Opinion by
In this mechanies' lien foreclosure action involving the priority of liens relative to a deed of trust, defendant Colorado Community Bank (CCB) appeals the summary judgment in favor of the following lien claimants: plaintiff, Ferguson Enterprises, Inc., and defendants Keybuild Solutions, Inc., Carpenters Service Inc., Autumn Landscaping, Inc., Premier Hass Solutions, Inc., SC Design, Inc., Systems Plumbing, LLC, and Colo Counter-Tops, Inc. (collectively, lien claimants). We reverse and remand.
I. Facts
The following facts, reflected in the chart attached to this opinion, are undisputed.
On August 22, 2002, Zion Development, LLC, became the owner of the real property involved in this action. It commenced the planning of a multi-unit project and, in 2005, borrowed money from Flatiron Bank. That loan was secured by a deed of trust, recorded on November 22, 2005.
Zion hired PWN Architects and Planners, Inc. (the architects), who created a master plan for the project and filed the plan with the City of Thornton on October 28, 2007. The record does not reflect whether there was any construction on or improvement to the property while Zion owned it.
Zion defaulted on the FlatIron loan, precipitating a foreclosure action. At a foreclosure sale in October 2007, FlatIron was the successful bidder and received a certificate of purchase. In January 2008, FlatIron received a public trustee's deed to the property and promptly recorded it. FlatIron did not commission any work on the property during its ownership.
On May 30, 2008, FlatIron conveyed the property to Water Tower Builders, LLC (Water Tower), which financed the purchase of the property and its later construction activities through two loans in excess of $3 million obtained from CCB. The two loans were secured by a single deed of trust recorded on June 5, 2008.
Water Tower initiated its first work on the project on July 1, 2008, when it hired a project manager. The lien claimants provided work and materials to the Water Tower property between November 14, 2008, and May 22, 2009.
Water Tower was also unable to pay its obligations, prompting the lien claimants to timely file lien claims against the property for work and materials they had provided. In October 2009, Ferguson filed this mechan-ies' lien foreclosure action, naming CCB and the other lien claimants as defendants. The aggregate amount of the mechanies' liens filed totaled $164,049.91.
CCB initiated a foreclosure proceeding on its deed of trust in December 2009 and gave proper notice to the lien claimants. As the only bidder at a foreclosure sale on April 14, 2010, it received a certificate of purchase. None of the lien claimants sought to redeem the property. Ultimately, CCB received and recorded a public trustee's deed to the property on May 10, 2010.
CCB moved for summary judgment in this case seeking to dismiss the mechaniecs' lien claims, contending, as pertinent here, that the lien of its deed of trust was prior and superior to the mechanies' liens involved here because CCB was a construction lender entitled to priority under Joralman v. McPhee,
The trial court denied CCB's motion and granted the cross-motion in favor of the lien claimants. The court concluded that the mechanics' liens related back to the date of the first work performed for Zion, based on the filing of the master plan on October 23, 2007 by the architects, thereby predating CCB's deed of trust and rendering CCB's interest junior to the mechanies' liens. This appeal followed.
CCB contends that the trial court erred in determining that the mechanics' liens involved here had a priority senior to its deed of trust. We agree in part and, because the record does not provide facts that are necessary for such a determination, we remand for further proceedings.
IL Standard of Review
Summary judgment is appropriate when the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits filed by parties, demonstrate that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. See C.R.C.P. 56(c). We review de novo an order granting summary judgment. McIntyre v. Bd. of County Comm'rs,
We also review a trial court's application of the law de novo. Asphalt Specialties, Co. v. City of Commerce City,
The mechanies' lien statute should be strictly construed with respect to those acts necessary to perfect the lien and should be construed liberally as to the provisions of the statute that are remedial in nature. Powder Mountain Painting v. Peregrine Joint Venture,
III. Construction Loan and Mechanics' Lien Law
Mechanics' liens are generally subordinate to a prior recorded deed of trust on the land. See Darien v. Hudson,
When the lien is for work done or labor or materials furnished for any entire structure, erection, or improvement, such lien shall attach to such building, erection, or improvement for or upon which the work was done ... in preference to any prior lien or encumbrance, or mortgage upon the land upon which the same is erected or put....
In Lew Hammer, Inc. v. Dash, Inc.,
Here, CCB appears to concede that lien claimants' work was performed on new improvements. Accordingly, section 88-22-103(2) is applicable and, absent more, would provide a superior lien on the improvements to the lien claimants.
