 12,
Several of plaintiffs remaining contentions deserve attention. First, plaintiff alleges that an OCI exists because of Westar’s vested interest in ensuring that AFS remains a financially sound institution and because of the possibility that Westar obtained information from the Army that was not available to other bidders. Plaintiffs allegations appear to be considerations that would be encompassed within 48 C.F.R. § 9.505-l(a). These concerns would be present in any instance where a contractor is providing SETA services and an affiliate at the same time provides the underlying major component.
Second, the court does not believe that plaintiff has satisfied 48 C.F.R. § 9.505(b)(1)-(2). The United States Court of Appeals for the Federal Circuit (Federal Circuit) has made clear that conflict violations must be established through “hard facts.” CACI, Inc.-Fed. v. United States,
II. Unusual and Compelling Urgency
Plaintiff asserts that defendant improperly invoked CICA’s unusual and compelling urgency exception. Plaintiff maintains that the actual reasons behind the exception’s invocation were a lack of advance planning and funding concerns. Plaintiff avers that the J & A does not adequately justify a sole source award to AFS. Further, plaintiff contends that the J & A does not adequately address the harm to the government. Plaintiff also questions the timing of the J & A. In addition, plaintiff asserts that defendant did not “request [offers] from as many potential sources as is practicable under the circumstances.”
Defendant asserts that plaintiff conceded in its complaint that there is an urgent need for the filters. Defendant nevertheless maintains that the current emergency was caused by the harsh desert conditions encountered in Operation Iraqi Freedom. Defendant also avers that the J & A was approved in a timely fashion. In addition, defendant contends that the substance of the J & A adequately addresses the need for the filters and the possible harm from any delay in procurement. Defendant also asserts that it was impracticable to seeks offers from other sources given the time constraints and Sikorsky’s qualifications. Defendant maintains that authorization for the procurement of 240 IBF kits is based on an estimate of the number of aircraft to be deployed in the next troop rotation and, therefore, does not exceed the minimum amount necessary to satisfy the current emergency. Defendant also maintains that the full amount of funding for
CICA requires an agency to conduct its procurements through “full and open competition.” 10 U.S.C. § 2304(a)(1)(A). As with most rules, the mandate is not absolute and is subject to several exceptions. Most pertinent to the present controversy is the unusual and compelling urgency exception. Id. § 2304(c)(2). Specifically, the exception reads as follows:
The head of an agency may use procedures other than competitive procedures only when ... (2) the agency’s need for the property or services is of such an unusual and compelling urgency that the United States would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals.
Id.; 48 C.F.R. § 6.302-2(a)(2). Noticeably, the provision only allows an agency the option of “limit[ing] the number of sources;” it does not permit the agency to simply disregard competition. The preference for optimizing competition is further reiterated in § 2304(e), which provides, in pertinent part, that “[t]he head of an agency using procedures other than competitive procedures ... by reason of the application of subsection (c)(2) ... shall request offers from as many potential sources as is practicable under the circumstances.” 10 U.S.C. § 2304(e); 48 C.F.R. §§ 6.301(d), 6.303-2(c)(2); see also Aero Corp. v. Dep’t of the Navy,
Several inherent limitations as to scope and duration have also been acknowledged. The court has recognized that “the agency [must] take reasonable steps to accurately determine its needs and describe them.” Filtration Dev. Co., LLC v. United States,
At the outset, plaintiff indicates in its reply brief that “[n]ever has [plaintiff] questioned that the Army has a need to equip the UH-60 aircraft in Iraq with IBF kits.”
Assuming arguendo that plaintiffs concession somehow does not extend to arguments concerning “lack of advance planning” and “funding concerns,” the court rejects those arguments on the merits. Plaintiff main
In addition, “funding concerns,” as contemplated by the FAR, did not drive the invocation of the exception. The J & A states that the Army expended $300 million to remove and replace approximately 400 engines.
Plaintiff argues more forcefully that the Army failed to “request offers from as many potential sources as is practicable under the circumstances.” 10 U.S.C. § 2304(e). Defendant counters that the urgent time constraints coupled with Sikorsky’s qualifications made it impracticable to seek offers from other sources. Stated another way, defendant avers that its conclusion that Sikorsky was the only source capable of meeting its requirements was reasonable. Defendant maintains that it only selected Sikorsky and, in turn, Sikorsky independently selected AFS. Plaintiff, on the other hand, asserts that the Army should not be permitted to hide behind its prime contractor.
