Ficara v. BelleauFicara v. Belleau
- Reporters:
- , ,
- Before:
- Wilkins
By a contract in writing the defendants agreed to install a heating and cooling system for the plaintiff. An auditor, whose findings of facts were to be final, found that the contract price was $6,200; that the defendants intentionally and wilfully abandoned the contract after the plaintiff had paid them $4,200; that the plaintiff reasonably paid $2,361 to another contractor to perform the balance of the work; and that the plaintiff was entitled to recover $2,361. A judge of the Superior Court ordered judgment for the plaintiff in the sum of $361, and the plaintiff appealed.
It was the duty of the judge, and is now our duty, to enter the correct judgment on the auditor’s report.
Union Old Lowell National Bank
v.
Paine,
318 Mass. 313, 315.
The plaintiff seeks to extend this doctrine in such a way as to collect exemplary damages and to obtain a $6,200 heating and cooling system for $4,200. It will be noted that the same rule of law, if sound and accepted as the court’s idea of justice, would apply if the contract price had been $62,000 and the reasonable cost of completion had been $62,361.
Restatement: Contracts, § 346, states the rule to be: “(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows: (a) For defective or unfinished construction he can get judgment for . . . (i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste . . ..” See illustrations of subsection (1) 1, 4, and 5; McCormick on Damages, § 169.
We think that this is the proper rule to apply here. The plaintiff relies upon
Glazer
v.
Schwartz,
276 Mass. 54, where a builder of a house for the contract price of $14,700 wilfully defaulted after receiving $13,000. The value of the house as left by the builder fell short by only $700 of what its value would have been if the contract had been fully performed. The builder brought a bill in equity against the owner to establish a mechanic’s lien and was denied relief. The owner sought affirmative relief for damages. “The
It is not the policy of our law to award damages which would put a plaintiff in a better position than if the defendant had carried out his contract. Magnolia Metal Co. v. Gale, 189 Mass. 124, 132-133. Snelling v. Dine, 270 Mass. 501, 506. Bucholz v. Green Bros. Co. 272 Mass. 49, 54. Associated Perfumers, Inc. v. Andelman, 316 Mass. 176, 185-186. “The fundamental principle upon which the rule of damages is based is compensation. . . . Compensation is the value of the performance of the contract, that is, what the plaintiff would have made had the contract been performed.” F. A. Bartlett Tree Expert Co. v. Hartney, 308 Mass. 407, 412. There is nothing to the contrary in Stevens v. William S. Howe Co. 275 Mass. 398, 402-403.
The plaintiff is entitled to be made whole and no more.
Order for judgment affirmed.