In February 2007, the plaintiff and the defendant Wheaton Builders, Inc., LLC (hereinafter Wheaton), entered into a
To state a cause of action alleging tortious interference with contract, the plaintiff must allege: the existence of a valid contract between it and a third party, the defendant’s knowledge of that contract, the defendant’s intentional procurement of the third party’s breach of that contract without justification, and damages (see Lama Holding Co. v Smith Barney,
New York does not recognize civil conspiracy to commit a tort as an independent cause of action (see Hebrew Inst. for Deaf & Exceptional Children v Kahana,
The Supreme Court also providently exercised its discretion in denying the plaintiffs cross motion for leave to serve a second amended complaint. Although leave to amend should be freely given in the absence of prejudice or surprise to the opposing party (see CPLR 3025 [b]), the motion should be denied where the proposed amendment is palpably insufficient or patently devoid of merit (see Scofield v DeGroodt,
The plaintiffs remaining contentions concern matter dehors the record (see Schwarz v Margie,