While the contract modification did not specifically direct Sikorsky to utilize AFS’s design, the administrative record in two separate instances provides that Sikorsky was directed to incorporate AFS’s design in August 2003.
Plaintiff does not contest Sikorsky’s qualifications,
On the other hand, the court can conclude that the Army has “[taken] reasonable steps to accurately determine its needs and describe them.” Filtration,
A subtle distinction, however, must be drawn between the Army’s overall needs and the needs necessary to satisfy the current emergency. Although some leeway must be factored into the equation, the Army’s December 15, 2003, procurement must reflect its immediate emergency need and must be temporally limited. Filtration,
III. Permanent Injunction
To obtain injunctive relief, plaintiff must succeed on the merits and prove that: (1) it will suffer irreparable harm if the injunction is not awarded; (2) granting relief serves the public interest; and (3) the harm it will suffer outweighs the harm to the government and third parties. Computer Sciences Corp. v. United States,
Plaintiffs request for injunctive relief falls into two categories. The first category of injunctive relief deals with enjoining the procurement of any IBF kits above the number for which funding is currently available, and directing that the procurement of any IBF kits over that number be conducted on a competitive basis. The second category involves future events and procurements. In particular, plaintiff seeks an injunction preventing Westar or any of its affiliates from being awarded a filter contract as long as Westar is providing SETA services, and an injunction prohibiting AFS from participating in the re-instituted trade study.
A. Actual Success on the Merits
Plaintiff has demonstrated actual success on the merits. There is no need in this subsection to expand on the parties’ arguments as they merely offer an abbreviated synopsis of their substantive contentions. Defendant, in its procurement of IBF kits, did not adhere to OCI requirements. The CO improperly usurped the authority granted to the chief of the contracting office. Lacking his approval or his signature, the proposed mitigation plans cannot be given binding effect. An actual OCI exists because of Westar’s 02K work. Moreover, defendant has exceeded the permissible bounds of the unusual and compelling urgency exception. As evidenced in the J & A, the Army may indeed have concluded that its overall needs encompassed 240 IBF kits. The Army’s true emergency needs are discerned from within the procurement; the most recent delivery schedule extends only until July 2004 and the most recent allocation of funds only contemplates the procurement of 183 “A kits” and 150 “B kits.” Accordingly, the resolution of this factor weighs in plaintiffs favor.
B. Irreparable Harm
Plaintiff asserts that it has demonstrated irreparable harm because it was not permitted to compete for the IBF kits. Plaintiff also maintains that it was deprived of lost profits. Further, plaintiff contends that its irreparable harm will be compounded because this procurement will provide AFS with an advantage in the procurement for the fully qualified IBF kits. Plaintiff also avers that Westar continues to occupy a highly influential position.
Defendant asserts that plaintiff will not be irreparably harmed because the current procurement is only a temporary solution. Defendant maintains that the IBF kits installed under an airworthiness release will be removed after the completion of military operations and that the engines will be returned to their original configuration. Defendant also contends that plaintiff will be able to participate in the re-instituted trade study and will have an opportunity to compete for the fully qualified IBF system.
The court has held that the opportunity to compete for a contract and to secure any resulting profits generally has been recog
C. Balance of Harm & Public Interest
The public interest factor, not surprisingly, was the most heavily contested by the parties. Plaintiff asserts that the public has an interest in ensuring that government procurements are conducted in an open and fair fashion. Plaintiff also maintains that the public has an interest in “minimizing the costs of federal procurements.”
Defendant maintains that the procurement was conducted fairly and in accordance with statutory and regulatory provisions. Defendant also avers that the cost of competition as well as the cost associated with any delay would dramatically increase the cost of the procurement. Lastly, but most importantly, defendant contends that an injunction would have an adverse impact on national defense. In particular, defendant avers that an injunction would result in delay and disruption as well as compromise military performance and readiness.
The Tucker Act instructs the court to “give due regard to the interests of national defense and national security” when considering bid protests. 28 U.S.C. § 1491(b)(3). The court proceeds well aware that it “must give serious consideration to national defense concerns and arguably should err on the side of caution when such vital interests are at stake, [but that] allegations involving national security must be evaluated with the same analytical rigor as other allegations of potential harm to parties or to the public.” ATA,
The record contains evidence that the driving force behind the procurement was both national defense needs and financial concerns. In the brief period since operations in Iraq began, the Army has expended approximately $300 million to remove and replace 400 engines.
