Fairway Prime Estate Management, LLC v. First American International BankFairway Prime Estate Management, LLC v. First American International Bank
On September 24, 2008, the New York City Council passed a zoning resolution for the area in which the subject property was located that decreased the maximum amount of buildable square footage allowed to a level below the amount plaintiff planned to use. Therefore, in October 2008, the parties agreed to extend the commitment through March 31, 2009 to allow plaintiff time to obtain a variance from the Board of Standards and Appeals (BSA).
On January 27, 2009, the BSA granted plaintiff a variance. Plaintiff immediately advised defendant that the variance had been obtained and delivered a copy of the BSA resolution to defendant. On February 23, 2009, plaintiff‘s lawyer sent the resolution and other documents to defendant‘s lawyer so that the parties could schedule a closing. However, plaintiff alleges, defendant avoided closing, instead demanding a further extension agreement authorizing it to obtain a new appraisal to replace the first appraisal, which was dated August 15, 2008.
On April 1, 2009, Capital Appraisal issued a “restricted” appraisal, i.e., one that “[did] not include discussions of the data, reasoning, and analysis that were used in the appraisal process,” estimating that, as of April 1, 2011, the gross sellout market value of the condominium would be $25 million, and the discounted net sellout value would be $21,300,000.
In or about May 2009, plaintiff completed the foundation for the property, as requested by defendant.
Defendant never terminated the August/September 2008 commitment (as extended in October 2008 and March 2009) in the manner required by its terms. Instead, on June 10, 2009, defendant sent plaintiff a new commitment letter, bearing the same loan number as the original commitment but decreasing the amount of the loan from $10 million to $8.38 million and imposing a number of onerous new conditions that had to be met within 45 days, including an additional bank balance totaling $2,000,000 to be used for the project and the inclusion in the general contractor‘s contract of a personal completion guarantee. Defendant allegedly told plaintiff that the new terms were “take it or leave it.” Plaintiff did not countersign and return the letter within the imposed deadline, and defendant refused to lend the funds previously agreed to.
We agree with the motion court‘s dismissal of plaintiff‘s fraud claim. “A claim for fraudulent inducement of contract can be predicated upon an insincere promise of future performance only where the alleged false promise is collateral to the contract the parties executed; if the promise concerned the performance of the contract itself, the fraud claim is subject to dismissal as duplicative of the claim for breach of contract” (HSH Nordbank AG v UBS AG, 95 AD3d 185, 206 [1st Dept 2012] [emphasis omitted]).
However, we conclude that plaintiff pleaded a viable cause of action for breach of contract. Although the second appraisal‘s values are very slightly lower than the amounts required by the contract‘s condition precedent—an appraised gross sellout market value of $25 million, compared to the required valuation of $25,100,000, and a discounted net sellout value of $21,300,000, compared to the required valuation of $22,400,000—there are several reasons for finding that the appraisal does not establish the failure of a condition precedent as a matter of law.
First, the appraisal itself is subject to question, given its “restricted” nature and the appraised values’ variation by less than 5% from the contract requirements. Such factors as the appraisal‘s margin of error and the “data, reasoning and analysis” that the appraiser used to arrive at its conclusions must be examined to determine whether reliance on those valuations is justified.
Second, “[a] party to a contract cannot rely on the failure of another to perform a condition precedent where he has frustrated or prevented the occurrence of the condition” (ADC Orange, Inc. v Coyote Acres, Inc., 7 NY3d 484, 490 [2006]). If, as plaintiff alleges, defendant delayed closing on the commitment despite plaintiff‘s satisfaction of all pre-conditions, including a timely appraisal within the dictated range, solely in order to avoid its contractual obligation by justifying its later insistence
Even if the second appraisal alone established a failure of the condition precedent, however, defendant‘s moving papers failed to establish as a matter of law that it effectively terminated its loan obligation in the manner required by the contract. If it failed to effectively terminate the contract, then defendant may have remained bound by its terms (see Maxton Bldrs. v Lo Galbo, 68 NY2d 373 [1986]).
Because plaintiff has since found alternative financing, the question of whether specific performance is available for a contract to lend money is moot. Defendant‘s argument that plaintiff‘s damages are speculative is also refuted by the financing that plaintiff has obtained. Concur—Saxe, J.P., Sweeny, Moskowitz, Freedman and Manzanet-Daniels, JJ.