Lead Opinion
This case was previously before us in Farber v. State,
The Farbers filed suit against defendant-respondent State of Idaho and defendants City of Nampa and Asphalt Paving and Construction Company, alleging a right to recover damages, primarily for the negligent planning, construction and design of the project. The Farbers’ amended complaint also sought to recover damages for the wrongful taking of a portion of their property.
A formal claim for dаmages against the defendant City of Nampa was filed on October 10, 1973, as provided by the Idaho Tort Claims Act (ITCA), I.C. § 6-901, et seq. A complaint against the state was filed on April 11, 1974. This complaint did not specifically refer to the ITCA. On June 11, 1974, the state moved to dismiss the action because of the Farbers’ failure to file timely notice of the claim with the state under the ITCA. On August 12, 1974, prior to a hearing on the state’s motion to dismiss, the Farbers filed a formal notice of claim with the state. They then filed an amended complaint, and the state again moved to dismiss for failure to comply with the ITCA. The district court granted the motion and dismissed with prejudice. The Farbers appealed that dismissal to this Court. In Farber v. State, supra, this Court dismissed the appeal because the lower court dismissal had not been certified as final pursuant to I.R.C.P. 54(b).
The Farbers subsequently filed in district court a motion to reconsider the granting of the state’s motion to dismiss. This motion was denied and a final order of dismissal was entered pursuant to Rule 54(b). The order denying the motion to reconsider specifically provided:
“1. That Plaintiffs’ Motion to Reconsider this Court’s earlier Order Granting the Státe of Idaho’s Motion to Dismiss is denied, except as hereafter set forth.
“2. That all claims by Plaintiffs against the State of Idaho based on tort or negligence contained in Plaintiffs’ Amended Complaint in the above-entitled matter are hereby dismissed with prejudice on the ground and for the reason that Plaintiffs havе failed to conform with the requirements of Idaho Code, Section 6-905, all as stated in this Court’s earlier Order Granting Motion to Dismiss dated September 2, 1975.
“3. That any claims Plaintiffs may have against the State of Idaho for inverse condemnation shall be preserved and Plaintiffs may amend their Amended Complaint to allege a cause of action based оn inverse condemnation against the State of Idaho.”
The Farbers contend on appeal that the district court erred in concluding that their claim did not meet the notice requirements of the ITCA. The Farbers also argue that the district court’s order improperly excludes claims for tort damages which are severe enough to constitutе a taking. In light of our disposition of the first issue, we need not decide the effect of the court’s
I.C. § 6-905
“Filing claims against state or employee — Time. All claims against the state arising under the provisions of this act and all claims against an employee of the state for any act or omission of the employee within the course or scopе of his employment shall be presented to and filed with the secretary of state within one hundred twenty (120) days from the date the claim arose or reasonably should have been discovered, whichever is later.”
The Farbers contend that their claim did not “arise” within the meaning of I.C. § 6-905 until April 29, 1974, the date that construction on the project was complеted and the project was approved by the state. Since the Farbers’ notice was filed on August 12, 1974 (105 days after April 29), if the Farbers’ contention as to the date their claim arose is correct, then they have fulfilled the notice requirements of the ITCA.
We have not previously addressed the question of when the 120 day notice requirement begins to run in сases of continuing torts involving damage to property. In support of their position that the 120 day provision begins to run from the time that the contract is approved by the state, the Farbers cite Gillam v. City of Centralia,
“[Wjhere a municipality, without condemnation proceedings, takes or damages private property for a public improvement, the stаtute of limitations does not commence to run against the property owner’s right of action for compensation until construction of the improvement has been entirely completed or until operations thereon have ceased for such a period of time as reasonably to indicate that the project has bеen abandoned.”128 P.2d at 663 .
Washington courts have steadfastly adhered to this rule. See Vern J. Oja & Associates v. Washington Park Towers, Inc.,
The state argues the general rule that “a cause of action arises or accrues . . . when the plaintiff could have first maintained the action to a successful conclusion,” 51 Am. Jur.2d Limitation of Actions § 107 (1970), and that “[i]f an actual injury to real property occurs, suit must be brought within the рeriod of limitation by the property owner not only for the actual injury that has occurred but also for any additional injuries which were foreseeable and estimable when the initial damage was suffered.” 51 Am. Jur.2d Limitation of Actions § 121 (1970). The state then argues that since the Farbers filed a claim against the City of Nam-pa on October 10,1973, and since that claim specified damages nearly identical to the damages claimed in their April 11, 1974 complaint against the state, the Farbers could have maintained a suit against the state as early as October of 1973.
