OPINION
FaulknerUSA, L.P., FaulknerUSA GP, Inc. (Faulkner), and Safeco Insurance Company of America (Safeco), appeal the trial court’s summary judgment in favor of Alaron Supply Company, Inc. (Alaron). We reverse.
BACKGROUND
Faulkner, as general contractor, entered into three contracts with Alaron, as subcontractor, to provide food service equipment, laundry service and equipment, and parking control system service and equipment at the San Antonio Convention Center Hotel. The food contract was for $2,306,000, the laundry contract was for $1,837,420, and the parking contract was for $349,037. Each contract required a 100 percent surety bond, which Safeco provided, and that 10 percent would be withheld as retainage. Further, each contract contained the following provision:
Condition Precedent to Payment by Owner to FaulknerUSA for the Subcontract Work is a condition precedent to Subcontractor’s payment by FaulknerU-SA. Subcontractor is entitled to payment only for that portion of the Subcontract Work for which FaulknerUSA has been paid by Owner. Subcontractor expressly assumes the risk of nonpayment by Owner. The Subcontract Amount includes compensation to Subcontractor for the assumption of this risk. This provision establishes a condition precedent, and it shall not be construed merely as a Time of Payment Clause.
Later, Alaron sued Faulkner and Safeco for suit on sworn account, breach of contract, and suit on payment bond. According to Alaron’s first amended petition, it fully or substantially performed under the three contracts and Faulkner and Safeco owed $790,577.74 for the services rendered. After verified denials were filed, Alaron moved for summary judgment. Although Faulkner and Safeco responded that Alaron’s summary judgment motion should be denied, they did not also move for summary judgment. The trial court granted summary judgment in favor of Alaron.
DISCUSSION
Faulkner raises nine issues on appeal. The first contends that the trial court erred by failing to sustain its objections to an affidavit attached to Alaron’s motion for summary judgment, the second alleges that the trial court failed to rule that an affidavit attached to Faulkner’s response to Alaron’s motion for summary judgment was sufficient to raise a fact issue, the third asserts that payment by the owner was a condition precedent to any payment to Alaron, the fourth contests whether there was a question of fact as to whether payment of retainage was due, the fifth challenges Alaron’s sworn account pleadings, the sixth contends that Faulkner filed a proper sworn denial to Alaron’s suit on sworn account, the seventh alleges that timely notice of bond was not given, the eighth asserts that Safeco was not subject to summary judgment, and the ninth contests whether judgment was proper against Faulkner “GP.” Finding merit in Faulkner’s third issue, we need not address the remaining claims. See Tex. R.App. P. 47.1 (“The court of appeals must hand down a written opinion that is as brief as practicable but that addresses ev *359 ery issue raised and necessary to final disposition of the appeal.”).
Standard of Review
Alaron moved for summary judgment on “traditional” grounds. Therefore, Alaron bore the burden to show that there was no genuine issue of material fact and that it was entitled to judgment as a matter of law. Tex. R. Crv. P. 166a(c). On appeal, we review Alaron’s motion and the evidence
de novo,
taking as true all evidence favorable to the nonmovant — Faulkner— and indulging every reasonable inference and resolving any doubts in Faulkner’s favor.
Valence Operating Co. v. Dorsett,
We further review
de novo
the construction of an unambiguous contract.
MCI Tel. Corp. v. Tex. Utils. Elec. Co.,
Condition Precedent
Condition precedents are events that must be performed before a right accrues to enforce a contract.
Hohenberg Bros. Co. v. George E. Gibbons & Co.,
The parties cite Gulf as controlling authority. In that case, the contract provided that:
When the owner or his representative advances or pays the general contractor, the general contractor shall be hable for and obligated to pay the sub-contractor up to the amount or percentage recognized and approved for payment by the owner’s representative less the retain-age required under the terms of the prime contract. Under no circumstances shall the general contractor be obligated or required to advance or make payments to the sub-contractor until the funds have been advanced or paid by the owner or his representative to the general contractor.
Gulf,
Although we agree with
Gulf
that we should be hesitant to find a condition precedent in a construction contract, we cannot turn a blind eye when, as here, the provision is an express condition precedent. Unlike the contract in
Gulf,
the provision here expressly states that payment to Faulkner by the owner was a “condition precedent” to payment to Alaron by Faulkner. The provision further states that Alaron is only entitled to payment for that portion of subcontract work that Faulkner has been paid for by the owner, and that Alaron “expressly assumes the risk of nonpayment by Owner.” Finally, the provision concludes that “[t]his provision establishes a condition precedent, and it shall not be construed merely as a Time of Payment Clause.” Such express language cannot be interpreted as a covenant that simply modifies the time and manner of payment, especially when the provision uses the term “condition precedent” and contemplates compensation for the assumption of risk of nonpayment until the owner pays Faulkner. We therefore conclude that the provision is an enforceable, express condition precedent.
See MidAm-erica Const. Management, Inc. v. MasTec North America, Inc.,
Alaron asserts that a reading of the entire contract does not support our finding that the above provision is a condition precedent. Specifically, Alaron points to another provision in the contract, which provides that final payment will be made “no later than thirty (30) days after inspection and verification by FaulknerUSA and Owner, payment by Owner to FaulknerU-SA, and the satisfaction of all other conditions required for payment.” Had the *361 contract not included the condition-precedent clause and compensation for the assumption of the risk, we would find merit in Alaron’s argument as the “no later than thirty days” clause resembles more of a covenant that modifies the time and manner of payment similar to that found in Gulf. However, the contract at issue in Gulf did not also specifically include a condition precedent clause for payment. The one before us does.
Because the provision is a condition precedent, whether the owner paid Faulkner such that Faulkner was obligated to pay Alaron was a material fact issue necessary to resolution of Alaron’s suit on sworn account, breach of contract, and suit on payment bond. Logically, if the owner has not paid Faulkner, Alaron cannot succeed on its theories of liability. Here, Alaron presented no evidence, much less made any allegation, that the owner paid Faulkner, and Faulkner alleged, through the affidavit of Donna Jenkins, that the owner had not paid Faulkner. 1 Consequently, we conclude that the trial court erred by granting summary judgment in favor of Alaron.
CONCLUSION
Having sustained Faulkner’s third issue, we reverse the trial court’s judgment and remand for further proceedings.
LARSEN, J., sitting by assignment.
Notes
. Alaron seemingly contends that we must infer that the trial court, by granting summary judgment in its favor, did not consider Jenkins' affidavit. Alaron did not object to Jenkins’ affidavit, and there is nothing in the record to indicate that the trial court did not consider it. Alaron contends that Jenkins’ affidavit is substantively defective. We need not address this contention as Faulkner did not move for summary judgment and we must take as true all evidence favorable to Faulkner, the nonmovant, indulging every reasonable inference and resolving any doubts in Faulkner's favor.
Valence,