Once again we must work our way through the brambles surrounding the right to indemnity at common law. In this case, there are two issues: (1) whether there is an implied right of indemnification arising from the terms of a subcontract between the general contractor and the subcontraсtor; and (2) if the right exists in this case, when does an
This case began on Mаrch 16, 1988, by a complaint founded on a contract dispute between the Fall River Housing Authority (Fall River) and H.V. Collins Company (Collins), the general contractor on a housing development for the elderly. On April 27, 1988, Collins filed a third-party complaint against Cape Cod Lath & Plaster, Inc. (Cape Cod), a subcontractor on the development, for contribution and indemnification of any payments which Collins might have to make to Fall River. On April 9, 1990, the Superior Court judge granted Cape Cod’s motion for summary judgment on the third-party claim and subsequently denied Collins’ motion for reconsideration on September 25, 1990. The judge ruled that Collins’ claim against Cape Cod was barred by the statute of limitations,
1
and judgment was entered on February 5, 1991, dismissing Collins’ third-party complaint as well as all remaining parties and claims in the case. However, when Collins turned to Fall River and moved for summary judgment on the ground that Fall River’s claims against Collins were likewise time barred, a different judge in the Superior Court denied Collins’ motion. The judge held that Fall River’s claim against Collins, in contrast to Collins’ third-party claim against Cape Cod, was not barred by the statute of limitations.
2
In reaching her decision, the judge
“An order granting or denying summary judgment will be upheld if the trial judge ruled on undisputеd material facts and his ruling was correct as a matter of law.”
Commonwealth
v.
One 1987 Mercury Cougar Auto.,
In contrast to the procedural history, the facts of this case are quite straightforward. On October 9, 1980, Fall River contracted with Collins for the construction of a low-income elderly housing project. Collins then subcontracted with Cape Cod to install a synthetic stucco wall system manufactured by Dryvit System, Inc. (Dryvit). Cape Cod’s work was finished by October, 1981; the work was certified as complete in November, 1981, and the subcontractors were paid the same month. The entire project was certified as substantially complete on March 22, 1982, and accepted by Fall River on
The subcontract between Collins and Cape Cod provides that Cape Cod will indemnify Collins for claims, damages, and expenses arising out of Cape Cod’s negligent performance. The parties agree, however, that this provision does not apply to their situation. The subcontract also states that “[sjuch obligation shall not be construed to . . . reduce any other right or obligation of indemnity which wоuld otherwise exist as to any party . . . .” We have held that indemnity provisions will be construed “fairly and reasonably ... to ascertain the intention of the parties and to effectuate their purpose.”
Whittle
v.
Pagani Bros. Constr. Co.,
When there is an
express
agreement of indemnity in a contract, a claim for indemnity accrues when there is a breach of that provision. See
Ryan Stevedoring Co.
v.
Pan-Atlantic S.S. Corp.,
Lacking an express indemnity provision applicable to the facts of this case, Collins asks this court to find an
implied
right of contractual indemnity so that an equitable resolution may be rеached. A contractual right to indemnity arises from the relationship between the parties.
Araujo
v.
Woods Hole, Martha’s Vineyard, Nantucket S.S. Auth.,
Moreover, this is not a case as in strict suretyship where both parties are liable for thе same obligation, and equity relocates the burden from the party who is secondarily liable to the party who is primarily liable. See Restatement of Restitution §§ 76 et seq. (1937). Here, there is no privity between Cape Cod and Fall River. 5 Rather, there are two sеparate contracts: one between the owner and the general contractor, and another between the general contractor and the subcontractor. Collins, therefore, has mischaracterized its situation. As the Superior Court judge recognized correctly, this is not a case of contractual indemnity but rather a simple breach of contract. 6 Therefore, we decline to write into the subcontract an indemnity provision not bargained for by the parties. As we noted in the cоntext of tort-based indemnity, “[s]uch a radical departure from the reasonable expectation of the parties, considering their relationship, is unwarranted in the absence of a clear expression in the contract.” New Bedford Gas & Edison Light Co., supra at 736.
In so holding, we do not deprive Collins of its rights in the subcontract or at common law. Collins had six years to bring a claim for breach of contract against Cape Cod.
7
Our decision comports with the Legislature’s intent to prohibit contract claims made more than six years after the cause of action accrues. G. L. c. 260, § 2. Because the judge found that the defects were not inherently unknowable, Collins cannot claim a lack of notice. If Collins truly could not have known about the defective performance, the discovery rule would operate to toll the statute of limitations, and thereby preserve Collins’ contract rights. See, e.g.,
Melrose Hous. Auth.
v.
New Hampshire Ins. Co.,
In summary, there is no implied contractual indemnity in this case. We hold that Collins’ cause of action against Cape
Judgment affirmed.
Notes
General Laws c. 260, § 2 (1990 ed.), reads: “Actions of contract, other than those to recover for personal injuries, founded upon contracts or liabilities, express or implied, except actions limited by section one or actions upon judgments or decrees of courts of record of the United States or of this or of any other state of the United States, shall, except as otherwise provided, be commenced only within six years next after the cause of action accrues.” The three-year statute of repose for tort actions, G. L. c. 260, § 2B (1990 ed.), does not apply to contract actions.
Anthony’s Pier Four, Inc.
v.
Crandall Dry Dock Eng’rs, Inc.,
The judge ruled that Fall River’s cause of action against Collins did not accrue until Fall River accepted the construction project on March 22, 1982, rather than in October of 1981 when the project was substantially completed. Since Fall River filed its complaint on March 16, 1988, its claim was not barred by the six-year statute of limitations.
At oral argument Collins abandoned its claim for cоntribution. The only question before the court now is whether Cape Cod must indemnify Collins for Collins’ payment to Fall River.
The holding in
Ryan
was superseded by statute, see
Larkin
v.
Ralph O. Porter, Inc.,
The boiler plate references to the development’s “Owner” in рaragraph 11.11 of the subcontract are insuEcient to establish privity between Fall River and Cape Cod.
We have held that “[a] plaintiff may not, of course, escape the consequences of a statute of repose or statute of limitations on tort actions merely by labelling the claim as contractual. The court must look to the ‘gist of the action.’ ”
Anthony’s Pier Four, supra
at 823, quoting
Hendrickson
v.
Sears,
Damages in such an action could have been based on repair costs resulting from defective performance of the subcontractor. See, e.g.,
DiMare
v.
Capaldi,
