History
  • No items yet
midpage
Field Intelligence Inc v. Xylem Dewatering Solutions Inc
49f4th351
3rd Cir.
2022
Check Treatment
Docket
Case Information

*1 Before: AMBRO, BIBAS, and ROTH, Circuit Judges (Opinion filed: September 13, 2022) *2 Christopher Larus Benjamen C. Linden Rajin S. Olson David A. Prange (Argued) Robins Kaplan 800 LaSalle Avenue 2800 LaSalle Plaza Minneapolis, MN 55402

Counsel for Appellant Aaron M. Frankel (Argued) Kramer Levin Naftalis & Frankel 1177 Avenue of the Americas New York, NY 10036

Counsel for Appellee _________ OPINION OF THE COURT ____________

AMBRO, Circuit Judge

Two companies, Xylem Dewatering Solutions and Field Intelligence, entered into two contracts. The first contained an

arbitration provision; the second required the parties to litigate

their disputes. As sure as Camille coughing in the first scene

and dying of consumption in the last, a conflict arose between

the businesses. Field Intelligence filed suit in federal court

alleging a breach of their second agreement. Xylem,

unconvinced that Field Intelligence’s lawsuit did not implicate

the parties’ first contract, filed an arbitration demand and

moved to stay the federal litigation pending the outcome of the

arbitration.

Field Intelligence protested. It asked the District Court to hold that the parties’ second contract superseded the first

such that the arbitration provision contained in that earlier

agreement was no longer in effect. While disputing this

interpretation of the contracts, Xylem responded that Field

Intelligence’s supersession challenge could, per the first

contract’s arbitration provision, only be decided by an

arbitrator. The Court disagreed. It held, first, that it had

authority to decide the supersession issue and, second, that the

parties’ later agreement did supersede their earlier contract,

thereby eliminating any duty to arbitrate. Xylem appeals both

rulings.

We agree with the District Court that it was authorized to determine whether the parties’ second agreement

superseded, and hence replaced, their first. But we disagree

that the first agreement was superseded. We therefore reverse

in part, vacate in part, and remand for further proceedings.

I. Background Xylem is a water technology company that manufactures and sells large-capacity water pumps. It wanted

a better way for its customers to monitor those pumps

remotely. In 2012 it called on Field Intelligence to develop a

custom telematics solution that would consist of hardware built

to interface with the pumps (“Hardware Units” or “Units”), and

computer software and support services for monitoring and

controlling the equipment.

Two contracts followed. The first, in 2013, was a “Non- Disclosure Agreement.” It governed the disclosure and

protection of “certain information and related materials” that

the parties considered to be “confidential and secret and in

which each has a proprietary interest” in connection with their

“development of a custom telematics solution.” Appx. 531.

Significantly, the agreement contained an arbitration provision

requiring that any “dispute, controversy or claim arising out of

or in connection with this Agreement, or the breach,

termination or invalidity thereof,” be “settled by arbitration in

accordance with the Rules of the American Arbitration

Association.” Id. at 533.

The parties launched the first-generation Hardware Units shortly thereafter. Second-generation Units became

available around December 2014. Xylem purchased them

from Field Intelligence via written Purchase Orders. It also

purchased monthly subscriptions that permitted Xylem’s

customers to access and use Field Intelligence’s software via

satellite or cellular networks, thereby allowing them to monitor

and control their Xylem pumps using the Hardware Units.

There was no written agreement governing Xylem’s software subscription purchases until 2017, when the parties

signed the second contract relevant to this dispute: the

“Software Subscription Service Agreement.” It states that

Field Intelligence is “the owner of certain proprietary computer

software” and “sells subscriptions for subscribers to access and

use” that software. Id. at 535. The contract allowed Xylem to

access the software via a Field Intelligence-hosted website and

provided subscription terms and monthly fees based on the

number of Hardware Units actively deployed in the field.

