FILCEK v UTICA BUILDING COMPANY
Docket No. 58064
Court of Appeals of Michigan
Submitted June 8, 1982. — Decided January 3, 1984.
131 Mich App 396
Held:
The limitation period for a negligence claim begins to run when the claim accrues. A claim accrues when all of the elements of the cause of action have occurred and can be pled in a proper complaint. Where an element, such as damages, has occurred but is not discoverable, the claim has not accrued. The claim accrues, and the limitation period begins to run, when the damages are, or with reasonable diligence should be, discovered. The determination of when the plaintiffs’ claim accrued is for the trier of fact, and accelerated judgment was improper.
Reversed and remanded.
P. R. JOSLYN, J., dissented. He would hold that, pursuant to statute, a claim such as the one herein accrues when the wrong is done, regardless of the time when damage results, and that the plaintiffs’ claim was therefore barred by the statute of limitations. He would affirm.
REFERENCES FOR POINTS IN HEADNOTES
[1] 51 Am Jur 2d, Limitation of Actions § 135.
[2] 13 Am Jur 2d, Building and Construction Contracts §§ 27, 138.
[3] 13 Am Jur 2d, Building and Construction Contracts § 114.
What statute of limitations governs action by contractee for defective or improper performance of work by private building contractor. 1 ALR3d 914.
1. TORTS — LIMITATION OF ACTIONS — ACCRUAL OF CLAIM.
The limitation period on a cause of action in tort does not begin to run until all of the elements of the cause of action have occurred and can be pled in a proper complaint; thus, where an element of the cause of action, such as damages, has occurred but cannot be discovered until sometime after it has occurred, the period of limitation begins to run at such time as that element is, or with reasonable diligence should be, discovered (
2. TORTS — NEGLIGENCE — CONSTRUCTION OF BUILDING — ELEMENTS OF CLAIM.
The elements of a cause of action for negligent construction of a building are: (1) the existence of a duty owed by the builder to the owner or to any of the owner‘s predecessors-in-interest, (2) to exercise due care in the construction, and (3) a breach of that duty which (4) proximately caused (5) damages to the owner or any of the owner‘s predecessors-in-interest.
DISSENT BY P. R. JOSLYN, J.
3. TORTS — LIMITATION OF ACTIONS — ACCRUAL OF CLAIM.
The period of limitation for an action for the negligent construction of a building is three years; such a cause of action accrues not when the damage is discovered but at the time when the wrong upon which the claim is based was done regardless of the time when the damage results (
Roesch, Schaberg & Baker (by Basil A. Baker), for plaintiffs.
Terry J. Nosan, for defendant.
Before: M. J. KELLY, P.J., and M. F. CAVANAGH and P. R. JOSLYN,* JJ.
PER CURIAM. In 1966, defendant constructed a house. Plaintiffs became remote purchasers of that house in July, 1977, i.e., there were at least two previous owners. Shortly after their purchase,
* Circuit judge, sitting on the Court of Appeals by assignment.
The trial court erred by granting accelerated judgment in favor of defendant. Plaintiffs’ tort claim for negligent construction is a viable one. The statute involved in this case,
“Sec. 5827. Except as otherwise expressly provided, the period of limitations runs from the time the claim accrues. The claim accrues at the time provided in sections 5829 to 5838, and in cases not covered by these sections the claim accrues at the time the wrong upon which the claim is based was done regardless of the time when damage results.”
At first glance, it appears that, pursuant to the foregoing statute, the wrong occurred when the house was built in 1966 and that the damage did not result, at the earliest, until plaintiffs purchased the house in 1977. Thus, it would seem that plaintiffs’ claim is time-barred.
However, the Supreme Court has interpreted
In this case, plaintiffs allege negligent construction. The elements of that action are: (1) the existence of a duty owed by defendant to plaintiffs
Since the final element to have occurred in this case was the property damage and since such damage is not always discoverable at the time it first occurs, the three-year limitation period began to run when that property damage was or with reasonable diligence should have been discovered. For example, if the damage was not discovered and could not reasonably have been discovered until after plaintiffs took possession of the house, then the three-year period of limitations began running at that time and plaintiffs’ action is not barred. On the other hand, if the damage was or with reasonable diligence should have been discovered prior to March 20, 1976, and plaintiffs’ predecessors-in-interest simply failed to institute any legal action against defendant, then plaintiffs’ cause of action is barred by the three-year statute of limitations. However, in both cases, the determination of when the limitations period commenced is for the trier of fact. Bonney, supra.
Reversed and remanded for further proceedings.
P. R. JOSLYN, J. (dissenting). I respectfully dissent. The Legislature has the power to limit the period in which a cause of action may be brought. The Legislature has determined that the proper period in this case is three years.
Plaintiffs claim damages as a result of the negligent construction of the footings to the house they purchased in 1977. The claimed negligence is the pouring or installation of the footings, apparently underneath the fireplace and chimney. Plaintiffs allege that the footings were only 24” below grade and should have been installed at 48” below grade, and that as a result of the defendant‘s negligent installation of the footings in 1966 the fireplace and chimney have been replaced and other damage to the dwelling has occurred and may continue into the future.
The trial court granted defendant‘s motion for accelerated judgment holding that the action was time barred and that the cause of action accrued when the footings were installed. The circuit court affirmed. It is my opinion that the granting of the motion for accelerated judgment was correct and should be affirmed.
The purpose of legislation rendering stale claims unenforceable is to protect the fact-finding process from risk of error in making decisions on the merits. Faulty decisions occur from the difficulty of obtaining reliable evidence of events and circumstances which prevailed in the remote past. Decisions which are based upon stale claims will result in the reduction of the validity of the result. Facts presented from more recent transactions are generally more reliable than facts presented from more remote times. The two opinions that hold that a cause of action accrues when damage re-
No one suffered any injury to their person on this claim, therefore, Connelly v Paul Ruddy‘s Equipment Repair & Service Co, 388 Mich 146; 200 NW2d 70 (1972), does not apply. It is easy to see that a cause of action could be pled and filed by any interested party the day the forms were removed from the footings. A more correct interpretation of the statute on an injury to property is reflected in Cree Coaches, Inc v Panel Suppliers, Inc, 23 Mich App 67; 178 NW2d 101 (1970), and H Hirschfield Sons Co v Colt Industries Operating Corp, 107 Mich App 720; 309 NW2d 714 (1981).
