35 F.2d 376 | W.D. La. | 1929
The allegations of the petition in this ease were fully stated in the opinion filed herein on January 25, 1926 [11 F.(2d) 404], passing upon the plea to the jurisdiction and the motion to dismiss. The answer, in substance, admits the contract and its performance by the contractor, Ben F. Casey, as well as payment to the Planters’ Bank of Haynesville, La., of $12,642.59, balance of the contract price, all as alleged, but in justification thereof avers that the defendant school board recorded its acceptance of the completed building in the mortgage office of Claiborne parish, La., on January 18, 1924, and that no claims for material or labor were served or filed with it or in said office within the 45 days provided by the act of the Legislature, No. 224, of 1918. For this reason it claims the payment to the bank on the order of the contractor of the balance due was lawful.
The jury has been waived and the parties have submitted the case to the court upon an agreed statement of facts, the substance of which is as follows;
The contractor completed the building and it was accepted by the board, who filed its written acceptance with the clerk of court and ex officio recorder of mortgages and conveyances on January 18, 1924, but, instead of recording in the mortgage book, he recorded it in the conveyance records of the parish on March 19, 1924. Both the conveyance and mortgage records are kept in the same room of the clerk’s office, who files all documents for record. The Act No. 224 of 1918 applies to the contract in this case. Certain of the creditors of the con
The said board “tentatively accepted and filed the order” referred to on December 31, 1924, and “on April 3, 1924, acting upon advice of its counsel by check No. 248, paid over to the Planters Bank of Haynesville the entire balance due Ben F. Casey on the Haynesville High School building, $12,642.-59.” The Victoria Lumber Company filed its mortgage lien in the mortgage office of the parish on March 7, 1924, which was recorded in the mortgage records April 9, 1924; the Fitzgerald Plumbing & Heating Company also filed its lien on March 8,1924, which was likewise recorded April 9, 1924; and H. H. Bain filed his lien on March 20, 1924, which was recorded April 12, 1924. The mortgage certificate of the clerk of court, ex officio recorder of mortgages, attached to the statement of facts and dated April 3, 1924, shows recordation of liens of the three above claimants, together with others, and also the contract and bond for the erection of the building. On “March 7th and 16th, 1924” attorneys for Fitzgerald Plumbing & Heating Company sent a registered letter to the school board, inclosing sworn statement covering amount of claim for labor and material furnished in constructing both the grammar and high school buildings; attorneys for Bain also sent to the school board, by registered letter, an attested account of his claim on March 9, 1924, “duly recorded lien in the mortgage office” of said parish; and the attorneys for Victoria Lumber Company on March 7, 1924, sent a “sworn account” of its claim to the school board by registered letter, and a copy thereof was filed in the mortgage office on March 7th and recorded —all of which letters and statements were received and were for the amounts which plaintiff had to pay in settlement of the judgments obtained against it. The attorney for the plaintiff “in the latter part of June, 1924,” learned that the school board had paid over the entire balance due the contractor, and “immediately thereafter had Ben F. Casey to secure from Edward F. Neild, architect, a final certificate No. 10, which the said Ben F. Casey, for value received, indorsed to the order of the” plaintiff, “surety on his bond. * * * ” The attorney for the plaintiff then went to Homer, the parish seat of Claiborne parish, and on July 9, 1924, wrote the president of the school board, advising him of the receipt of the certificate, No. 10, from the architect and its indorsement to plaintiff by the contractor, that the payment to the bank “was unauthorized and illegal,” and the plaintiff company would hold it responsible for the payments under the contract as provided therein, and liable to it for damages resulting from such action. Thereafter plaintiff addressed other communications to the school board, seeking to be reimbursed for the payments made to the above claimants, but the board declined to comply therewith, and this suit was filed on March 30, 1925.
As I see the matter, the question to be decided is as to whether, as a matter of law, the defendant school board, after notice of the existence of these claims, which admittedly it received before the money was paid over to the bank on Casey’s order, could thereby relieve itself from responsibility to them and to the surety who was bound with the contractor for their payment.
It is contended that the notice of acceptance of the completed building, which was filed January 18, 1924, with the elerk of court, ex officio recorder both of mortgages and conveyances, but recorded in the conveyance records on March 19th, was sufficient under the law; and the claims paid by plaintiff having been filed in the mortgage office March 7, March 8, and March 20, 1924, long after the expiration of the 45 days allowed by the statute, the liens were lost and the school board was bound to pay over the balance to the contractor or other persons on his order.
As pointed out in the opinion on the plea to the jurisdiction and motion to dismiss, the contract and bond together constituted a three-sided agreement between the school board, the contractor, and the surety, carrying mutual rights and obliga^tions which, by the very nature of the undertaking, all were bound to respect and perform. The contractor was required to complete and deliver the "building to the
Under the views above expressed, it is unnecessary to determine what the effect would have been had the school board paid the balance of the contract price after the expiration of the 45 days without notice of the existence of these claims. Neither do I think it necessary to consider the question raised as to the recording of the notice of acceptance of the building in the conveyance instead of the mortgage records. My opinion is that, as a matter of law, since the balance in the board’s hands after the completion of the work was more than sufficient to pay these claims and it deliberately paid the same to the bank after knowledge of their existence, it therefore became liable to the plaintiff as the ultimate beneficiary of the fund, and the latter should have judgment for the amount which it paid out under the obligations of its bond.
Decree may be presented.