However, even when section 38-22-108(2) is applicable to grant priority to me-
Here, CCB's recorded deed of trust states that "this Security Instrument secures an obligation incurred for the construction of an improvement on the Project." Accordingly, the deed of trust is expressly intended to secure a loan for construction. The record also shows that the deed of trust secured two loans, one for construction of improvements and one to complete the actual purchase of the property by Water Tower. One promissory note in the amount of $1,839,000 indicates that the purpose of the loan is to "construct 13 townhomes in Thornton, Colorado," while another promissory note in the amount $1,225,000 indicates its purpose is to "purchase 52 developed townhome lots." Two affidavits submitted by CCB to the trial court with its motion for summary judgment and its reply reflect that CCB agreed to advance up to $1.8 million for construction, and actually advanced "at least $1.6 million."
Accordingly, the lien claimants are charged with notice of the CCB deed of trust lien from the time the deed of trust was recorded, see Ist Choice,
We reject lien claimants' argument that the two affidavits CCB submitted are contradictory, thus creating a genuine issue of material fact. The Bowlds affidavit states, "[Water Tower] received a loan from CCB on May 29, 2008 for the purpose of developing and constructing improvements on the Property. CCB advanced approximately $1.8 million solely to fund construction of the improvements." The Hay affidavit, signed one month after the Bowlds affidavit, recites the amounts the lien claimants actually received from the construction loan funds and summarizes, "all told, [Hay's] calculations indicate that at least $1.6 million was paid directly by CCB to various contractors and subcontractors for work related to the construction of the premises." The Bowlds affidavit qualifies its statement of the amount as "approximate," while the Hay affidavit avers that $1.6 million was actually paid. Moreover, there is no contrary affidavit to dispute that CCB actually applied "at least $1.6 million" to the project, or that takes issue with the statement that lien claimants received the stated proceeds from CCB's construction loan.
We also reject lien claimants' contention that the affidavits are insufficient because they do not contain an accounting of exactly where all construction loan funds were employed. The affidavits are sufficient to establish the fact of payment, and any lack of accounting does not diminish their prima facie evidentiary value.
Accordingly, it is undisputed that CCB has met the construction loan requirements identified in Joraiman and 1st Choice, inasmuch as its deed of trust was recorded on June 5, 2008, before any work commissioned by Water Tower began on the property. Further, the deed of trust states that it secures a loan for construction, and CCB disbursed loan proceeds of $1.6 million for construction purposes. See Ist Choice,
However, this conclusion is subject to a determination whether the mechanies' liens relate back to the architects' services for Zion, which would provide them priority over the CCB deed of trust regardless of the construction loan doctrine. We now turn to that issue.
IV. Relation Back of Mechanics' Liens
Lien claimants contend that their liens "attached" as of October 28, 2007, because their work relates back to work performed by the architects for the previous owner, Zion. This contention requires examination of the relation back doctrine applicable in certain situations. We conclude that further proceedings are necessary to resolve this contention.
Section 838-22-106(1), C.R.S.2011, which provides for priority of mechaniecs' lens and their attachment, states:
All liens established by virtue of this article shall relate back to the time of the commencement of work under the contract between the owner and the first contractor, or, if said contract is not in writing, then such liens shall relate back to and take effect as of the time of the commencement of the work upon the structure or improvement, and shall have priority over any lien or encumbrance subsequently intervening, or which may have been created prior thereto but which was not then recorded and of which the lienor, under this article, did not have actual notice. Nothing contained in this section, however, shall be construed as impairing any valid encumbrance upon any such land duly made and recorded prior to the signing of such contract or the commencement of work upon such improvements or structure.
This statute embodies a relation back doctrine, which essentially provides that a mechanies' lien relates back in time and has priority from the date work first commences on the project at issue, thus gaining a preference over other liens and interests in the land that may have been recorded before the actual filing of the lien. See Trustees of Mortg. Trust v. Dist. Court,
The rendition of services by an architectural firm in preparing preliminary plans and drawings for a project has been held to constitute the commencement of work under this statute. See Bankers Trust Co. v. El Paso Pre-Cast Co.,
At first blush, lien claimants' argument appears to have merit. As previously noted, a mechanices' lien generally relates back in time and has priority from the date work first commences "on the project at issue," see Trustees of Mortg. Trust,
CCB argues, however, that the statutory language that mechanics liens "shall relate back to the time of the commencement of work under the contract between the owner and the first contractor" does not define the term "owner" in this context. CCB argues that the term "owner" must be read to mean "current owner," noting, correctly, that only work done at the instance of the owner of the property can support a lien, see C & W Electric, Inc. v. Casa Dorado Corp.,
In construing a statute, our primary duty is to give effect to the intent of the
To effectuate the legislative intent, a statute must be read and considered as a whole and should be interpreted in a manner that will give consistent, harmonious, and sensible effect to all its parts. State v. Nieto,
"We read words and phrases in context and construe them literally according to common usage unless they have acquired a technical meaning by legislative definition." People v. Yascavage,
Here, CCB's interpretation would mean that mechanies' liens can never relate back to work done for prior owners. Were that proposition correct, landowners could avoid mechanies' liens simply by transferring the property during construction to some related third party such as a spouse or entity controlled or owned by the landowner, and contend that work the original landowner commissioned from contractors thereafter is not lienable because it was not done at the behest of the "current owner." And even purchasers for value could assert that they would take title free of any liens, even though having actual knowledge of work performed for or construction liens recorded against a property. Such constructions of the statute would be absurd, a result we must avoid. See Reg'l Transp. Dist. v. Lopez,
Even so, lien claimants' position that their work relates back to work performed by the architects for the previous owner ignores the fact that an intervening foreclosure by Flatiron against Zion, the previous owner, has taken place. In such a foreclosure, under section 38-38-501, a certificate of purchase holder generally takes title to the property in question free and clear of all liens and encumbrances junior to the lien foreclosed. See First Interstate Bank v. Tanktech, Inc.,
In Ragsdale Bros. Roofing, Inc. v. United Bank,
The owner defaulted on the promissory note to United Bank, prompting a foreclosure proceeding on the second deed of trust. United Bank purchased the property at the public trustee's sale, received a certificate of purchase, and later received and recorded a deed to the property.
