63 Pa. Super. 561 | Pa. Super. Ct. | 1916
Opinion by
The Act of June 4,1901, P. L. 431, relating to mechanics’ liens in its 12th Section provides that “If the labor or materials be furnished continuously in the erection and construction of, addition to, or removal of a structure or other improvement, the claimant may file a single claim, though furnished under more than one contract, with the same effect as if furnished continuously under a single contract.”
The only question before us is whether the materials furnished in the case at bar were furnished continuously as required by the above in part quoted section. The first items of the lien were furnished February 19,1912, up to March 22, 1912, and from March 22d to June 3d there were no materials furnished. After that they were furnished at frequent intervals until the completion of the improvement.
The Act of April 14, 1855, P! L. 238, provided for the filing of mechanics’ liens for work done or materials furnished continuously. Prior to that act as stated in Singerly v. Doerr, 62 Pa. 9, the purchasing of material as needed on a job was a new contract at every purchase and any item more than six months old was barred. The Act of 1855 changed this so that when the materials were furnished for a single building in the ordinary progress of the work, thns giving to the items a unity of purpose if not of contract, even if there was an interval of time between the procuring of the articles, a lien could be filed within six months of the last item: Diller v. Burger, 68 Pa. 432, and Hofer’s App., 116 Pa. 360. In the last case there was a much longer interval than in the case before us. “The question, usually, is not so much respecting the length of the interval, as to whether the work was ordered and done in its ordinary progress from
The judgment is affirmed.