The 2017 agreement also contained an “integration clause” (known also as a “merger clause”) stating that “[t]his

Agreement constitutes the entire agreement between the parties

with respect to its subject matter, and supersedes any and all

prior or contemporaneous understandings or agreements

whether written or oral.” Id. at 540. And, unlike its

predecessor, the 2017 contract contained no arbitration

provision, instead requiring any “action under or concerning”

that contract to be litigated in a state or federal court in New

Jersey. Id. at 539.

Eventually, Xylem began building its own hardware.

Suspecting Xylem had developed its product by reverse-

engineering the Units, Field Intelligence sued it for breach of

the 2017 contract, among other things. Per that contract’s

forum-selection provision, Field Intelligence filed its action in

the U.S. District Court for the District of New Jersey. Its

complaint did not mention the 2013 contract, let alone allege

any breach of that first agreement.

Xylem moved to dismiss on the following rationale: Field Intelligence could not maintain its breach-of-contract

claim because, even if Xylem had reverse-engineered the

Hardware Units, the 2017 agreement did not bar it from doing

so. The District Court rejected that interpretation of the

contract and denied Xylem’s motion to dismiss in part.

The parties then moved to discovery. Xylem sent Field Intelligence an interrogatory request asking if it intended to

rely on the parties’ 2013 contract to support any of its claims.

Field Intelligence responded that

Xylem breached the provisions [of the 2013 contract] by copying the design and functionality of the [Hardware Units], modifying [them], using [them] to test and develop Xylem’s knock off designs, sending [them] to APD&M for purposes of developing Xylem’s knock off designs, and not taking reasonable precautions to protect the[ir] confidentiality . . . .

Id. at 827.

A month later, Xylem filed an arbitration demand with the American Arbitration Association seeking various forms of

declaratory relief, including a determination that it did not

breach the 2013 contract. It then moved to stay the federal

litigation pending resolution of the arbitration. It argued that

Field Intelligence’s interrogatory response revealed for the first

time its intent to rely on the 2013 agreement as requiring

Xylem to maintain the confidentiality of the Hardware Units.

Xylem disputed this interpretation, as it maintained that these

questions of contract scope and meaning were not for the

District Court to decide but instead delegated to an arbitrator

under the 2013 contract’s arbitration provision.

Field Intelligence opposed and cross-moved to enjoin the arbitration. Its claim was that the 2017 agreement

superseded the 2013 contract such that the earlier agreement to

arbitrate ceased. The District Court agreed. It held first that

it—rather than an arbitrator—needed to determine whether the

2013 contract was still in effect. Second, it ruled that the 2017

agreement did replace the parties’ 2013 contract, thereby

eliminating any arbitration obligation contained in the prior

agreement. The Court enjoined the arbitration and denied as

moot Xylem’s motion to stay the federal litigation. This appeal

followed.

II. Jurisdiction and Standard of Review The District Court had jurisdiction under 28 U.S.C. §§ 1331 and 1332. Our jurisdiction is under 9 U.S.C.

§ 16(a)(1)(A), which allows us to consider an order refusing a

stay pending arbitration. We review anew (or de novo ) the

District Court’s denial of Xylem’s motion to stay proceedings

pending arbitration. MZM Constr. Co. v. N.J. Bldg. Laborers

Statewide Benefit Funds , 974 F.3d 386, 395 (3d Cir. 2020)

(fresh review where district court has denied a party’s “asserted

right to have [an] issue submitted to arbitration”).

III. Discussion Congress enacted the Federal Arbitration Act, 9 U.S.C.

§ 1 et seq. , “to reverse the longstanding judicial hostility to

arbitration agreements” and place them on “the same footing

as other contracts,” Spinetti v. Serv. Corp. Int’l , 324 F.3d 212,

218 (3d Cir. 2003) (quoting Gilmer v. Interstate/Johnson Lane

Corp. , 500 U.S. 20, 24 (1991)). It “reflects the fundamental

principle that arbitration is a matter of contract.” Rent-A-Ctr.,

W., Inc. v. Jackson , 561 U.S. 63, 67 (2010). Arbitration

agreements are thus “valid, irrevocable, and enforceable, save

upon such grounds as exist at law or in equity for the revocation

of any contract.” 9 U.S.C. § 2. If a court is “satisfied that the

making of the agreement for arbitration . . . is not in issue,” it

must send the parties to an arbitrator. Id. § 4.

