ORDER
Fairchild Republic Company (Fairchild) appeals from the decision of the Armed Services Board of Contract Appeals
Background
On November 1, 1978, Fairchild was awarded Contract No. F33657-78-C-0135 (the prime contract) with the government to build the Air Force’s A-10 jet fighter.
In 1980, as part of the prime contract, Fairchild entered into Supplemental Agreement No. P00157 (the supplemental agreement) to provide computer resource management and technical requirement documents for the inertial navigation system of the A-10 fighters. The supplemental agreement price included as a substantial cost element some $2 million dollars worth of data to be provided by Kaiser Electronics, a subcontractor. At the conclusion of the supplemental agreement contract negotiations, Fairchild certified that the cost and pricing information furnished to the government in connection with the negotiations was accurate, complete and current, as required by the Truth in Negotiations Act, 10 U.S.C. § 2306(f) (1982).
The government, however, performed a post-award audit of both the prime contract and the supplemental agreement and determined that the cost and pricing information furnished by Kaiser to Fairchild, and subsequently to the government, was defective, resulting in an overcharge of $511,-191.00.
Based on this audit, the contracting officer issued a final decision on December 12, 1983, finding that the cost and pricing information furnished by Fairchild was incomplete, inaccurate and non-current and, therefore, a violation of the Truth in Negotiations Act. Accompanying the final decision was unilateral contract modification MOD-P00370, which reduced the price of the prime contract by $511,191.00, the amount attributable to the alleged defective pricing data, as determined by the contracting officer.
Fairchild appealed to the ASBCA, contesting the defective pricing determination and asserting that the contracting officer had exceeded his authority in unilaterally reducing the prime contract price and withholding the claimed amount. Thereafter, Fairchild filed a motion for summary judgment, seeking payment of the $511,191.00 withheld by the government, on the grounds that the unilateral modification and withholding were in violation of the Truth in Negotiations Act, 10 U.S.C. § 2306(f), the Debt Collection Act, 31 U.S.C. § 3716(a), and Defense Acquisition Regulation, Appendix E, Part 6 (DAR Appendix E).
In response, the government asserted that the Truth in Negotiations Act did not prohibit the unilateral modification or the withholding of the amount claimed, and that neither the Debt Collection Act nor DAR Appendix E applied to price reductions for defective pricing arising solely under the same existing contract.
The ASBCA denied Fairchild’s motion in its decision dated April 1, 1985. The board held that the Debt Collection Act was not applicable because Fairchild had not been paid, and thus no “debt” due the government was available to offset administratively. DAR Appendix E was held inapplicable as well, because “the price reduction here was made prior to payment or the legal establishment of a debt.” Finally, the board rejected Fairchild’s argument that the Truth in Negotiations Act had been violated. The board stated in this regard that Fairchild’s proposed procedure that the board must decide defective pricing issues before a reduction can be made
Upon Fairchild’s Motion for Reconsideration, the board modified its opinion but affirmed its original decision denying the motion for summary judgment. A second Motion for Reconsideration by Fairchild was denied. Fairchild now appeals from these adverse determinations.
OPINION
As an initial matter, the Government has raised the issue of this court’s jurisdiction to hear this appeal. Because the board has not yet considered the underlying defective pricing determination of the contracting officer, the government contends that the board’s decision is not a final decision within the meaning of 28 U.S.C. § 1295(a)(10) (1982).
Fairchild has pointed out'that its petition to the board contained two claims: (1) that the contracting officer had violated the Truth in Negotiations Act, the Debt Collection Act, and DAR Appendix E, by improperly withholding money due Fairchild, and (2) that there was no defective pricing violation. Citing this court’s decision in
Dewey Electronics Corp. v. United States,
The Federal Courts Improvement Act of 1982, Pub.L. 97-164, grants this court exclusive jurisdiction “of an appeal from a final decision of an agency board of contract appeals pursuant to section 8(g)(1) of the Contract Disputes Act of 1978 (41 U.S.C. § 607(g)(1)).”' 28 U.S.C. § 1295(a)(10) (1982). The relevant Contract Disputes Act section provides:
(1) The decision of an agency board of contract appeals shall be final, except that—
(A) a contractor may appeal such a decision to the United States Court of Appeals for the Federal Circuit within one hundred twenty days after the date of receipt of a copy of such deci-sion____
41 U.S.C. § 607(g)(1)(A) (1982) (emphasis added).
In interpreting these statutes, this court has repeatedly held that, as an appellate tribunal, it may only review “final decisions.”
See United States v. W.H. Moseley Co.,
It helps preserve the respect due trial judges by minimizing appellate-court interference with the numerous decisions they must make in the prejudgment stages of litigation. It reduces the ability of litigants to harass opponents and to clog the courts through a succession of costly and time-consuming appeals. It is crucial to the efficient administration of justice.
Cabot Corp. v. United States,
This court noted in
Dewey,
however, that there is not always “ ‘precise congruence between “the classical jurisdictional requirements” applied to appeals from district courts and the jurisdictional standards applicable to review of administrative pro-ceedings____’”
Dewey,
We held that the ASBCA’s decision was final as to the four claims appealed and that the appeal should not be deferred pending resolution of quantum for the five claims remanded. In doing so, we concluded that the ASBCA’s jurisdiction was limited to reviewing decisions of the contracting officer, that only liability or entitlement had been constructively determined in that case by the contracting officer, and that the ASBCA had decided the entitlement issue as to all nine claims before it. We said “the Board decided all of the issues then before it____”
Dewey,
The same cannot be said in this case. In fact, the board stated, “[w]e therefore leave the parties where we find them, that is, with the issue of whether defective pricing existed on this contract.” This issue was decided by the contracting officer and is clearly still pending before the board.
See Teller Envtl. Systems, Inc. v. United States,
Fairchild also argues that the rule of
Cohen v. Beneficial Indus. Loan Corp.,
That exception is inapplicable to the facts of this case. Fairchild’s claim that the government improperly withheld the amount of the defective pricing is not completely separate from the merits of the claim of defective pricing. Both issues arose out of interrelated conduct and the same or closely connected facts.
Teller,
In considering the inconvenience and costs of piecemeal review on the one hand and the danger of denying justice by delay on the other, we conclude that a considerable savings in judicial resources can be achieved by waiting to consider both of Fairchild’s “claims” in one appeal.
See Flanagan v. United States,
Accordingly, IT IS ORDERED THAT:
This appeal is dismissed without prejudice for lack of jurisdiction.