In Ralphs v. City of Spirit Lake,
In Ralphs, a single act caused the damage for which compensation was claimed. While the damages alleged were continuing, and their full extent unknown, the act complained of was completed, and some damages had apparently occurred, long before the notice of claim was filed. Here, the act complained of is in the nature of a continuing tort. While the damages complained of have occurred over a pеriod of time, as in Ralphs, we feel that it is better policy to focus upon the act complained of, rather than the damages, in determining when the 120 day notice requirement of the ITCA is triggered. Thus the holding in Ralphs that “[wjhere there is a coincidence of a negligent act and the occurrence of damages a ‘wrongful act’ has been committed” is not determinative of whether a “negligent act” should be defined as the first step in a continuing project, or as the project as a completed whole.
In interpreting the meaning of the word “act” in I.C. § 6-905, it must be remembered that the 120 day notice provision of I.C. § 6-905 is not itself a statute of limitation. A separate section of the ITCA provides for limitation of actions under the Act. See I.C. § 6-911; Independent School District v. Callister,
Our conclusion is founded upon the legislative intent behind the nоtice requirement and several important policy considerations. The purposes of I.C. § 6-905 are to (1) save needless expense and litigation by providing an opportunity for amicable resolution of the differences between parties, (2) allow authorities to conduct a full investigation into the cause of the injury in order to detеrmine the extent of the state’s liability, if any, and (3) allow the state to prepare defenses. See Newlan v. State,
Independent policy considеrations dictate a similar result. First, the need for certainty, and the resulting increase in efficiency of administration, suggests that interpreting the Act to provide clearly ascertainable dates from which the notice requirement will run is a desirable approach. In the case of damages arising from action taken pursuant to a contract with the state, the date that the state approves the work and accepts the contract provides an easily discernible point from which to gauge compliance with the time limits of the notice requirement.
Secondly, our interpretation of I.C. § 6-905, as it applies to continuing torts arising out of projects for which the state сontracts, is consistent with our announced policy of liberally construing statutes “with a view to accomplishing their aims and purposes, and attaining substantial justice,” Keenan v. Price,
The summary judgment is reversed and the case is remanded for further proceedings consistеnt with this opinion.
Notes
. I.C. § 6-905 was amended in 1976, after the Farbers initiated this action. The amendments are not relevant, however, to the Farbers’ contentions.
. I.C. § 5-241 states that:
“Actions [arising out of the design or construction of improvements to real property] will be deemed to have accrued and the statute of limitations shall begin to run ... as follows:
“(a) Tort actions . . . shall аccrue ... six (6) years after the final completion of construction ....
“(b) Contract actions shall accrue and the applicable limitation statute shall begin to run at the time of final completion of construction of such an improvement.” (Emphasis added). Our legislature has thus expressed the same general approach to determining when a cause of action accrues for damages arising out of a construction project as the court in Gillam.
. We do not suggest that it would be improper to file an ITCA notice of claim prior to completion of a project. We simply address the question of the last possible day upon which a notice meeting the requirements of the Act must be filed.
. We are fully aware that other noncontract activities undertaken by the state may occur over a long period of time and thus constitute a “continuing tort,” but without a definite date of completion to trigger the running of the notice period. We do not address the question of when the notice period begins to run in these noncontract continuing tort cases.
Dissenting Opinion
dissenting.
The majority recognizes the applicability of Ralphs v. City of Spirit Lake,
“Where there is a coincidence of a negligent аct and the occurrence of damages a ‘wrongful act’ has been committed for which a legal remedy in damages is generally available. Therefore the applicable statutes begin to run from the occurrence of the wrongful act albeit the full extent of the damages may be unknown or unpredictable at that initial time.”98 Idaho at 227 ,560 P.2d at 1317 .
The majority also notes that Ralphs would appear to be dispositive of the issue presented by appellants absent “compelling reasons” for distinguishing the circumstances of the two cases.
Appellants filed such a notice of claim against the city of Nampa on October 10, 1973, and at that time were apparently aware of the state’s potential liability. This awareness is reflected by the fact that a letter of complaint, though not of notice of claim, dated August 21, 1973, was delivered to the state Department of Transportation, Division of Highways, some two months prior to thе filing of notice of claim against the city. This letter, the record indicates, was followed by a meeting and a detailed written response from the state. Moreover, appellants filed, on April 11, 1974, an action sounding in tort against the state as well as the city. Thus the record reflects that appellant’s claim against the state, which under Ralphs requirеs but the occurrence of a wrongful act together with damage, was probably known as of August or October, 1973; at any rate, it was necessarily and certainly known prior to the filing of the suit against the state and others in April, 1974.
Even assuming that knowledge of the claim against the state was not had by appellants until shortly before the filing of the April action, notice of the claim, as required by the act, was not filed until over 120 days had passed. Not only was the time limit for providing notice of claims not met, the statutory scheme providing for prelitigation notice and allowance or denial of claims was frustrated. As we noted in Newlan, supra,
. One of these “compelling reasons” appears to be based on the argument that damages or the extеnt of liability may be difficult to determine in the case of a “continuing” tort. Here, how