Parties may refer more than the merits of their disputes to arbitration. They may also agree to delegate to an arbitrator

“‘gateway’ questions of ‘arbitrability,’ such as whether the

parties have agreed to arbitrate or whether their agreement

covers a particular controversy.” Henry Schein, Inc. v. Archer

& White Sales, Inc. , 139 S. Ct. 524, 529 (2019) (quoting Rent-

A-Ctr. , 561 U.S. at 68–69). This appeal involves such a

threshold question: whether Field Intelligence is bound by the

arbitration provision in the parties’ 2013 contract, or whether

the 2017 agreement superseded that contract completely,

thereby eliminating its duty to arbitrate.

Two issues stem from this gateway concern. First, who should decide whether the second contract replaced the first, a

court or an arbitrator? Second, if a court, rather than an

arbitrator, should decide, does the parties’ 2017 contract in fact

supersede their earlier agreement? Field Intelligence also asks

us to consider a third issue: whether Xylem waived any right

to seek arbitration under the 2013 contract by participating in

this federal litigation. We address each in turn.

A. To the first issue, we hold that the parties’ supersession dispute is for a court, not an arbitrator, to decide. That

conclusion flows necessarily from a first principle of

arbitration law: that “arbitration is strictly a matter of consent.”

Lamps Plus, Inc. v. Varela , 139 S. Ct. 1407, 1415 (2019)

(alteration adopted) (quoting Granite Rock Co. v. Teamsters ,

561 U.S. 287, 299 (2010)). An arbitrator’s authority is limited

to those claims that “the parties have agreed to submit to

arbitration.” First Options of Chi., Inc. v. Kaplan , 514 U.S.

938, 943 (1995); AT&T Techs., Inc. v. Commc’ns Workers of

Am. , 475 U.S. 643, 648–49 (1986). So before sending parties

to an arbitrator, a court must decide whether they agreed to

resolve their dispute in that forum, First Options , 514 U.S. at

943, which in turn requires it to determine “whether an

arbitration agreement exists at all,” Williams v. Medley Opp.

Fund II, LP , 965 F.3d 229, 237 n.7 (3d Cir. 2020) (quoting

Lloyd’s Syndicate 457 v. FloaTEC, L.L.C. , 921 F.3d 508, 515

n.4 (5th Cir. 2019)); Henry Schein , 139 S. Ct. at 530 (“[B]efore

referring a dispute to an arbitrator, the court determines

whether a valid arbitration agreement exists.”). Because the

substance of the parties’ supersession dispute is “whether there

is an agreement to arbitrate,” Jaludi v. Citigroup , 933 F.3d 246,

255 (3d Cir. 2019), the District Court rightly declined to send

it to an arbitrator.

Xylem asks us to view this case differently. It points to the general rule, referenced above, that parties may delegate

threshold arbitrability issues to an arbitrator provided there is

“clear and unmistakable” evidence they agreed to do so. First

Options , 514 U.S. at 944 (alterations adopted) (internal

quotation marks omitted). The 2013 contract’s arbitration

provision, it says, contains such clear and unmistakable

evidence, as it expressly delegates arguments over its

“termination or invalidity” to an arbitrator. Appx. 533. Hence

that person, not a court, must decide the supersession dispute.

Were this fight simply about whether the 2013 agreement had terminated or was invalid, we might agree. But

the question here is whether, by the later contract, the parties

intended to extinguish their prior agreement and litigate any

disputes between them moving forward. Put another way, if

Field Intelligence is correct that the 2017 contract superseded

the 2013 agreement, then there is no arbitration agreement for

us to enforce. And “it can hardly be said that contracting

parties clearly and unmistakably agreed to have an arbitrator

decide the existence of an arbitration agreement when one of

the parties has put the existence of that very agreement in

dispute.” [1] MZM , 974 F.3d at 401; see also McKenzie v.

