OPINION
Fall River Rural Electric Cooperative, Inc. (Fall River) petitions for review of two Federal Energy Regulatory Commission (FERC) orders. Fall River applied for a license to construct, operate, and maintain a new hydroelectric power generating facility at Hebgen Dam on the Madison River in Gallatin County, Montana. In its orders FERC dismissed Fall River’s license application and denied Fall River’s request to hold the proceeding in abeyance,
Fall River Rural Elec. Coop., Inc.,
111 ¶
The Missouri-Madison Hydroelectric Project develops hydropower on a 324-mile stretch of the Madison and Missouri Rivers in southwestern Montana. The project is licensed to Pennsylvania Power and Light Montana, LLC (PPL) under FERC Project No. 2188.
PP & L Montana, LLC,
Hebgen Dam is an earth-filled structure with a concrete core wall and is 721 feet long and 85 feet high. Discharges from Hebgen Reservoir are controlled by outlet works consisting of an intake tower, a conduit through the dam, and a conduit outlet. The intake tower includes four openings, two of which are presently closed with timber stoplogs, while the other two are used for reservoir discharges. Water passes from the intake tower through the dam structure in a woodstave-lined conduit, which has an unreinforced concrete encasement and is approximately 785 feet long and twelve feet in diameter. The conduit outlet is an irregularly-shaped concrete box structure at the toe of the dam that directs discharges into the Madison River. The Hebgen Development also includes a spillway, which is located on the right abutment of the dam.
In 2001, FERC granted Fall River a three-year preliminary permit to conduct investigations and to secure data necessary to determine the feasibility of a hydroelectric development project at Hebgen Dam.
Symbiotics, LLC,
In May 2004, Fall River filed its Final License Application for the proposed Heb-gen Dam Hydroelectric Project No. 11882. In its application, Fall River proposed several modifications and additions to the existing Hebgen Development. First, Fall River proposed constructing a powerhouse with a single turbine generator unit eighty feet downstream from the toe of the dam and immediately north of the present conduit outlet. Discharges would be made through a submerged concrete-lined draft tube below the surface of the tailwater. Second, Fall River proposed pressure-grouting and steel-lining the conduit because it was not designed to withstand the full reservoir pressure required for power generation. Third, Fall River proposed bifurcating the conduit approximately 50 to 60 feet upstream of the current conduit outlet. Fall River proposed installing a steel penstock ten feet in diameter to direct the flow from the existing conduit to the proposed powerhouse. The bifurcation and isolation valves would be located in a new concrete valve house upstream of the proposed powerhouse. Fifth, a new power transmission line would be installed to connect the plant electrical output to Fall River’s existing Hebgen substation near Grayling, Montana. Sixth, and finally, Fall River proposed using all four of the
While Fall River’s license application did not propose modifying the existing spillway, PPL would have to use the spillway for all discharges during approximately three months of the construction period. Once completed, the powerhouse would operate in “run-of-river mode,” and would utilize flow releases from Hebgen Dam as determined under PPL’s license. Fall River would not have access to reservoir storage for additional power generation.
In July 2004, FERC informed Fall River by letter that its license application potentially conflicted with Section 6 of the Federal Power Act (FPA), 16 U.S.C. § 799. 2 Specifically, FERC stated that it “cannot, without [PPL’s] concurrence, approve a development proposal that would materially affect or modify the licensed project. Without PPL’s consent to [Fall River’s] proposed modifications to Project No. 2188, [Fall River’s] application would be precluded by the requirements of FPA Section 6 and therefore would be subject to rejection under 18 C.F.R. § 4.32(e)(2).” 3 However, because Fall River was in the process of negotiating a site use and operations agreement with PPL, FERC stated that it would “continue to process [Fall River’s] application, conditioned on [Fall River] filing ... additional information showing that PPL has not ruled out an agreement to the modifications to its Project No. 2188.” FERC required Fall River to provide this information within thirty days and by the end of each subsequent sixty-day period. Fall River did so, filing five status reports between August 2004 and May 2005.
Just before Fall River filed its last status report, however, PPL sent a letter to Fall River terminating negotiations. The letter stated that “the negotiations with [Fall River] over an extehded period have not been successful” and that PPL was “not interested in proceeding any further with negotiations.” PPL also filed a copy of the letter with FERC.
