By a contract in writing the defendants agreed to install a heating and cooling system for the plaintiff. An auditor, whose findings of facts were to be final, found that the contract price was $6,200; that the defendants intentionally and wilfully abandoned the contract after the plaintiff had paid them $4,200; that the plaintiff reasonably paid $2,361 to another contractor to perform the balance of the work; and that the plaintiff was entitled to recover $2,361. A judge of the Superior Court ordered judgment for the plaintiff in the sum of $361, and the plaintiff appealed.
It was the duty of the judge, and is now our duty, to enter the correct judgment on the auditor’s report.
Union Old Lowell National Bank
v.
Paine,
The plaintiff seeks to extend this doctrine in such a way as to collect exemplary damages and to obtain a $6,200 heating and cooling system for $4,200. It will be noted that the same rule of law, if sound and accepted as the court’s idea of justice, would apply if the contract price had been $62,000 and the reasonable cost of completion had been $62,361.
Restatement: Contracts, § 346, states the rule to be: “(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows: (a) For defective or unfinished construction he can get judgment for . . . (i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste . . ..” See illustrations of subsection (1) 1, 4, and 5; McCormick on Damages, § 169.
We think that this is the proper rule to apply here. The plaintiff relies upon
Glazer
v.
Schwartz,
It is not the policy of our law to award damages which would put a plaintiff in a better position than if the defendant had carried out his contract.
Magnolia Metal Co.
v.
Gale,
The plaintiff is entitled to be made whole and no more. *83 This is true in an action against a defendant for breach of contract, albeit a wilful one, even though the same defendant in suing as a plaintiff on the same contract might be barred by the rule of Sipley v. Stickney.
Order for judgment affirmed.
