76 N.C. 49 | N.C. | 1877
The deeds not yet having been executed, the plaintiff at Fall Term, 1876, moved the Court below to order the defendants to execute the deeds pursuant to the judgment of the Supreme Court. The Court accordingly ordered the defendants to execute the deeds on or before the 11th of November, 1876, and that the plaintiff, at the same time, should pay them the purchase money, then in the office for their use, being the same bid for the land and the accrued interest. From this order the defendants appealed.
They now contend here, that the purchase money was not paid within a reasonable time after the judgment and order of this Court, and by consequence, that the sale and purchase of the land should be annulled and cancelled. We know of no authority for such a contention. The sale has been confirmed by the solemn adjudication of this Court, and it will never allow its judgments to be evaded or made of no effect in this way. It will always, before any ulterior proceedings are allowed, fix a time certain, at or upon which the order of the Court shall be obeyed. That is precisely what was done by His Honor in the Court below. It was the fault of the defendants, of which they can take no advantage, that the money has not been received by them, for by the order of this Court, the money was to be paid on the due execution of the deeds. The defendants held back, and they still *51 refuse to make the deeds. They will not entitle themselves to the money until they perform their part of the order.
But the defendants insist that prior to the 31st of August, and prior to the adjournment of the Supreme Court, they procured from the Clerk of that Court, a certified copy of its opinion rendered in the case, and in pursuance of it, executed and tendered the deeds, which the plaintiff declined to receive. The Clerk of this Court however inadvertently certified the said opinion, as it is against the rules and course of the Court, without a special order, to issue a certificate either of its opinion or judgment in term time. The plaintiff in courtesy to the defendants, might have acted on this certificate, but it would have been at his own risk. He was under no legal obligation to do so until it was regularly certified. For all the proceedings of the Court are in fieri, subject to be amended, modified or annulled, until the expiration of the term, at which period, in legal contemplation, all the judgments of the Court are delivered.
There is no error.
PER CURIAM. Judgment affirmed. *52