The recognition that the IBF kits are necessary to ensure combat readiness does not stem solely from defendant’s correspondence, an Army directive, and the J & A. Prior to this suit being filed, plaintiff acknowledged that “[ajside from the obvious advantages, it would seem also prudent for the the [sic] Government to evaluate several alternative solutions (such as FDC’s design), considering the fact that the overall design is critical to flight performance, mission safety/reliability, maintainability, and costs.”
Plaintiff attempts to analogize its situation to cases which plaintiff asserts lacked “ ‘true’ national security considerations.”
On the other hand, plaintiff fails to provide a substantive basis on which to distinguish bid protest decisions where genuine national defense considerations have been raised. In CSE, this court refused to issue an injunction where the Army argued that upgrading two firing ranges in Missouri was critical to training soldiers under modern standards. CSE Constr. Co., Inc. v. United States,
The case before the court likewise raises national defense considerations which lead to the same conclusion. At this juncture, it is important to keep in mind that plaintiff must show its entitlement to the extraordinary remedy of injunctive relief by clear and convincing evidence. CACI, 719 F.2d at 1581; Cincom,
The obvious and unavoidable conclusion which follows from these facts is that a failure to immediately meet the demand would jeopardize the helicopters availability to provide critical support to Army operations. The Army should not be placed in a compromising position that would require it to operate the helicopters with deteriorated and corroded replacement engines that have been subjected to the abusive wear and tear of desert terrain. The Army is unquestionably entitled to the means to operate its combat zone helicopters at peak performance levels. Upon reviewing the arguments that plaintiff proffers to support its position against this backdrop, and “giv[ing] due regard to the interests of national defense,” the court holds that this factor weighs heavily in defendant’s favor; so much so, it conclusively tilts the scale against granting permanent injunctive relief for the 183 “A kits” and 150 “B kits” for which funding has been allocated and a delivery schedule has been set.
The court, however, reaches a contrary conclusion with respect to any kits in excess of 183 “A kits” and 150 “B kits.” From the record, it is unascertainable whether and when funding for the additional kits will be available and when the kits would be delivered. Defendant represented at oral argument that the cost of procuring 183 “A kits” and 150 “B kits” has decreased to approximately $30 million.
Defendant should not be permitted to extend the current emergency indefinitely. More than half a year has passed since Sikorsky was directed to incorporate AFS’s design. It is unclear if any additional steps, besides representations that a trade study for fully qualified IBF kits will be conducted, have been taken to promote competition. The court will take the opportunity to endorse, and ensure compliance with the proposition that “[cjontracting officials must act affirmatively to obtain and safeguard competition; they cannot take a passive approach and remain in a noncompetitive position where they could reasonably take steps to enhance competition.” Matter of: Signals & Sys., Inc., B-288107, 2001 CPD If 168, at 12,
Lastly, the court declines to enter a permanent injunction precluding AFS from future competition for engine filters. Defendant argues that the court’s review in bid protest cases is limited to applying the APA standard of review to the administrative record. Defendant, however, overlooks the fact that the basis for the future injunction would be a finding that the current procurement created an OCI on a future acquisition. The FAR expressly contemplates such review and indicates that “some restrictions on future activities of the contractor may be required.” 48 C.F.R. § 9.502(c). Nevertheless, this is not the only provision in the FAR which guides the resolution of the issue. The FAR provides the following instruction: “[ejach individual contracting situation should be examined on the basis of its particular facts and the nature of the proposed contract.” Id. § 9.505. Further, the FAR permits the CO, after finding that it is in the best interest of the United States to do so, to award the contract despite the OCI upon obtaining a waiver from the head of the agency or a designee. Id. §§ 9.503, 9.504(e). Given that the court can envision a situation where such an option could be exercised, a permanent injunction excluding AFS from the re-instituted trade study and from future competition is inappropriate.
Conclusion
For the above-stated reasons, plaintiff has shown that the Army violated OCI regulations and exceeded the permissible bounds of 10 U.S.C. § 2304(c)(2). In light of plaintiffs burden of demonstrating its entitlement to the extraordinary remedy of permanent injunctive relief by clear and convincing evidence, and after “giv[ing] due regard to the interests of national defense and national security” as required by 28 U.S.C. § 1491(b)(3), the following is hereby ordered:
1) Defendant is entitled to procure 183 “A kits” and 150 “B kits” under its current invocation of the unusual and compelling urgency exception;
2) Any procurement in excess of 183 “A kits” and 150 “B kits” must be conducted on a competitive basis unless an independent justification for invoking an exception to full and open competition is provided;
3) AFS will not be enjoined from participating in the re-instituted trade study or from participating in future competition.
