282 Mass. 442 | Mass. | 1933
This is a claim brought by petition against
In its answer the Commonwealth admitted the making of the contract; that on June 20, 1930, there was payable to the copartners a sum in excess of $12,000; that it received from the petitioner on June 21, 1930, a written notice of an assignment (a copy of which appears in the record); that on July 26, 1930, the copartners had completed their work and that it had approved the same; and that it is indebted for work done under said contract in the sum of $14,325.78. But it denied that that money is payable to the petitioner. It also admitted that on February 24, 1931, the petitioner made a written demand on it to pay over to the petitioner all moneys payable to Frank Lanza and Sons under said contract and that it refused to pay the same. Further answering the Commonwealth stated that “under and by virtue of a contract referred to in said petition . . . it was covenanted therein by said Contractor that it should not either legally or equitably assign any of the moneys payable thereunder, or the Contractor’s claim thereto, except with the previous written consent of the Department,” and further stated “that the Department never gave such assent to the assignment of any of the moneys payable under said contract.” The answer of the Commonwealth further set up the provisions of the contract contained in art. XLIII, entitled “Claims against Contractor”; and alleged “that there have been claims filed against said sum retained by the Department under said contract in the total sum of $28,727.56 by persons whose names and residences are as follows . . .”; that it “has no interest in the subject matter of the present con
The case was referred to an auditor “under an agreement that the findings of fact were to be final.” Hearings were had and a report was duly filed. Upon motion for confirmation of the auditor’s report the case was heard with certain other cases (referred to in the bill of exceptions) by a judge of the Superior Court sitting without a jury. Upon the findings of the auditor the judge made the following orders and rulings in the instant case: “In the case of Federal National Bank v. Commonwealth of Massachusetts, number 258448, the report of the auditor is confirmed and a finding is entered for the defendant upon the report of the auditor. I rule, upon the facts found by the auditor, that Commonwealth of Massachusetts has no funds in its possession due to Federal National Bank, because of the terms of the contract between Frank Lanza and Sons and the Commonwealth of Massachusetts, relative to assignments, there being no written consent by the Commonwealth of Massachusetts to the assignment and no waiver or estoppel of its right to set up the provisions of the contract. ” The petitioner duly excepted to the judge’s order, ruling, and overruling of the petitioner’s objections to the auditor’s report. The case is before this court on the exception thus taken.
The auditor found as a fact that the contract referred to in the petition was made between the Commonwealth and the copartnership doing business under the firm name and style of Frank Lanza and Sons; that “The bond filed by Lanza et al. with the Commonwealth is in the penal sum of $96,400 with New Jersey Fidelity & Plate Glass Insurance Company as surety and is conditioned upon the fulfilling of the covenants, conditions, and agreements in the foregoing contract on the part of the contractor, Lanza, and to indemnify and save harmless the Commonwealth, its officers and agents, and also that Lanza would pay for all labor performed or furnished and for all materials used or employed in carrying out of said contract. . . . [that this
At the hearing before the auditor the surety company offered, and the auditor received, in evidence the application for the bond referred to as part of the contract of December 24, 1929. The application is dated December 19, 1929, and contains an agreement of indemnity, one clause of which is as follows: “In further consideration of the execution of the said bond, the undersigned does hereby agree, as of this date, that the said NEW JERSEY FIDELITY & PLATE GLASS INSURANCE COMPANY, shall as surety on said bond, be subrogated to all rights, privileges and properties of the undersigned as principal and otherwise in said contract, and does hereby assign, transfer and convey to said Company all the deferred payments, and retained percentages, and any and all moneys and properties that may be due and payable at the time of such breach or default, or that may thereafter become due
The petitioner, in addition to its contention based upon the foregoing documentary evidence, raises the following issues: (1) “That by reason of a conversation between Lanza and Fair, the financial secretary of the department of public works, prior to the loan by the bank to Lanza and also by reason of a conversation between counsel for the bank and Fair prior to the assignment, Fair orally and by his conduct waived the provisions of the contract requiring written consent of the department of public works to the assignment to the bank”; (2) “That the moneys borrowed from the Federal National Bank by Frank Lanza and Sons were for the payment of laborers and material-men engaged in the construction of this work”; and (3) “That the bond filed . . . was more than adequate to pay the claims of all laborers and materialmen.”