Brannan , 19 F.4th 8, 18–20 (1st Cir. 2021) (contract delegating

arbitrability issues to an arbitrator cannot provide “clear and

unmistakable” evidence of the parties’ intent if alleged to be

superseded by a later agreement).

Xylem’s arguments to the contrary are unpersuasive. It alludes to the so-called “severability” doctrine, under which an

arbitration provision (including a provision delegating

arbitrability issues to an arbitrator) is severable from the

contract in which it is contained and may be enforced despite

an assertion that the container contract is invalid. Prima Paint

*11 Corp. v. Flood & Conklin Mfg. Co. , 388 U.S. 395, 403–04

(1967); Rent-a-Ctr. , 561 U.S. at 70–71. But we have held that

this doctrine “presumes an underlying, existent[] agreement.”

Sandvik AB v. Advent Int’l Corp. , 220 F.3d 99, 106 (3d Cir.

2000). It does not apply where, as here, the existence of the

parties’ arbitration agreement has been challenged.

We recently reaffirmed this holding in MZM , a case that, like this one, involved a contractual provision purporting

to delegate arbitrability issues to an arbitrator. The dispute

there arose from a one-page, short-form agreement hurriedly

signed between MZM Construction Co. and a local labor

union. 974 F.3d at 392. The short-form agreement

incorporated a separate agreement requiring MZM to make

contributions to the New Jersey Building Laborers’ Statewide

Benefit Funds (the “Funds”). Id. That incorporated agreement

contained an arbitration provision. Id. at 393. When the Funds

learned years later that MZM likely was not contributing the

required amount (which MZM denied), they indicated they

would be submitting the dispute to an arbitrator per that

provision. Id.

MZM sued to enjoin the arbitration. Id. Its claim was

fraud in the execution—that the union misrepresented the

substance of the short-form agreement to obtain MZM’s

consent. Id. at 393–94. Because of this misrepresentation,

MZM argued that agreement was void. Id. The Funds

countered that the Court lacked authority to decide the fraud-

in-the-execution claim under the incorporated agreement’s

arbitration provision, which entitled an arbitrator “to decide

whether an Agreement exists, where that is in dispute.” Id.

We disagreed. Because the Federal Arbitration Act requires courts to compel arbitration only when “satisfied that

the making of the agreement for arbitration . . . is not in issue,”

id. at 397 (alteration in original) (quoting 9 U.S.C. § 4), they—

rather than arbitrators—must “decide questions about the

formation or existence of an arbitration agreement, namely the

element of mutual assent,” id. at 397–98. No doubt parties

may, as a general matter, delegate arbitrability questions to an

arbitrator. But “the legal effect of the delegation must come

from an ‘independent source’ outside the contract whose

formation or existence is being disputed.” Id. at 402 (quoting

Sandvik , 220 F.3d at 108). “[C]ourts retain the primary power

to decide questions of whether the parties mutually assented to

a contract containing or incorporating a[n arbitration]

delegation provision.” Id.

Granted, MZM dealt with issues of contract formation rather than contract supersession. Our parties, by contrast, do

not dispute that the 2013 agreement was valid when executed.

But we think the distinction deserves little weight in this

context. Like a formation dispute, Field Intelligence’s

supersession challenge places the parties’ mutual assent

directly at issue. Its contention is that the parties agreed, by

their 2017 contract, not to submit the dispute before us to an

arbitrator. A court should rule on that issue before referring a

case to arbitration.

To hold otherwise would foster passing strange results.

Xylem asks us to enforce the arbitration provision contained in

the parties’ 2013 contract despite the assertion that it was

extinguished and that the parties instead redefined their

relationship in the 2017 agreement not to include an arbitration

obligation. Were we to do so, parties would never be able to

execute a superseding agreement to rid themselves of a prior

agreement to arbitrate arbitrability. They would forever be

bound by that agreement even if their later dealings show an

intent to avoid it. That in turn would undermine our guiding

principle in the arbitration context: that “no arbitration may be

compelled in the absence of an agreement to arbitrate.”

