J. R. FARBER аnd Amelia V. Farber, husband and wife, Plaintiffs-Appellants, v. The STATE of Idaho, The City of Nampa, Asphalt Paving and Construction Co., Inc., a corporation, Defendants, and The State of Idaho, Defendant-Respondent. ASPHALT PAVING AND CONSTRUCTION CO., INC., a corporation, Cross-Plaintiff, v. The STATE of Idaho, Cross-Defendant.
No. 13212
Supreme Court of Idaho
July 7, 1981
630 P.2d 685
J. R. FARBER and Amelia V. Farber, husband and wife, Plaintiffs-Appellants,
v.
The STATE of Idaho, The City of Nampa, Asphalt Paving and Construction Co., Inc., a corporation, Defendants,
and
The State of Idaho, Defendant-Respondent.
ASPHALT PAVING AND CONSTRUCTION CO., INC., a corporation, Cross-Plaintiff,
v.
The STATE of Idaho, Cross-Defendant.
No. 13212.
Supreme Court of Idaho.
July 7, 1981.
Kenneth E. White, Nampa, for plaintiffs-appellants.
Warren E. Jones of Eberle, Berlin, Kading, Turnbow & Gillespie, Boise, for respondent.
BISTLINE, Justice.
This case was previously before us in Farber v. State, 98 Idaho 928, 576 P.2d 209 (1978). A brief summary of the facts as set forth in that opinion is as follows: The action arises from the reconstruction of Twelfth Avenue South and Seventh Street South in Nampa, Idaho. Respondent State of Idaho entered into a cooperative agreement with defendant City of Nampa for the reconstruction project, and defendant Asphalt Paving and Construction Company was awarded the contract to perform the reconstruction work. Appellants, the Farbers, own a building and lot located at the intersection of Twelfth Avenue South and Seventh Street South, both of which were affected by the reconstruction wоrk.
The Farbers filed suit against defendant-respondent State of Idaho and defendants City of Nampa and Asphalt Paving and Construction Company, alleging a right to recover damages, primarily for the negligent planning, construction and design of the project. The Farbers’ amended complaint also sought to recover damages for the wrongful taking of a portion of their property.
A formal claim for damages against the defendant City of Nampa was filed on October 10, 1973, as provided by the Idaho Tort Claims Act (ITCA),
The Farbers subsequently filed in district court a motion to reconsider the granting of the state‘s motion to dismiss. This motion was denied and a final order of dismissal was entered pursuant to
“1. That Plaintiffs’ Motion to Reсonsider this Court‘s earlier Order Granting the State of Idaho‘s Motion to Dismiss is denied, except as hereafter set forth.
“2. That all claims by Plaintiffs against the State of Idaho based on tort or negligence contained in Plaintiffs’ Amended Complaint in the above-entitled matter are hereby dismissed with prejudice on the ground and for the reason that Plaintiffs have failed to cоnform with the requirements of Idaho Code, Section 6-905, all as stated in this Court‘s earlier Order Granting Motion to Dismiss dated September 2, 1975.
“3. That any claims Plaintiffs may have against the State of Idaho for inverse condemnation shall be preserved and Plaintiffs may amend their Amended Complaint to allege a cause of action based on inverse condemnation agаinst the State of Idaho.”
The Farbers contend on appeal that the district court erred in concluding that their claim did not meet the notice requirements of the ITCA. The Farbers also argue that the district court‘s order improperly excludes claims for tort damages which are severe enough to constitute a taking. In light of our disposition of the first issue, we neеd not decide the effect of the court‘s
“Filing claims against state or employee—Time. All claims against the state arising under the provisions of this act and all claims against an employee of the state for any act or omission of the employee within the course or scope of his employment shall be presented to and filed with the seсretary of state within one hundred twenty (120) days from the date the claim arose or reasonably should have been discovered, whichever is later.”
The Farbers contend that their claim did not “arise” within the meaning of
We have not previously addressed the question of when the 120 day notice requirement begins to run in cases of continuing torts involving damage to property. In support of their position that thе 120 day provision begins to run from the time that the contract is approved by the state, the Farbers cite Gillam v. City of Centralia, 14 Wash.2d 523, 128 P.2d 661 (1942), which held that:
“[W]here a municipality, without condemnation proceedings, takes or damages private property for a public improvement, the statute of limitations does not commence to run against the property owner‘s right of action for cоmpensation until construction of the improvement has been entirely completed or until operations thereon have ceased for such a period of time as reasonably to indicate that the project has been abandoned.” 128 P.2d at 663.
Washington courts have steadfastly adhered to this rule. See Vern J. Oja & Associates v. Washington Park Towers, Inc., 89 Wash.2d 72, 569 P.2d 1141 (1977) (cause of action for damage tо apartment building from use of pile-driver accrues upon completion of the project); Papac v. City of Montesano, 49 Wash.2d 484, 303 P.2d 654 (1956) (statute of limitations for damage to land runs from time project is completed, or substantial injury occurs, whichever is later). See also Shockley v. Public Service Co., 525 P.2d 1183 (Colo.App. 1974) (statute of limitations for cause of action arising out of public road improvement runs from time project is comрleted); Ashmon v. City of Des Moines, 209 Iowa 1247, 228 N.W. 316 (1929) (statute of limitations runs from time construction project is completed). As a policy reason for adopting their position, the Farbers suggest that they cannot know the full extent of their damages until the project is complete. They urge that this is particularly true where the state retains the right to require changes in the work prior to approvаl.
