106 A. 333 | Conn. | 1919
The first two reasons of appeal are based on the refusal of the court to charge as requested by the defendant. The action is for a balance due upon a building contract, and for extras, and the plaintiff's right to recover upon the contract depends *385 upon substantial performance, and the right upon the extras depends upon whether they were ordered.
The first of the defendant's requests relates merely to the essentials of a discharge of the contract by agreement, and treats of termination by agreement and substitution of a new contract. The record does not raise any such questions and there was no error in not charging as requested. But this request to charge also incorporates a reference to performance: "The jury must find for the defendant, in case said defendant proves that plaintiff failed to perform said contract according to its terms, unless such failure was caused by any of the three discharges enumerated above," referring to discharge by agreement, by impossibility of performance, and by breach. This, standing by itself, is not an accurate statement with reference to building contracts. The necessities of such cases have led to a modification of the statement, to prevent injustice, as set out in Pinches v. Swedish EvangelicalLutheran Church,
The second request to charge relates to impossibility of performance, and to a recovery on quantum meruit.
As to the first of these points, the record does not show that impossibility of performance was claimed. The contract did not provide for its completion at any definite time, hence it was to be completed in a reasonable time; and the real question was as to the defendant's imperative directions to the plaintiff to proceed before the walls were fit to be papered, and the woodwork varnished, on his definite promise to pay for work that might have to be done over in consequence. No claim of the plaintiff is based on impossibility of complying with the terms of the contract. The claim was, that owing to the condition of the walls compliance with the hurry-up-order of the defendant necessarily resulted in the peeling off of some paper and the consequent *386
repapering. As to quantum meruit, the entire request is based upon the theory that the plaintiff's action is upon the technical quantum meruit, and quite overlooks the real meaning of the Pinches case, which recognizes the action as still on the contract, though deductions may be made from the contract price when there has not been entire conformity with the contract, provided the deviation was not wilful. Daly Sons v. New Haven Hotel Co.,
In view of our conclusions above stated, the reason of appeal (3) which alleges that the court did not charge "in every particular as requested by the defendant," *387
needs no consideration further than to say that the court is never bound to charge "in every particular" as a party may request. If the charge is proper and adequate, the whole duty of the court is performed. Crotty v. Danbury,
Another reason of appeal (4) predicates error in the entire charge in failing to state the law explicitly and in leaving the principles of law undefined, and not sufficiently explicit. No specific error is pointed out. This is a sort of blanket objection which this court will not consider. Harper Machinery Co. v. Ryan-UnmackCo.,
The defendant also appeals from the denial of a motion to set aside the verdict as against the weight of evidence and as unsupported thereby. An examination of the record shows very clearly that there was evidence before the jury on which they might fairly come to the conclusion they did. The rule in this respect has been so often and so consistently stated by the court that it should be elementary law for those who undertake the trial of cases. We only refer to *388
two of the later cases. Robinson v. Backes,
The ninth and tenth reasons of appeal are that the court erred in holding and charging that under the pleadings the plaintiff could offer evidence as to the frozen condition of the walls, and the orders of the defendant with reference thereto, as stated above. The pleadings, omitting the third defense of payment as to which no question is made, are, in substance, performance of the contract by the plaintiff, and denial of performance by the defendant. The pleadings themselves make no mention of frozen walls or defective work. When, as appears from the record, the fact of performance and of workmanship depends upon the condition of the walls, and the only reason why some papering and varnishing had to be done over was claimed to be due to defendant's explicit orders to go ahead under the promise to pay for doing over any of this work which might be due to the condition of the walls, the plaintiff may show these facts to explain that the work he did was in performance, that his work was well done, and that what, at first impression, might appear due to defective workmanship, was due solely to the condition of the walls which the defendant ordered him to paper in spite of plaintiff's protest and warning. The defendant cannot order work to be done on unfit walls with knowledge of their unfitness for the work, and if it turns out badly, shift the blame upon the plaintiff, who urged that the work be not done until the walls were fit. There is no error on either of these two grounds. But further, in this case, the condition of the walls was the basis of plaintiff's claim for extras, and the evidence would necessarily come in connection with his case in chief.
The seventh and eighth reasons of appeal are based *389 upon claimed errors in the admission of evidence with reference to the frozen and damp walls. What has already been said with reference to the ninth and tenth reasons of appeal sufficiently answers these claims of error.
The defendant claims that the court did not charge the jury properly or at sufficient length upon the burden of proof relative to showing impossibility of performance of the contract. The controversy was not as to impossibility of performance, but the much narrower question, whether the fact that paper would not stay on wet and frozen walls showed defective workmanship when put on by the paperer under protest on the positive order of the defendant and an agreement to pay for such repetition of the work as might, as a consequence, be needed. In addition to the part of charge already quoted, the court further charged as to the doing over of the work as extras, as follows: "If you find that the plaintiff did this work under an express contract, or an implied contract, with the defendant; that is, if in so many words the contract was made to do this extra work, or if the plaintiff went at the request either of the defendant Nielson, or of his man who was in charge there, who testified he was in charge and rented the rooms, and so forth, — if you find that the plaintiff did this extra papering by the direction of any one in behalf of the defendant, and that he was not at fault; if you find that the paper came off on account of the frost, or the frost coming out of the walls; if you find it is the duty of the defendant Nielson to keep the walls in condition, and the frost out, then the plaintiff is entitled to a reasonable sum for this extra work; and if you find that, then it would be your duty, also, to find in favor of the plaintiff as regards the counterclaim of the defendant; that is, any work which the defendant after he had *390 discharged the plaintiff, — any work which he had to do, if you find that it had to be done in consequence of frost, or the condition of the walls which you find it was the duty of the defendant Nielson to have in condition, the frost out of them, and in condition so that they would take paper properly, then that cannot be charged against the plaintiff." As to plaintiff's claim and the defendant's counterclaim, the court charged upon the burden of proof: "The burden of proof is on the plaintiff to establish his claim as to the contract, and establish his claim as to the extras which he did. But when you come to the counterclaim, gentlemen, when the defendant sets up matter in defense apart from the contract, — affirmative matter, then it is his duty to prove by a fair preponderance of the evidence the statement which he makes in his counterclaim, and it is his duty to prove that by a fair preponderance of the evidence which is offered to you."
While we do not commend this precise form of statement, yet the jury could not have drawn any other conclusion from it than that each side, to recover, must make out his case by a fair preponderance of the evidence.
It is claimed the court erred in not charging correctly with reference to consideration for the contract for extras. The charge as to extras, quoted above, sufficiently and fully meets the objections taken.
The thirteenth reason of appeal is that the court erred in holding that the plaintiff under his pleadings and proof could recover as for substantial performance of his contract, and the fourteenth reason is that the court erred in holding that there was either an express or implied contract for extras proved by the evidence. Both these reasons confuse the action of the court and of the jury. It was for the jury to determine these matters under proper instructions, and there is no *391 specific exception taken to the charge upon these points. These assignments furnish no ground for error.
The fifteenth and last reason of appeal is that the court erred in holding that breach of contract was not the sole remedy under the proof, but that plaintiff could recover under his proof as for substantial performance. This assignment does not point out any specific ruling or statement in the charge of which the defendant complains, referring only to the charge as a whole, and under the rule already stated furnishes no ground of appeal.
None of the reasons of appeal as stated are tenable.
There is no error.
In this opinion the other judges concurred.