The parties’ cross-motions for judgment on the administrative record are GRANTED to the extent stated above, and otherwise DENIED. The Clerk of the Court is hereby directed to enter judgment in accordance with this opinion.
The parties shall notify the court by Monday, April 26, 2004, of any portion of the opinion containing proprietary information, national defense or national security concerns, or classified information, that should be redacted prior to publication. The parties shall also file with the court any proposed entitlement to costs by said date.
IT IS SO ORDERED.
Notes
. The facts of this case were discussed in detail in the court's previous opinion on defendant’s motion to dismiss. See Filtration Dev. Co., LLC v. United States,
. Administrative Record (AR) Exhibit (Ex.) A H 3; AR Ex. O at 2.
. Supplemental Administrative Record (SUP AR) at 0003.
. AREx.AH 3.
. Id. Ex. C H 4.
. Id. Ex. C K 3.
. Id. Ex. C 11 5(d).
. Id. Ex. C H 7.
. Id. Ex. S 112.0 (General Technical Requirements), H 3.19 (Systems Engineering).
. Id. Ex. S H3.17.
. Compare Plaintiff's Statement Of Facts H 46 with Defendant’s Counter-Statement Of Facts H 46.
. Defendant’s Counter-Statement Of Facts VH 38-40; see AR Ex. Y.
. SUP AR 0086.
. Id. 0015-0033.
. Id. 0133-0140, 0142-0147.
. AREx.K.
. Transcript of Oral Argument (Tr.) at 38-3 9.
. Id.
. Amended Complaint (Amend.Compl.) at 17.
. SUP AR 0015-0033.
. AREx. At 3.
. SUP AR 0001.
. AREx.Y.
. Id. Ex. S H 3.17; Id. Ex. V 113.2.2.
. SUP AR 0086.
. Id. at 0085.
. Id. at 0091.
. Decisions of the Comptroller General in procurement cases are not binding on this court, nevertheless, the court may consider and adopt their reasoning in recognition of the Comptroller General’s expertise and role in the resolution of contested procurement decisions. Computer Sciences Corp. v. United States,
. Consistent with the court's holding concerning the presumption of prejudice, "hard facts” are only required to "establish the existence of the [OCI], [but] not the specific impact of that conflict.” Aetna, B-254397.15, 95-2 CPD 11129, at 18,
. Plaintiff Filtration Development Company's Motion For Judgment On The Administrative Record (Pl.’s Mot.) at 15.
. Id. at 25 (quoting 10 U.S.C. § 2304(e)).
. Id. (quoting Matter of: Signals & Sys., Inc., B-288107, 2001 CPD H168, at 12,
. Plaintiff Filtration Development Company's Reply Brief In Support Of Its Motion For Judgment On The Administrative Record (Pl.'s Reply) at 1.
. Amend. Compl. t 3; see also Tr. at 15-16.
. AR Ex. EH 1.1(a).
. The court also finds that this monetary justification is sufficient in and of itself to justify the invocation of the exception and to demonstrate harm to the government. 48 C.F.R. § 6.302-2(a)(2) ("delay in award of a contract would result in serious injury, financial or otherwise, to the Government.” (emphasis added)); see also id. § 6.303 — 2(a)(9)(iii).
. SUP AR 0003.
. AR Ex. A H 3; Id. Ex. O at 2.
. PL's Reply Brief at 10.
. See AR Ex. A H 3; see also id. Ex. O at 2.
. Id. Ex. A 114.
. Id. Ex. C If 9(b).
. Id. Ex. C 1110(a); SUP AR 0003.
. AREx. AH7.
. Tr. at 47.
. AREx. K.
. Tr. at 21, 29.
. At oral argument, it was brought to the court's attention that plaintiff was only interested in providing "B kits.” Id. at 43. Although the court sought clarification on this point, plaintiff’s counsel could only assure the court of his "understfanding]” that plaintiff would provide both the "A kits” and the “B kits.” Id. at 53.
. Plaintiff Filtration Development Company’s Opposition To Defendant’s Cross-Motion For Judgment On The Administrative Record at 16 (citing Vanguard Sec. Inc. v. United States,
. AR Ex. C 115(d).
. Id. Ex. O at 1.
. Id.
. SUP AR 0003 (emphasis added).
. AR Ex. C 119(b) (emphasis added).
. SUP AR 0034 (emphasis added).
. Pl.’s Mot. at 38.
. Tr. at 44.
. Id. at 37.
. Id. at 40.