In support of the contention numbered 1, the petitioner called Fair, who testified, in substance, that his position is that of financial secretary of the department of public works; that he is familiar with his own records; “that he has charge of the accounts, receipts and expenditures of all moneys, etc., which covers highways and waterways expenditures; that so far as the department of public works is concerned the actual payments are made by the State Treasurer upon vouchers; that if payment is to be
Upon the evidence the auditor found “as a fact and not as a matter of law” that Fair was without authority to waive the provision of this contract of the department of public works for and on behalf of the Commonwealth, and that he is an employee of the department of public works and not an executive or administrative officer of the Commonwealth. This finding of the auditor is final and conclusive, and required a rejection of the testimony, which is reported in the bill of exceptions, to the effect that the contractor before making the assignment to the petitioner had a talk with Fair wherein Fair told Lanza it was all right to make an assignment to the bank; that Lanza asked if it was necessary to get a written order to give the bank and Fair said there was no need of it, they would call up and “find out whatever it is”; that counsel for the bank thereupon talked with Fair, either on the day or the day before the assignment was executed, and said that Lanza had been to the bank in regard to a loan to be secured by an assignment of the fifteen per cent reserved by the Commonwealth; that he and Fair checked up the amount and found it to be in excess of $12,000. Counsel then asked Fair how the assignment could be made and the requirements of the Commonwealth in regard to notice of it, and Fair said if counsel filed a copy of the assignment as drawn, it would be filed with the board and that would be ade
It is obvious that the auditor’s conclusion of fact upon all the evidence, that there was no waiver on the part of the Commonwealth of the provision relative to assignments and at no time was there written consent to the assignment by the department of public works, has evidence to support it and that his findings of fact in this respect must stand. Marden v. Howard, 242 Mass. 350, 355; Walsh v. Cornwell, 272 Mass. 555, 562. The petitioner, however, contends that the auditor fails to deal at all with the question of waiver by the board of commissioners of public works, and presents in support of its position the following facts found by the auditor: (1) A copy of the assignment was mailed to the department of public works, State House, Boston, directed to the attention of Fair; (2) The receipt of the assignment was recorded by Fair on his records. There is no finding that the receipt was recorded by the board. (3) No reply was made to the letter of the bank containing the assignment; and (4) On February 24, 1931, counsel for the bank wrote to the department of public works making a demand for the money payable under the Lanza contract. On March 3, 1931, this letter was brought to the attention of the commissioners of public works and it was “Voted that Mr. Bailen [attorney for the bank] be informed that there is a reserve under the Hingham-Weymouth contract of $14,325.78, that there are claims on file . . . amounting to more than $28,000, and that the department cannot . . . pay over money to the Federal National Bank as requested.” On March 4, 1931, as voted, a letter was sent to Mr. Bailen, “Attorney, Federal National Bank of Boston,” and no other writing was sent or given by the department relative to this assignment. The petition in the case was filed March 13, 1931.
It is plain, aside from the acts and declarations of Fair,
Upon the issue of the petitioner numbered 2 the auditor found “that the money borrowed from the bank as well as money received by Lanza from the Commonwealth as payments on account of contract was placed in the general account of Frank Lanza and Sons, from which account all payments of the concern were made, which included office rent and expenses, salaries of members of the firm, and so forth. Some of the money so borrowed was used for the payment of labor and materials, but what part, how much
The petitioner is not entitled to priority in the retained percentages as against the surety company, for the reason that the surety company was an assignee of such retained percentages by virtue of an assignment prior in time to the assignment held by the petitioner. The "assignment to the surety company was for a valid consideration; it was contained in the application for the surety bond signed by the contractor which was dated before the date of the contract. In Commercial Casualty Ins. Co. of Newark v. Murphy, ante, 100, it was said of a like situation that the application for a surety bond, the execution of the bond, and the contract all related to the same subject matter and should be treated as essential parts of one transaction; so considered that assignment is not invalid.
The issue numbered 3 relates to the bond to pay claimants. It is immaterial whether or not the bond filed with the contract was more than adequate to pay the claims of laborers and materialmen for the reason that here there were claims (subject to the approval of the court) amounting to $26,711.64, and there was in the hands of the Commonwealth after the approval of the work $14,325.78. There therefore remained nothing in the retained percentages which was applicable to the assignment, the petitioner had no rights under the bond and could not have brought an action at law or in equity in its own name thereon. Newbury v. Lincoln, 276 Mass. 445, 450.
Exceptions overruled.