Lead Opinion
Fеderal Commerce and Navigation Company Limited (Federal) and Kane-matsu-Gosho, Ltd. (Kanematsu) have brought cross-appeals from Judge Metz-ner’s decision in the Southern District denying their cross-motions to modify an arbitration award on the grounds that the award exceeded the scope of the submission agreеment. We affirm.
Federal, which charters ocean-going vessels, and Kanematsu, an importer of grain to Japan, executed a master charter on June 8, 1970 for the shipment of nine cargoes of grain products from the United States to Japan. The master charter provided that the first shipment was to be mаde between October 16 and December 15, 1970 and thereafter one shipment would be made in each quarter of 1971 and 1972 at intervals not shorter than 50 days nor lоnger than 100 days. The charter further provided, “should any dispute arise between [Federal] and [Kanematsu], the matter in dispute shall be referred to the [arbitrators] . their decision . . . shall be final, and . . . may be made a rule of court.”
After the master charter had been agreed upon, an individual charter agreement сovering the first of the nine shipments was executed. This agreement provided that if Federal did not provide a vessel for the first shipment by December 15, 1970, Kanemаtsu had the option to cancel this voyage without penalty.
Federal designated the Martha Envoy to carry the first shipment, but the vessel did not arrive in port by December 15 and this voyage was evеntually can-celled by Kanematsu.
Federal nominated the Rolwi on December 29 to perform the second char
Federal then demanded arbitration over the refusal of the Rolwi and, on January 28, 1971 a panel of three arbitrators met. At the hearing Kanemat-su’s attorney indicated that he was prepared to arbitrate the validity of the entire master charter. Federal’s attorney argued that the arbitration should be limited to the dispute regarding the refusаl of the Rolwi and Federal sought an order to this effect in the Southern District. On March 2, 1971, Judge Frankel ordered “that either party may arbitrate all claims under the Mastеr Charter,” but by agreement of the parties, the pending arbitration was withdrawn.
Federal and Kanematsu then agreed, on April 8, 1971, to arbitrate
“certain disputes [which] have arisen under the charter party, to wit:
Charterer’s [Kanematsu] Claims
Charterer claims that the master charter dated June 8, 1970 is void by reason of various actions taken by Owner [Federal].
Owner’s Claims
Owner claims that the master charter dated June 8, 1970 is a valid, existing agreement which has not been voided by any action taken by the Owner.”
Hearings were held by thе arbitrators and, on April 28, 1971, an award issued. The award provided, “The first two cargoes and vessels under the Master Charter Party Contract are considered сan-celled without penalty to either party; and the remainder of the Master Charter Pax’ty as written is valid and must be performed by both parties commenсing during the third cargo period.”
Federal moved to amend the award, arguing that the arbitrators did not have the power to decide the validity of the individual charters, but could only consider the master charter in toto. Ka-nematsu moved to strike certain refer-enees in the arbitrators’ decision which were not contained in the award.
Judge Metzner denied both motions, holding that the arbitrators had the power to find the charter valid in part as they did and that the extraneous references were non-prejudicial and not contained in the award so that the court did not have the power to excise them. We agree.
An arbitrаtor is entitled to pass on every question of law or fact necessary to the disposition of the issue submitted to him. Here the arbitrators determined that the vаlidity of the master charter was affected by the status of the first two individual charters. At the very least, this determination was not in “manifest disregard,” Wilko v. Swan,
Federal asserts, however, that the arbitrators had exceeded the bounds of the submission agreement by passing on the validity of the individual contracts. But this judgment presupposеs a rule of law — that the validity of the master charter depended only on whether the delay in furnishing the first ship was a substantial breach of the contract. It is not thе function of a reviewing court, in the guise of interpreting the scope of the submission agreement, to substitute its judgment on the law for what the arbitrators thought with good rеason to be relevant. Amicizia Societa Navegazione v. Chilean Nitrate and Iodine Sales Corp.,
Overly technical judiciаl review of arbitration awards would frustrate the basic purposes of arbitration: to resolve disputes speedily and to avoid the expense and delay of extended court proceedings. Saxis S.S. Co. v. Multifacs
The references in the arbitrators’ decision to which Kanеmatsu took exception were harmless and, not being in the award are not subject to modification by this court.
Affirmed.
Dissenting Opinion
(dissenting):
The award of an arbitrator is enforcеable by a federal court only to the extent that he decides questions which the parties have submitted to him for arbitration. United Steelworkers of America v. Enterprise Wheel & Car Corp.,
In the present cаse the submission agreement is unambiguous. The parties had disagreed at the initial arbitration hearing as to the issue to be arbitrated: the validity of the master chаrter or only the Rolwi dispute. Thereafter, the parties agreed that the arbitrators should decide, in light of Federal’s actions, whether or not the master charter as a whole was valid. The individual disputes concerning the Rolwi and the Ionian Pioneer was not submitted to the arbitrators. The fact “that if the arbitrators held the master charter invalid, they would necessarily be ruling in favor of Kanematsu as to the individual charters” is irrelevant. The parties obviously foresaw that possibility when they agreed on the issue tо be arbitrated. In view of the unequivocal language of the submission agreement, as well as the facts of the case, “it may be said with positive assurancе that the arbitration clause is not susceptible of an interpretation that” the validity of the individual charters was submitted for arbitration. United Steelworkers of Amеrica v. Warrior & Gulf Navigation Co.,
I would grant the petition for an order striking all reference in the award to the Rolwi and the Ionian Pioneer, because “the arbitrators . . . awarded upon a matter not submitted to them . . .,” 9 U.S.C. § 11(b) (1970). Enterprise Wheel & Car Corp. v. United Steelworkers of America,