The state argues the general rule that “a cause of action arises or accrues . . . when the plaintiff could have first maintained the action to a successful conclusion,” 51 Am. Jur.2d Limitation of Actions § 107 (1970), and that “[i]f an actual injury to real property occurs, suit must be brought within the period of limitation by the property owner not only for the actual injury that has occurred but also for any additional injuries which were foreseeable and estimable when the initial damage was suffered.” 51 Am. Jur.2d Limitation of Actions § 121 (1970). The state then argues that since the Farbers filed a claim against the City of Nampa on October 10, 1973, and since that claim specified damages nearly identical to the damages claimed in their April 11, 1974 complаint against the state, the Farbers could have maintained a suit against the state as early as October of 1973.
In Ralphs v. City of Spirit Lake, 98 Idaho 225, 560 P.2d 1315 (1977), this Court examined a similar issue arising out of a personal injury case. The plaintiff there had been
In Ralphs, a single act caused the damage for which compensation was claimed. While the damages alleged wеre continuing, and their full extent unknown, the act complained of was completed, and some damages had apparently occurred, long before the notice of claim was filed. Here, the act complained of is in the nature of a continuing tort. While the damages complained of have occurred over a period of time, as in Ralphs, we feel that it is better policy to focus upon the act complained of, rather than than the damages, in determining when the 120 day notice requirement of the ITCA is triggered. Thus the holding in Ralphs that “[w]here there is a coincidence of a negligent act and the occurrence of damages a ‘wrongful act’ has been committed” is not determinative of whether а “negligent act” should be defined as the first step in a continuing project, or as the project as a completed whole.
In interpreting the meaning of the word “act” in
Our conclusion is founded upon the legislative intent behind the notice requirement and sеveral important policy considerations. The purposes of
Independent policy considerations dictate a similar result. First, the need for certainty, and the resulting increase in efficiency of administration, suggests that interpreting the Act to provide clearly ascertainable dates from which the notice requirement will run is a desirable approach. In the case of damages arising from action taken pursuant to a contract with the state, the date that the state approves the work and accepts thе contract provides an easily discernible point from which to gauge compliance with the time limits of the notice requirement.4
Secondly, our interpretation of
The summary judgment is reversed and the case is remanded for further proceedings consistent with this opinion.
BAKES, C. J., and DONALDSON, J., concur.
McFADDEN, Justice, dissenting.
The majority recognizes the applicability of Ralphs v. City of Spirit Lake, 98 Idaho 225, 560 P.2d 1315 (1977), where it is stated:
“Where there is a coincidence of a negligent act and the occurrence of damages a ‘wrongful act’ has been committed for which a legal remеdy in damages is generally available. Therefore the applicable statutes begin to run from the occurrence of the wrongful act albeit the full extent of the damages may be unknown or unpredictable at that initial time.” 98 Idaho at 227, 560 P.2d at 1317.
The majority also notes that Ralphs would appear to be dispositive of the issue presented by appellants absent “compelling reasons” for distinguishing the circumstances of the two cases.1 I fail to see such reasons.
Appellants filed such a notice of claim against the city of Nampa on October 10, 1973, and at that time were apparently aware of the state‘s potential liability. This awareness is reflected by the fact that a letter of complaint, though not of notice of claim, dated August 21, 1973, was delivered to the state Department of Transportation, Division of Highways, some two months prior to the filing of notice of claim against the city. This letter, the record indicates, was followed by a meeting and a detailed written response from the state. Moreover, appellаnts filed, on April 11, 1974, an action sounding in tort against the state as well as the city. Thus the record reflects that appellant‘s claim against the state, which under Ralphs requires but the occurrence of a wrongful act together with damage, was probably known as of August or October, 1973; at any rate, it was necessarily and certainly known prior to the filing of the suit against the statе and others in April, 1974.
Even assuming that knowledge of the claim against the state was not had by appellants until shortly before the filing of the April action, notice of the claim, as required by the act, was not filed until over 120 days had passed. Not only was the time limit for providing notice of claims not met, the statutory scheme providing for prelitigation notice and allowance or denial of claims was frustrated. As we noted in Newlan, supra, 96 Idaho at 716, 535 P.2d at 1353, the language of the ITCA, that no claim or action shall be allowed unless the claim has been presented and filed within the time limits and in the manner prescribed by the act, is clear and unambiguous and without such compliance the suit cannot be maintained. I believe dismissal of the action was proper.
SHEPARD, J., concurs.
Notes
Our legislature has thus expressed the same general approach to determining when a cause of action accrues for damages arising out of a construction project as the court in Gillam.“Actions [arising out of the design or construction of improvements to real property] will be deemed to have accrued and the statute of limitations shall begin to run as follows:
“(a) Tort actions . . . shall accrue . . . six (6) years after thе final completion of construction . . .
“(b) Contract actions shall accrue and the applicable limitation statute shall begin to run at the time of final completion of construction of such an improvement.” (Emphasis added).