In its final status report, after noting PPL’s letter and recognizing that “it appeared] that negotiations ha[d] come to a stalemate,” Fall River declared its “intent to continue it’s [sic] efforts to resolve there [sic] difference’s[sic] with PPL in the hopes of coming to an acceptable financial arrangement.” Fall River further noted that “prior to PPL’s letter of January 17, 2005 there ha[d] been no objection by PPL for the licensing and development of additional generation at the Hebgen Dam,” and therefore requested that FERC “continue to move forward with the licensing of the Hebgen Dam project.” Alternatively, if FERC “fe[lt] it [was] unable to proceed with the licensing” in the absence of PPL’s consent, Fall River requested that FERC “hold the licensing process in abeyance
PPL then sent a letter to FERC to “supplement and clarify” certain issues in Fall River’s status report. PPL stated: “[0]n April 29, 2005, PPL Montana notified Falls Riverfsic] that it was terminating negotiations for a site agreement. As PPL Montana has already communicated to Falls Riverfsic] and NPSI, we do not intend to resume these negotiations for the installation of additional generation at the Hebgen Development by Falls River [sic] or NPSI.” 4
Shortly thereafter, the Director of FERC’s Division of Hydropower Licensing dismissed Fall River’s license application and denied its request to hold the application in abeyance. Fall River Rural Elec. Coop., Inc., 111 FERCT 62,333 (2005) (the Dismissal Order). The Director concluded that Fall River’s proposed project is barred under FPA Section 6 because it “would substantially alter PPL Montana’s licensed project works” without PPL’s consent. Id. at 64,733. The Director specifically noted Fall River’s proposals to modify the “existing intake structure by inserting new gates and screens in two presently-closed intake openings,” to bifurcate the outlet conduit, to install a pen-stock extending to a new powerhouse, and that “installation of its valve house to bifurcate the Hebgen outlet conduit ... will require extensive excavation of the earth fill covering the conduit.” Id. The Director concluded, “[t]hese are the types of modifications to a licensed project that the Commission has found require the licensee’s consent under Section 6 of the FPA.” Id. Therefore, “[w]ithout PPL Montana’s consent for these alterations, the application must be dismissed ... without prejudice to Fall River re-filing its application, in the event it is able to obtain PPL Montana’s consent for use of the Hebgen Development.” Id. The Director further concluded that because of PPL’s intention not to resume negotiations, “[n]o public purpose would be served by continuing to process the application or to hold the application in abeyance.” Id.
Fall River then filed a request for rehearing, which a panel of three commissioners denied.
Fall River Elec. Coop., Inc.,
After explaining that “a substantial alteration may result ... from significant alterations to project works” alone,
id.
at 61,509, the panel also concluded that “the potential for ... joint-use operational problems would be a substantial alteration
The panel also concluded that FERC’s prior issuance of a preliminary permit was not inconsistent with its dismissal of Fall River’s license application, in light of the limited purpose of the preliminary permit and the intervening breakdown in negotiations between PPL and Fall River. Id. at 61,510. Finally, the panel rejected Fall River’s arguments that PPL either expressly consented to future modifications of its license by accepting Standard Articles 9 and 10 in its Missouri-Madison license, or had “impliedly consented” by expressing no opposition to Fall River’s preliminary permit application or its final license application, or by cooperating with Fall River for years before abruptly terminating negotiations. Id. at 61,510-11.
Fall River timely petitioned for review of both the Dismissal Order and the Rehearing Order.
II. Standards of Review
Under the Administrative Procedure Act, this court reviews decisions by FERC to determine whether the agency action was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. 5 U.S.C. § 706(2);
Cal. Dep’t of Water Res. v. FERC,
III. Discussion
A. Substantial Evidence of an “Alteration” Under Section 6 of the FPA
Fall River first argues that because its proposal would not substantially or materially alter PPL’s project’s configuration, mode of operations, or power generation, FERC’s orders are not supported by substantial evidence. We disagree.
Section 6 of the FPA states that licenses “may be altered ... only upon mutual agreement between the licensee and the Commission....” 16 U.S.C. § 799. The term “altered” is not statutorily defined; however, both parties agree that in order to violate Section 6, a proposed project must
substantially
alter an existing license. As neither party disputes the relevant standard, for purposes of this appeal we assume without deciding that in order for Section 6 of the FPA to apply, a proposed project must substantially alter an
Under FERC precedent, “[w]hat constitutes an ‘alteration’ for Section 6 purposes is primarily a factual issue to be determined in each case.”
