76 N.J. Eq. 495 | New York Court of Chancery | 1909
This suit is brought to foreclose a mortgage made by the defendants Albert A. Guigues and wife to secure the payment of the sum of $10,000 and interest. The mortgage is dated May 27th, 1907, and was duly lodged for record in the clerk’s office of the county of Middlesex on May 28th, 1907. It covers two tracts of land in Perth Amboy. The first is bounded by Eector, Lewis and Water streets, and lands of one Eunyon; the second is a dock lot lying easterly of the first lot and separated from it by a narrow public highway called Water street. At the time of the making of the mortgage there was in course of construction on the first tract a dwelling-house of large proportions, the contract price of which was upwards of $33,000, and towards the erection of which four of the defendants claim to have performed labor and furnished materials. The debts claimed by them respectively therefor not having been paid, they filed lien claims under the provisions of the Mechanics’ Lien law against both tracts, and in consequence were made parties defendant to this suit.
Two questions are raised by the complainant against each of the lien claims. The first one concerns the validity of the claims under the lien law, and the second touches the size of the curtilage. I will take up the claims seriatim.
OORT HARDWARE COMPANY CLAIM.
This claim arises out of an agreement dated September 29th, 1906, between the Cort Hardware Company and the defendant Guigues, and provides for furnishing all the hardware for the dwelling-house in question. It provided in article IX. that the sum to be paid by the owner for the said materials was $442, to be paid to the contractor in current funds only upon certificates of the architects, but in one payment when all was furnished complete and within thirty days after the delivery. It appears that up to November 19th, 1907, the Cort Hardware Company had furnished considerable of the hardware provided for by this contract, and that the hardware had been put in place throughout 'the second story, and possibly some other portions of the building, and that there remained in the building a considerable portion which had not yet been attached. On that date the president of the company went with one of the architects to the building for the purpose of delivering the final installment of the hardware. This final installment he carried with him. When they arrived at the building they found the hardware which had not been attached to the building scattered about, and the architect, in the presence of the president of the claimant, had the hardware packed into a barrel and shipped to the claimant at Newark. The claimant’s president did not deliver the final installment, but carried it back to Newark with him, and the claimant then took into its possession all the hardware which had been shipped from the Perth Amboy house, checked it up and re-polished some of it, and then delivered the same to the architect,
The result is that this claim must be disallowed
This claim arises out of a contract for plumbing work upon the house in question. The plumbing contract was first taken by a man named Joyce, who failed, and Kelly & McAlinden Company undertook to finish the work. They made a new and special contract with the owner on January 28th, 1907, which provided that they should furnish all the work for the completion of the plumbing, gasfitting and metal work required for the house for $2,950. Their payments were to be made as the work progressed, monthly, to the amount of eighty per cent, of the value of labor and materials furnished. The remaining twenty per cent, was to constitute the final payment.
The first objection to this claim is that the lien had expired before the claim was filed. The lien claim was filed June 29th, 1908. Kelly & McAlinden swear that the last work that was done by them on the contract was done March 25th, 1908. That turned out to be four hours’ work by two men who were engaged in connecting up the kitchen range. They had done no work on the building previously to this time since September 25th, 1907. The reason why they were delayed in finishing their work was that the owner did not furnish the range until March of 1908; hence the claimants could not put it in place and connect it up. In my opinion the work that they did on March 25th, 1908, was not trivial, but was a substantial portion of the contract, and was required in order to finish it up. I therefore conclude that the lien claim was filed in time.
During the progress of the work the architects furnished to the Ivelty & McAlinden Company two certificates, the first one for $1,293.87, and the second one for $1,018.13, making altogether $2,312, on account of which they were paid $1,000, leaving due to them $1,312 on account of the contract. Their lien claim includes $202.36 for extra work, a portion of which should be disallowed. The items charged under date of March 14th were for testing the work which had been done by Joyce, and should be disallowed, because it is part of the contract to see that the work is properly done, and although there was some evidence
My conclusion as to this claim is that it should be allowed for $1,312, and in addition thereto the items for extra work, excepting those which are disallowed.
PIGOTT & MATHESIUS CLAIM.
The claimants in this case are the architects of the building. Their claim was filed January 31st, 1908. The principal objection to this claim is that the lien had expired before the lien claim was filed. Mr. Pigott, one of the firm, visited the premises on November 19th, 1907, in company with Mr. Birkenmeier, president of the Cort Hardware Company, but inasmuch as no work was being done at that time, and apparently there had been no work done on the building for some two or three months previous, it can hardly be claimed that that visit was sufficient to keep the lien alive. The visits made by Mr. Pigott to the building before that time were made in October. His account of railroad expenses shows that he was at the building October 17th and 24th. Previous to that Mr. Pigott was at the building on September 3d arid 27th; at that time the plumber was working, the stucco man was fixing up defects • in his work, and another man was engaged in putting on weather strips; but when he went there in October the building was practically at a standstill. He says, however, he had to go down there to see that things were safe, to take care of the place, to see if anyone was
Their claim will therefore be allowed for the sum of $1,229.41.
IEA E. OBOUSE CLAIM.
The lien claim in this case was filed on June 23d, 1908, and the testimony of the claimant is that the last work that he did on the house was about May 12th of that year. This claim arises out of a contract made on May 22d, 1906, between Ira R. Crouse and Albert A. Guigues, by which Crouse agreed to perform all the carpenter, mason and excavation work for the Guigues residence as shown on the specifications, for the sum of $16,526. The payments were to be made monthly to the extent of eighty per cent, of the value of the work performed up to the date of the architects’ certificate, and the twenty per cent, held back was to constitute the final payment.
Mr. Crouse was never permitted to finish his contract, although he always stood ready to do so. The difficulty arose out of a controversy between the owner and the architects and their subsequent discharge from the owner’s employ, and also from the fact that the claimant, Mr. Crouse, could not work from the detailed drawings, his reason being that the trim and wainscoting which was specified for the first floor of the house did not correspond with the requirements of the specifications prepared by the architects. There was another reason which arose out of the financial embarrassment of the owner. Mr. Crouse’s work appears to have proceeded properly up to the time when the difficulties above mentioned became acute. He holds an archi
All these claims will bear interest, and if counsel cannot agree upon .the amount I will undertake to settle it.
CURTILAGE.
The property covered by the complainant’s mortgage includes not only the tract of land bounded by Water, Lewis and Eector streets, on which the mansion-house is situated, but includes alsc a dock lot abutting upon Earitan bay, but separated from the plot on which the mansion-house stands by a narrow street or driftway, which appears to be also a public highway. There is a controversy between the mortgagee and the lien claimants as to the size of the curtilage upon which the lien claims which have been allowed are-to stand. It is quite apparent that the statute (.Mechanics’ Lien law §21) does not apply to the case, and that we must have recourse to the decisions which have been made on the subject in our state. In Derrickson v. Edwards, 29 N. J. Law (5 Dutch.) 468, it was held that the curtilage intended by
It need hardly be said that the lien claims are concurrent liens upon the ¡iremises to which they have been confined. They are all of one character and there is nothing in any of the circumstances which could operate to give one priority over the other. See Mechanics3 Lien law § 20.