F & G Heating Co. v. Board of EducationF & G Heating Co. v. Board of Education
— In an action to recover damages for breach of a construction contract, plaintiff appeals from (1) an order and judgment (one paper) of the Supreme Court, Kings County (Gold-stein, J.), dated March 4, 1983, which granted the defendant board of education’s cross motion for partial summary judgment dismissing plaintiff’s claim for delay damages in the amount of $277,664.45 and (2) an order of the same court, dated July 21, 1983, which denied plaintiff’s motion, which was, in effect, to reargue defendant’s cross motion for partial summary judgment. H Order and judgment dated March 4, 1983, affirmed. 11 Appeal from the order dated July 21, 1983, dismissed. 1i The respondent is awarded one bill of costs. 11 The plaintiff’s motion which resulted in the order dated July 21, 1983 was labeled as one “to renew and reargue”. A motion for reargument is “addressed to the discretion of the court [and] is designed to afford a party an opportunity to establish that the court overlooked or miscomprehended the relevant facts, or misapplied any controlling principle of law” (Foley v Roche,
“(a) $ 11,127.45 representing 15% interest per annum on every partial payment not received within 30 days after it was requested.
“(b) 136,000.00 representing ‘[p]roject manager’s expenses as a result of delay in contract completion’.
“(c) 10,480.00 representing delay damages incurred by plaintiff’s subcontractor.
“(d) 7,000.00 representing legal fees incurred in prosecuting two CPLR article 78 proceedings against defendant to recover payments under the contract.
“(e) 113,057.00 representing damages in increased labor and material caused by defendant’s failure to make plans and construction sites available and defendant’s major design changes.”
11 After joinder of issue, the defendant cross-moved for partial summary judgment dismissing the claim for delay damages on the ground that plaintiff had failed to serve a notice of such claims within three months after their accrual, pursuant to subdivision 1 of section 3813 of the Education Law. II In support of the cross motion, defendant alleged that (1) a claim accrues under subdivision 1 of section 3813 of the Education Law when plaintiff’s damages are ascertainable, (2) the delays for which plaintiff was seeking damages occurred during the contract performance which ended when the contract work was substantially completed, and (3) plaintiff’s delay damages were therefore ascertainable on September 10, 1979 when the work was substantially completed. Since the plaintiff’s notice of claim was served on defendant more than two years after the work was substantially completed, defendant argued that its cross motion for partial summary judgment dismissing the claim for delay damages had to be granted. H In opposition to defendant’s cross motion for partial summary judgment, plaintiff argued, inter alia, that its claim for delay damages did not accrue “until July 6, 1981 when [the defendant] issued its check for $7,371.24 * * * stating that this was final payment for the job in question”. Defendant further argued that “[i]t was only after receipt of the * * * check marked ‘final payment’ that plaintiff was aware of the amount [defendant] intended to pay and the damages could be calculated”. Accordingly, defendant argued that (1) it served a notice of claim within three months from the claim’s accrual (i.e., July 6, 1981 — October 2, 1981), and (2) it had therefore complied with subdivision 1 of section 3813 of the Education Law. H Special Term granted defendant’s cross motion for partial summary judgment. 11 We affirm. U Subdivision 1 of section 3813 of the Educational Law