Sandvik , 220 F.3d at 107–08. We decline to reach such an odd

outcome and instead conclude that the District Court was right

to resolve the supersession issue itself rather than send it to an

arbitrator.

B. Because a court, rather than an arbitrator, must decide whether the parties’ 2017 contract superseded their 2013

agreement, we move now to that issue. They agree that New

Jersey law governs our analysis. Under that law, supersession

is a question of the parties’ intent as discerned “from the

contracts themselves.” Rosenberg v. D. Kaltman & Co. , 101

A.2d 94, 96 (N.J. Super. Ct. Ch. Div. 1953). A later contract

does not supersede an earlier one unless both concern “the

same subject matter” and the later agreement is so

“inconsistent” with the former “that the two cannot stand

together.” Id. ; accord Doyle v. Northrop Corp. , 455 F. Supp.

1318, 1332 (D.N.J. 1978).

According to Field Intelligence, the parties intended the 2017 contract to replace completely their prior agreement, such

that the arbitration obligation imposed by that earlier contract

no longer exists. It relies primarily on the 2017 contract’s

merger provision, which (to repeat) states: “This Agreement

constitutes the entire agreement between the parties with

respect to its subject matter, and supersedes any and all prior

or contemporaneous understandings or agreements whether

written or oral.” Appx. 540. But that statement expressly

limits its effect to prior agreements concerning the same

subject matter as the 2017 contract. So it alone cannot resolve

the parties’ supersession dispute; rather, we must first

determine whether the 2013 and 2017 agreements involve

identical subject matter.

We cannot say they do. The 2013 contract is a “Non- Disclosure Agreement” that applies to the parties’ exchange of

confidential and proprietary information during their

“development of a custom telematics solution.” Appx. 531.

The 2017 contract, by contrast, is a “Software Subscription

Service Agreement,” entered after the telematics solution was

developed, to provide Xylem and its customers access to Field

Intelligence’s software for “monitor[ing] the status and

operation of remotely located machinery.” Appx. 535. And

while that later agreement, like the 2013 one, includes

protections for Field Intelligence’s confidential information,

those protections do not extend to information exchanged

between the parties prior to their execution of the 2017

contract.

Neither are the two agreements so “inconsistent” that they “cannot stand together.” See Rosenberg , 101 A.2d at 96.

The only potential inconsistency between these documents is

their differing dispute-resolution provisions, one of which

provides for arbitration while the other provides for litigation.

But those provisions are reconcilable. Each is expressly

limited to the subject matter of its agreement: the 2013 contract

requires arbitration of disputes “arising out of or in connection

with this Agreement ,” Appx. 533 (emphasis added), whereas

the 2017 contract requires litigation of disputes arising “under

or concerning this Agreement ,” Appx. 539 (emphasis added).

The result: claims involving the first agreement are heard by

an arbitrator, while claims involving the second are heard in

court.

One last note. The 2013 contract states that it “may be modified or waived only by an express amendment and waiver

in writing signed by the Parties.” Appx. 533. Thus, if they

meant to supersede that contract and its arbitration obligation,

we would expect to see some specific language to that effect in

the 2017 agreement. But there is none. The 2017 contract does

not even mention its predecessor, let alone expressly indicate

any intent to replace that earlier agreement. And with no

indication in the 2017 agreement that the parties intended to

replace the 2013 contract, we cannot say it was superseded.

Accordingly, the 2013 contract’s arbitration provision is still

in effect, and Xylem was entitled to arbitrate claims tied to that

agreement.

C. In a final effort to avoid arbitration, Field Intelligence submits Xylem lost its right to seek such relief by engaging in

the federal litigation. We disagree.