The contractors filed an action to foreclose their liens, naming United Bank as a defendant. The trial court held that what is now section 38-38-501 did not cut off the contractors' liens on the building, but did cut off the liens on the land. Id. at 752.
Affirming on appeal, a division of this court noted that, under section 38-22-103(2), when a mechanies' lien is for work done or material furnished for any entire structure, the lien attaches to the structure in preference to any prior lien or mortgage on the land. Noting United Bank had conceded that its deed of trust was junior to the contractors' liens as to the structure under section 38-22-103(2), the division then had to reconcile that provision with section 88-88-501. The division concluded that "[when a lien is filed later in time than a deed of trust, yet is superior to the deed of trust, the title acquired pursuant to the public trustee's sale and deed is subject to the superior lien," and that the trial court did not err in ruling that United Bank's title pursuant to the public trustee's certificate of purchase and deed was subject to the contractors' superior mechanies' liens on the building. Id. at 753.
Applying the above principles here, the FlatIron foreclosure, which was based upon a deed of trust recorded on November 22, 2005, would have extinguished all liens junior to its deed of trust as to the real estate. See id. The architects' work involved the creation of a master plan for the project, which was filed and approved on October 23, 2007, the date upon which the lien claimants here rely for attachment for their liens. Clearly, FlatIron's deed of trust lien on the real estate, recorded in 2005, was senior to any lien on the real estate that the architects 'had or could have had in 2007. See § 38-22-106(1) ("Nothing contained in this section, however, shall be construed as impairing any valid encumbrance upon any such land duly made and recorded prior to the signing of such contract or the commencement of work upon such improvements or structure."); see also Lew Hammer, Inc.,
Whether the Flatiron foreclosure extinguished any architects' lien that arose as of October 283, 2007, would depend upon whether there was any structure or improvements to which any lien could attach under section 38-22-103(2). If so, the architects' lien would be a superior lien upon any improvements and structures under section 38-22-103(2), and FlatIron would have taken title upon receipt of the certificate of purchase and deed subject to that superior lien. See Ragsdale Bros. Roofing,
However, if any architects' lien were junior to FlatIron's lien on any structure or improvements, the foreclosure would have extinguished it, and the lien claimants could not relate their work back to the master plan filing. Also, in the event that the architects did not actually file a lien, the lien claimants could not relate back their work thereto, because a bona fide purchaser without notice at the FlatIron foreclosure sale would have had no record notice of any lien claim, and the foreclosure would have cut off any inchoate lien. See generally First Interstate Bank,
V. Additional Contentions
CCB contends that the lien claimants cannot relate their liens back to work done by the architects for Zion because, under section 38-22-122, C.R.S8.2011, the work was not completed under the same contract between the same parties. However, as lien claimants point out, CCB did not assert this argument in the trial court. Accordingly, we decline to address it here. See Brown v. Silvern,
CCB also contends that, under section 38-38-501, the mechanics' liens at issue here were extinguished by its own foreclosure of the deed of trust granted by Water Tower. However, under Ragsdale Bros. Roofing,
Accordingly, because the record does not contain sufficient facts for a legal determination of lien seniority to be made, resolution of this issue will also depend on facts that must be developed on remand.
The judgment is reversed and the case is remanded with directions to allow the filing of further affidavits sufficient to respond to the factual issues noted in this opinion, or, if genuine issues of material fact preclude summary judgment, for further discovery and trial.