Universal Elec. Power Co.,
In this case, FERC concluded that both Fall River’s proposed physical modifications to the Hebgen Development and the possible operational impacts to the Missouri-Madison project constitute “substantial alterations” of PPL’s license.
FERC first explained in its Rehearing Order that the “proposed project requires alterations of the existing project’s facilities that are much greater than the kind of physical alterations the Commission has previously found to be insubstantial.”
Fall River first objects to FERC’s finding that its proposal includes installing screens on the intake tower. Though screens were mentioned on multiple occasions in the documents supporting Fall River’s license application, Fall River is correct that screens were not part of its final license application. Nevertheless, Fall River does not dispute that it proposes making physical alterations to the intake tower, namely removing the timber stoplogs from the two presently-closed intake openings and installing two new intake gates in their place.
Fall River next notes that excavation would be limited to a relatively small area on the downstream toe of the dam, and would not amount to the “excavation of a large area of the dam” described by FERC. Fall River asserts that the excavation would be limited to the hillside over the downstream sixty feet of the conduit. There is no dispute, however, that the proposed excavation requires removing approximately 3,100 square feet of soil for construction of the new powerhouse and valve house. Fall River simply prefers to characterize this as excavating a “relatively small area” rather than a “large area.”
Next, while conceding that it proposes relining the conduit, Fall River objects to FERC’s finding that the outlet conduit will be “reconfigured.” However, the license
After discussing the aforementioned physical alterations, FERC also concluded that in this case the potential for “joint-use operational problems would be a substantial alteration of the existing license.”
Fall River contends that FERC’s conclusion with respect to PPL’s operations is purely speculative and has no basis in evidence. Again, we disagree. It is undisputed that Fall River’s license application proposes closing the intake gates and conduit during approximately three months of the construction period, with all discharges being made via the spillway during this time. It is also undisputed that Fall River proposes discharging water below the tail-water’s surface rather than allowing the flow to drop into the tailwater, as it currently does. Finally, in its “official response” to Fall River’s draft license application, Montana Fish, Wildlife and Parks recommended that Fall River incorporate the following language into its license: “If future monitoring results indicate that significant entrainment is occurring and that screening is a necessary and effective option for reducing entrainment, then screening the intake may be required at some future date.” (Emphasis added.)
Choosing to focus on the impact of each of these proposed modifications individually, Fall River apparently does not appreciate the cumulative impact of its proposed project. Fall River proposes doubling the number of intake openings used and installing new gates on the intake tower, thereby increasing pressure within the conduit. Fall River proposes steel-lining and pressure-grouting the conduit because it “was not designed to withstand the full reservoir pressure which would be required for power generation.” Rather than using the existing conduit outlet, Fall River proposes bifurcating the conduit and installing a new penstock. Rather than having discharges drop into the tailwater below the conduit outlet as they currently do, Fall River proposes releasing water below the tailwater’s surface. During approximately three months of construction, Fall River proposes making all discharges via the spillway, which is not ordinarily used for discharges and has no backup, as it is the backup. Collectively, these alterations fundamentally change the physical characteristics and operation of the Heb-gen Development. Admittedly, FERC cannot know whether certain operational problems will arise, but neither can Fall River ensure that they will not. However, FERC’s ability to accurately predict the future is rather beside the point. Here, there is much more than a “mere scintilla” of evidence supporting FERC’s conclusion that Fall River’s proposal would substantially alter PPL’s license; therefore, it is supported by substantial evidence. In sum, we conclude that each of FERC’s factual findings with respect to Fall River’s proposed physical alterations and operational interferences with PPL’s license are supported by substantial evidence, and that FERC’s conclusion that Fall River’s proposal would substantially alter PPL’s
B. FERC Precedent
Fall River next argues that FERC’s orders are inconsistent with its precedents and are therefore not entitled to deference. In its Rehearing Order FERC analyzed Fall River’s proposed project by applying both cases involving a substantial alteration of an existing license, and cases where it found no substantial alteration.
1. Cases Finding a Substantial Alteration
In
Niagara Mohawk Power Corporation,
FERC rejected a license application that proposed a two-phase modification of an existing development.
