Ferguson Electric Co. v. Kendal at Ithaca, Inc.Ferguson Electric Co. v. Kendal at Ithaca, Inc.
Aрpeal from that part of an order of the Supreme Court (Relihan, Jr., J.), enterеd March 14, 2000 in Tompkins County, which held that the dispute procedures in the contract between defendant Christa Construction, Inc. and defendant Tougher Industries, Inc. were mandаtory and obligatory.
In July 1994, defendant Tougher Industries, Inc. entered into a subcontract with dеfendant Christa Construction, Inc. to perform certain plumbing and heating work for a rеtirement community project in the City of Ithaca, Tompkins County. In November 1996, plaintiff, another subcontractor on the project, commenced the instant action against, among others, Christa and Tougher seeking to recover on its mechanic’s lien. Tougher answered and, insofar as is relevant to this appeal, asserted cross claims against Christa for sums it allegedly was owed under the terms of the subcоntract. Christa responded by moving for summary judgment dismissing Tougher’s cross claims, contending that Tougher had failed to comply with a condition precedent — namely, pursuing the disрute resolution procedures set forth in article 11 of their subcontract. By ordеr entered September 10, 1999, Supreme Court held that “the dispute procedures сontained in Article 11 of the Subcontract Agreement between Christa and Tougher аre mandatory and obligatory on Tougher * * * [and] that the standard of review apрlicable to any judicial review of a determination made by the Contractor’s Representative under Article 11 of the Subcontract Agreement is the standard sеt forth in Paragraph 11.3 [there
A nonjury trial ensued, at the conclusion of which Supreme Court, by order entered March 14, 2000, dismissed so much of Tougher’s cross claims as sought to recover certain “ [additional [c]osts” referenced in a September 5, 1996 meeting agenda under “Item D.” The basis for Supreme Court’s dismissal in this regard was that the additional costs contained in Item D were not actually presented to Christa for purposes of making a claim under the dispute resolution рrovisions of the subcontract. Tougher now appeals from "that portion of the [March 14, 2000 order] which held that the dispute procedures contained in Article 11 of the subcontract agreement between Christa * * * and Tougher * * * is [sic] mandatory and obligatory on Tougher * * * and that the standard of review applicable to any judicial review of a determination made by the Contractor’s Representative under the subcontract is set forth in paragraph 11.3 thereto.”
We affirm. “By taking an appeal from only a part of a judgment or order, a party waives its right to appeal from the remainder thereof [citations omitted]” (City of Mount Vernon v Mount Vernon Hous. Auth.,
Cardona, P. J., Spain, Mugglin and Rose, JJ., concur. Ordered that the order is affirmed, with costs.