183 N.J. Super. 454 | N.J. Super. Ct. App. Div. | 1982
The opinion of the court was delivered by
Defendants Dunes Hotel & Casino of Atlantic City, Inc. and Dunes Hotels & Casinos, Inc. (hereinafter “Dunes”), appeal from an order for summary judgment dated July 17, 1981 on a mechanics’ lien claim in the amount of $1,789,127.13. Plaintiff is a structural steel subcontractor for a casino/hotel construction project. It holds a lien claim under a mechanics’ notice of intention assertedly served on defendants and filed in the office of the Atlantic County Clerk on August 17, 1979. The value of the labor and materials furnished after filing of the notice is supplied in a certification signed by plaintiff’s board chairman after making due allowance for $253,250 for payments already made.
Citing Judson v. Peoples Bank & Trust Co. of Westfield, 17 N.J. 67, 74 (1954), and cases following, defendants first contend that plaintiff has failed to demonstrate the absence of any genuine issue as to all material facts challenged. It maintains that “a substantial issue as to the amount of work performed prior to August 17,1979” remains. The “work” referred to chiefly involves fabrication of the materials furnished and other off-site labor of a preparatory nature. Normally, such preparatory efforts are not separated from the claim of a lien for the materials. 53 Am.Jur.2d, Mechanics Liens, § 102 at 614. Although N.J.S.A. 2A:44-71 precludes the imposition of a mechanics’ lien for “labor performed or materials furnished prior to the filing ... of a mechanics notice of intention ...,” it is evident to us that this is addressed to “labor performed” at the job site in connection with the actual furnishing or installation of the materials. The statutory language does not apply to work on the materials furnished which is done in preparation for delivery and use. The value of the preparatory work is incorporated into the price of the materials themselves which, in this case, were delivered to the site after the notice of intention was filed.
Defendants’ final point is that fact questions remain as to the validity of plaintiff’s service of the notice of intention upon defendants. Our examination of the record satisfies us that no question exists as to the fact of service by Walter Bucher upon Bennett Strahan at the Dunes office in Atlantic City; that Bucher explained to Strahan the purpose of his visit; that Strahan was in charge of the office and signed a receipt for the notice. Nor do we find any question as to whether service could effectively have been made upon Strahan, who was the project director.
Affirmed.