In
JDJ Energy Company,
FERC rejected a preliminary license application that proposed modifying approximately 75 feet of an existing dam and modifying an existing powerhouse to accommodate construction of a new powerhouse.
In
Green Island Power Authority,
FERC rejected a preliminary license application that proposed constructing a new dam that would inundate an existing dam, decommissioning various other facilities, thereby rendering an existing project inoperable.
2. Cases Finding No Substantial Alteration
In
Weber Basin Water Conservancy District,
FERC granted a license that proposed installing a penstock underneath an existing canal.
In
Howard W. Bair,
FERC granted a preliminary permit that proposed utilizing an existing fish water release pipe and constructing a powerhouse.
Finally, in both
PG & E,
In sum, we disagree with Fall River’s argument that FERC’s orders are inconsistent with its precedents. In citing these cases, FERC did not suggest they are on all fours factually with Fall River’s proposed project. Instead, FERC used these cases as examples of instances where alterations were substantial and where they were not. As FERC explained in its Rehearing Order, “[t]he degree of encroachment that makes an alteration ‘substantial’ is a case-specific determination.”
C. Preliminary Permit
Fall River next argues that FERC’s orders are inconsistent with its regulations and with its issuance of a preliminary permit in this case because Fall River’s Preliminary Permit Application was substantially identical to its Final License Application. Fall River contends that this change in policy must be supported by a reasoned explanation.
See generally Flagstaff Med. Ctr., Inc. v. Sullivan,
We cannot say that it was “clear” at the preliminary permit stage that Fall River’s proposed project would substantially alter PPL’s license, nor can we say that there was a “permanent legal barrier” to Fall River’s proposed project when FERC issued the preliminary permit. In fact, Fall River discussed developing Hebgen Dam with PPL in early 2001, and at that time PPL agreed that Fall River could and would make an application for a preliminary permit, and that it would negotiate a site use agreement with Fall River.
In granting Fall River’s preliminary permit, FERC noted Fall River’s representation “that they will not impact [PPL’s] project.”
D. Consent
Fall River’s final argument is that FERC failed to adequately consider whether PPL impliedly consented to Fall River’s proposed project by not intervening in, protesting, or commenting on either the Preliminary Permit Application or the Final License Application.
In its Rehearing Order, FERC noted Fall River’s argument that “PPL has impliedly consented by expressing no opposition to Fall River’s preliminary permit or filing no comments in response to its license application proposal.”
Nevertheless, Fall River does not cite a single case requiring FERC’s orders to thoroughly analyze each and every argument in order to engage in reasoned decision making, nor have we found one. We would not expect FERC to have spent much time addressing Fall River’s implied consent argument in this case, as Section 6 of the FPA unequivocally provides that a
Finally, because Fall River did not argue its express consent argument specifically and distinctly in its opening brief we deem it waived.
See Diaz v. Eagle Produce Ltd. P’ship,
IV. Conclusion
In sum, we conclude that substantial evidence supported FERC’s conclusion that PPL’s license would be substantially altered under Section 6 of the FPA by Fall River’s proposed project, that FERC’s orders were consistent with its precedents and with its issuance of a preliminary permit, and that PPL did not impliedly consent to Fall River’s proposed modifications. Therefore, Fall River’s petition for review is DENIED.
Notes
. FERC subsequently replaced all references to Symbiotics, LLC with "Fall River Rural Electric Cooperative, Inc.”
. Section 799 provides in pertinent part: “Licenses may be revoked only for the reasons and in the manner prescribed under the provisions of this chapter, and may be altered or surrendered only upon mutual agreement between the licensee and the Commission after thirty days' public notice." 16 U.S.C. § 799.
. Section 4.32(e)(2) provides in pertinent part:
If, within 90 days of its filing date, the Director of the Office of Energy Projects determines that an application patently fails to substantially comply with the requirements of paragraph (a), (b), and (c) of this section and of § 4.38 of this part or § 16.8 of this chapter, or is for a project that is precluded by law, the application will be rejected as patently deficient with the specification of the deficiencies that render the application patently deficient.
18 C.F.R. § 4.32(e)(2).
. ''NPSI” refers to Northwest Power Services, Inc., which Fall River designated as its project liaison for correspondence. Accordingly, most if not all of Fall River’s correspondence in the record is by or to NPSI.
