48 Pa. Super. 27 | Pa. Super. Ct. | 1911
Lead Opinion
Opinion by
This action was brought to enforce the alleged liability of the defendant as surety upon a bond given to secure the performance of a contract by Jacob J. Jordan. Jordan, the principal in the bond, had entered into a written contract with the plaintiffs under which he agreed to furnish the latter the labor to lay 800,000 bricks in a building then in process of erection, for which the plaintiffs were to pay him at the rate of $5.25 per 1,000; “The payments on this work to be at the rate of $5.00 per 1,000, brick yard count, on Friday, for all bricks laid up to Thursday night preceding; the balance of 25 cents per 1,000 to be paid when this contract is completed,” and the bond upon which this action was brought was executed to secure the obligees, the plaintiffs, “from any pecuniary loss resulting from a breach of any of the terms, covenants and conditions of the said contract upon the part of the said principal to be performed.” The bond expressly referred to the written contract and provided that it should “become a part of this bond.” Jordan partly performed his contract and the plaintiffs made payments to him upon account of the same, but after about half of the brick had been laid Jordan stopped
The surety upon a contractor’s bond is entitled to stand upon the terms of the contract, precisely as they were when he agreed to become responsible for its performance. Any dealings by the owner, the obligee in the bond, with the contractor which amount to a departure from the contract by which a surety is bound and which may materially vary or enlarge the latter’s liability, without his consent, operate as a discharge of the surety: Bessemer
The effect of the stipulation in the contract that a certain part of the price of the work should remain in the hands of the plaintiffs until the entire work was completed was twofold: First, to accumulate in the hands of the plaintiffs a fund to be applied to the completion of the work in case Jordan did not do so; and second, the amount remaining unpaid for work already done was an incentive intended to operate upon the mind of Jordan to finish the work in due time. What the plaintiffs did was perhaps calculated to make it easier for Jordan to complete the work if he acted with prudence and good faith, but it also took away that particular sort of pressure which, by the contract, was intended to be applied to him, and this de
Even if we had reached the conclusion that the effect of the overpayment did not work an absolute discharge of the surety, there can be no question that the surety
The judgment is reversed with a procedendo.
Concurrence Opinion
concurs in the judgment upon the ground that defendant was entitled to credit in the amount of the anticipated payments.