137 F. 866 | 2d Cir. | 1905
This is a writ of error by the defendant in the court below to review a judgment for the plaintiff rendered upon the veydict of a jury.
The action was brought against the defendant as a surety upon a bond executed to the United States by one Conkling, as principal, conditioned for the faithful performance by Conkling of a contract entered into May 18, 1899, between Conkling and the United States. The contract provided that Conkling should remove “the stone owned by the United States, stored on the south side of the cut through Dyckman’s Meadows,” amounting to 235,000 cubic yards, more or less; that he should be paid therefor by the United States at the rate of 22 cents per cubic yard; that he should commence the removal of the stone on or before June 17, 1899, and that he should complete the removal on or before June 11, 1900. It also provided that, in case Conkling should, in the judgment of the engineer in charge for the United States, fail to prosecute faithfully and diligently the work, the government should be at liberty to annul the contract by giving notice to that effect to Conkling.
The following facts appeared upon the trial: The premises upon which the stone was at the date of the making of the con
“I have therefore to request that you resume at once the work and remove the stone under your contract dated May 18, 1898, which was sus- ' pended by you without authority from this office. If work is not commenced promptly, and satisfactory progress is not made, it will be necessary to annul the contract and to proceed to the completion of the work as prescribed therein.”
It further appeared that Conkling did not, after December 1, 1899, attempt to go on with the work of removing the stone, and on May 3, 1900, the government gave him written notice annulling the contract for noncompliance with its terms.
The only assignment of error which we deem it necessary to consider is that based upon the refusal of the court to order a verdict for the defendant. At the close of the evidence the defendant requested that such a verdict be directed upon the ground, among others, that there had been a breach of contract upon the part of the government in permitting the lease to lapse.
Upon the undisputed facts we are of the opinion that the trial judge should have directed a verdict as requested by the defendant, and that the defendant, as a surety, was discharged by the default of the government to remain in lawful possession of the demised premises during the period necessary to enable Conkling to fulfill his contract. The contract by necessary implication included an obligation on the part of the government to permit Conkling to remove the stone, and in this behalf to secure to him the privilege of access to the premises during the necessary period of his performance. It is quite immaterial that this understanding
' “The city had full authority under its organic law to secure the right of way,’ if not already acquired, and by its contract with Murray it impliedly agreed to secure a place for the structure. We know of no reason why the city could not contract for the construction of the viaduct in advance of securing the right of way for its location, just as a railroad company may con'tract for the grading of its roadbed before securing the entire right of way. We hold, then, that Kansas City made a binding contract with Murray, and that by such a contract the city undertook by implication to secure the right of way for the viaduct, and that said city failed to comply with such obligation, and became at the date of such perpetual injunction liable to plaintiff •for damages by him thereby suffered.”
By the law of New York, as at common law, the tenant who holds over after the expiration of his term without the permission of his landlord becomes a trespasser at the election of the landlord, and to entitle him to claim any rights either as a tenant at will or as a tenant at sufferance the holding over must be continued for such a length of time and under such circumstances as to authorize the implication of assent upon the part of the landlord. Commissioner of Pilots v. Clark, 33 N. Y. 251; Schuyler v. Smith, 51 N. Y. 309, 10 Am. Rep. 609; Smith v. Littlefield, 51 N. Y. 539; Haynes v. Aldrich, 133 N. Y. 287, 31 N. E. 94, 28 Am. St. Rep. 636. By the failure of the government to renew the lease Conkling -was interrupted in the performance of his contract for a period of three months, during which time he could only have entered upon the premises to remove the stone as a trespasser. It was not incumbent upon him to undertake performance in that capacity. Upon the facts as they appeared upon the trial, because the government had not performed upon its own part it was not entitled to recover against Conkling for nonperformance of the contract; consequently there was no right of recovery against the defendant as surety,
Some of the evidence upon the trial indicates that Conkling was anxious to throw up his contract, and had been assured by Some of thé subordinate officers of the government that the government- would protect him if he would go on with the work.
The judgment is reversed.