77 N.J.L. 740 | N.J. | 1909
The opinion of the court was delivered by
This is a writ of error to the Atlantic Circuit removing a judgment founded upon a verdict directed for the plaintiff for $400 and interest. The suit was brought upon a written instrument guaranteeing the payment of rent accruing under a written lease. The lease was dated April 25th, 1904, made to the plaintiff by one Stone. The guaranty was endorsed upon the lease and was dated May 24th, 1904. Both the lease and guaranty were drawn in duplicate and were executed on the days of their respective dates. The defendant had directed Mrs. Stone, who subsequently became the tenant, to one Calloway, a real estate agent, to look about for tier for a house in Atlantic City which she might rent. The defendant had promised her to become surety for her rent before she went to Atlantic City. After Calloway had secured
There are endorsed upon the lease two payments—April 25th, $50; May 16th, $350. It is asserted that Mrs. Stone went into possession of the premises on the 16th of May, and that being in possession and having made a payment of rent the contract of leasing had become completed, and therefore, when the defendant afterward, on May 24th, signed the guaranty, that instrument was without consideration and unenforceable.
As before stated, the evidence shows that' the leases were not delivered but were held by Mr. Calloway awaiting the signature of the surety, and that the plaintiff had refused to accept them until the surety had signed. The contract of
In the present case the plaintiff had refused to deliver the lease and accept the first payment unless he had-security, and awaiting the promised signature of such surety the leases had remained in the hands of Mr. Calloway undelivered. The possession of the premises by the tenant before the delivery of the leases, if indeed the tenant was in possession, was a mere occupancy in contemplation of the subsequent delivery of the written lease with surety, and until such delivery the transaction was incomplete.
Williams v. Perkins, 21 Ark. 18, was a case where a payee of a writing obligatory took it at the time when it was executed by the principal obligors, and held it for some length of time before the signatures of the sureties were procured. At the time the writing was signed by the principal obligors it was understood that the sureties would also sign the bond. It was held that it did not follow that the writing obligatory was first made and signed by the principal obligors and accepted by the payee as a complete contract, and afterwards, at another time, the contract of the sureties was made as a distinct and independent transaction, because at the time it was signed by the principal obligors it was understood by the payee that the sureties would also sign and that the payee did not accept the writing obligatory as a complete contract until the signatures of the sureties were obtained. Although the
In Grim v. Semple, 39 Iowa 570, it was held that a bond to indemnify a surety upon a bond for costs was sustained by a sufficient consideration, although not executed until after the bond for costs, where it appeared that the latter was signed under a promise that the former should be given. See, also, Bowen v. Thwing, 56 Minn. 177; Smith v. Molleson, 148 N. Y. 241.
The landlord and tenant having executed the lease which the landlord refused to accept unless and until a promised surety had been obtained, it would seem to follow from the above cases that the engagement of the surety when entered into would have a valid consideration for its support.
There is much authority for the view that a contract induced by the promise of security thereafter to be given, affords sufficient consideration for the contract of suretyship when given.
Aside from the above doctrine, however, this case shows that the delivery of the lease did not occur until after the surety had signed, and therefore until such delivery the contract of letting tvas incomplete, even though the tenant in the meantime may have entered into the occupancy of the premises and paid an installment of rent.
The delivery of the lease being contemporaneous with the delivery of the surety’s obligation, each contract became completed at the same time, and the consideration which supports the principal contract supports the subsidiary one.
The contract of suretyship was therefore made upon sufficient consideration, and the court rightly refused the nonsuit, and also rightly refused to direct a verdict for the defendant, and was justified in directing a verdict for the plaintiff.
The judgment must be affirmed.
For reversal—None.