A party can waive its ability to arbitrate a claim by litigating it in court. [2] Gray Holdco, Inc. v. Cassady , 654 F.3d

*16 444, 451 (3d Cir. 2011). But, given the “strong preference” for

“enforc[ing] private arbitration agreements,” waiver is not

lightly inferred. Id. The “touchstone” of the inquiry is

prejudice, Ehleiter v. Grapetree Shores, Inc. , 482 F.3d 207,

222 (3d Cir. 2007) (quoting Hoxworth v. Blinder, Robinson &

Co. , 980 F.2d 912, 925 (3d Cir. 1992)), which we assess using

several factors, including the timeliness of the party’s

arbitration demand and the extent to which it has contested the

merits of (and engaged in discovery with respect to) its

arbitrable claims, see Gray Holdco , 654 F.3d at 451;

Hoxworth , 980 F.2d at 926–27 (detailing prejudice inquiry).

There was no prejudice here. Field Intelligence brought its claims under the 2017, not the 2013, agreement. It did not

indicate any intent to raise claims under the earlier contract

until responding to Xylem’s discovery requests. When Xylem

asked if Field Intelligence planned to rely on the parties’ 2013

agreement to support any of its claims, the latter responded by

citing several sections of the 2013 agreement which, in its

view, required Xylem to keep confidential and not copy the

Hardware Units’ design. Following this admission, Xylem did

not delay in asserting its rights under that prior agreement: it

filed its arbitration demand the next month.

Given that Field Intelligence framed its suit around the 2017 agreement, Xylem did not waive its right to pursue

arbitration for claims arising under the 2013 contract merely

by engaging in this litigation. See Forby v. One Techs., L.P. ,

we have no evidence Xylem intentionally abandoned its

arbitration rights. Still, because the distinction does not bear

on our analysis, we proceed based on how the parties have

framed the issue.

13 F.4th 460, 465 (5th Cir. 2021) (“For waiver purposes, ‘a

party only invokes the judicial process to the extent it litigates

a specific claim it subsequently seeks to arbitrate.’” (emphasis

in original) (quoting Subway Equip. Leasing Corp. v. Forte ,

169 F.3d 324, 328 (5th Cir. 1999))). Field Intelligence asserts

harm caused by Xylem’s belated arbitration demand, but as its

lawsuit focuses on an entirely different contract, it can hardly

claim prejudice as to any claims Xylem may bring under the

2013 agreement.

* * * In sum, while we agree with the District Court that it, and not an arbitrator, was required to determine whether the

parties’ first agreement was superseded by their second, we do

not agree that the earlier agreement was in fact superseded.

Because the 2013 agreement still exists, Xylem was entitled to

enforce its arbitration provision as to what that contract covers.

We therefore reverse the Court’s judgment enjoining the

arbitration proceedings. We vacate its judgment as to Xylem’s

motion to stay the federal litigation while arbitration is pending

and remand for it to consider the merits of that motion in light

of our opinion.

[1] Xylem argues that the 2013 agreement’s incorporation of American Arbitration Association rules further indicates an intent to arbitrate gateway arbitrability issues. Although “virtually every circuit to have considered the issue has determined that incorporation of the AAA arbitration rules constitutes clear and unmistakable evidence that the parties agreed to arbitrate arbitrability,” we have yet to decide it in this context. Chesapeake Appalachia, LLC v. Scout Petroleum, LLC , 809 F.3d 746, 763 (3d Cir. 2016) (alterations adopted) (quoting Oracle Am., Inc. v. Myriad Grp. A.G. , 724 F.3d 1069, 1074 (9th Cir. 2013)). We save it again for another day because, as we explain below, even assuming the 2013 contract’s arbitration provision delegates arbitrability issues to an arbitrator, it does not govern this dispute.

[2] There is a distinction between waiver and forfeiture. “Whereas forfeiture is the failure to make the timely assertion of a right, waiver is the intentional relinquishment or abandonment of a known right.” United States v. Brito , 979 F.3d 185, 189 (3d Cir. 2020) (internal quotation marks omitted) (quoting United States v. Olano , 507 U.S. 725, 733 (1993)). We note that this may well be a forfeiture dispute, as

Case Details

Case Name: Field Intelligence Inc v. Xylem Dewatering Solutions Inc
Court Name: Court of Appeals for the Third Circuit
Date Published: Sep 13, 2022
Citation: 49f4th351
Docket Number: 21-2087
Court Abbreviation: 3rd Cir.
Read the detailed case summary
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.