247 Conn. 234 | Conn. | 1998
Opinion
This certified appeal arises from an action brought by the plaintiff, F. B. Mattson Company, Inc., to foreclose a mechanic’s lien on property located at 161 Hillside Avenue in the city of Waterbury (property). The named defendant, Conrad Tarte, is the current owner of the property. The two other defendants are Commercial Investments International, Inc. (Commercial Investments), the previous owner of the property, and Great Western Bank, the holder of a mortgage on the property.
The renovations began in April, 1995, and were substantially completed on October 3, 1995. By that time, Commercial Investments had fallen behind in payments due the plaintiff under the contract. On October 10, 1995, the plaintiff stopped work on the property but left scaffolding and roofing brackets in place. On that same date, Commercial Investments transferred ownership of the property to Tarte, the president and one-third owner of Commercial Investments.
Tarte subsequently requested that the plaintiff remove the scaffolding and roofing brackets from the property. The plaintiff returned to the premises on November 10,1995, and two of its employees, a carpenter and an apprentice carpenter, worked all day removing the scaffolding and roofing brackets. Thereafter, the plaintiff performed no further work on the property.
On January 25, 1996, the plaintiff recorded a certificate of mechanic’s hen against the property at 161 Hillside Avenue. The certificate, which claimed a balance due of $83,723.29, stated that the plaintiff had ceased furnishing services and materials to the property on November 10, 1995.
The plaintiff subsequently filed the present action seeking to foreclose its mechanic’s hen. The trial court rendered judgment in favor of the plaintiff, and the defendants appealed from the trial court’s judgment to
Thereafter, the plaintiff filed a petition for certification to appeal from the judgment of the Appellate Court to this court. We granted certification limited to the following question: “Did the Appellate Court properly conclude that the plaintiffs mechanic’s lien was untimely filed?” F. B. Mattson Co. v. Tarte, 243 Conn. 966, 707 A.2d 1265 (1998). We answer the certified question in the negative and reverse the judgment of the Appellate Court.
We begin our analysis by noting that in Connecticut, the “mechanic’s lien is a creature of statute and gives a right of action which did not exist at common law.” Diamond National Corp. v. Dwelle, 164 Conn. 540, 543, 325 A.2d 259 (1973); Parsons v. Keeney, 98 Conn. 745, 748, 120 A. 505 (1923). “The purpose of the mechanic’s
Moreover, “[t]he guidelines for interpreting mechanic’s lien legislation are . . . well established. Although the mechanic’s lien statute creates a statutory right in derogation of the common law; Camputaro v. Stuart Hardwood Corporation, [180 Conn. 545, 550, 429 A.2d 796 (1980)]; Gruss v. Miskinis, 130 Conn. 367, 370, 34 A.2d 600 (1943); its provisions should be liberally construed in order to implement its remedial purpose of furnishing security for one who provides services or materials. H & S Torrington Associates v. Lutz Engineering Co., [supra, 185 Conn. 553]; Henry F. Raab Connecticut, Inc. v. J. W. Fisher Co., 183 Conn. 108, 115, 438 A.2d 834 (1981). Our interpretation, however, may not depart from reasonable compliance with the specific terms of the statute under the guise of a liberal construction. Camputaro v. Stuart Hardwood Corporation, supra, 551; Stone v. Rosenfield, 141 Conn. 188, 191, 104 A.2d 545 (1954).” (Internal quotation marks omitted.) New England Savings Bank v. Meadow Lakes Realty Co., 243 Conn. 601, 611-12, 706 A.2d 465 (1998); Thompson & Peck, Inc. v. Division Drywall, Inc., 241 Conn. 370, 375-76, 696 A.2d 326 (1997).
Section 49-34 provides in relevant part: “A mechanic’s lien is not valid, unless the person performing the services or furnishing the materials . . . within ninety
We previously have concluded that, although the general rule is that the time period for filing a certificate of mechanic’s lien commences on the last date on which services were performed or materials were furnished; Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., 99 Conn. 396, 403, 122 A. 102 (1923); when work has been substantially completed and the contractor unreasonably has delayed final completion, the time period for filing a certificate of mechanic’s lien will be computed from the date of substantial completion. Id. Moreover, when an unreasonable period of time has elapsed since substantial completion of the work, the performance of trivial services or the furnishing of trivial materials generally will not extend the time for filing the certificate past the date of substantial completion. Id., 400. If, however, subsequent to the date of substantial completion, trivial services or materials are provided at the request of the owner, rather than at the initiative of the contractor for the purpose of saving a lien, the furnishing of such work or material will extend
On November 10, 1995, two persons employed by the plaintiff, a carpenter and a carpenter’s apprentice, worked all day removing scaffolding and roofing brackets from the property. The work was done at the request of Tarte. Consequently, even if we assume, without deciding, that the plaintiff unreasonably delayed final completion of the work, and if we further assume, without deciding, that the work done on November 10,1995, was trivial, under the rule of Nichols v. Culver, supra, 51 Conn. 183, the time period for filing a certificate of mechanic’s lien is computed from November 10, 1995, rather than from October 3, 1995, the date of substantial completion.
Relying on Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., supra, 99 Conn. 403, the Appellate Court nevertheless concluded that the work done by the plaintiff on November 10, 1995, did not operate to extend
Regardless of the fact that it was at the request of Tarte that the plaintiff removed the roofing brackets and scaffolding from the property, Great Western argues that the work done on November 10, 1995, did not operate to extend the commencement of the ninety day period for filing a certificate of mechanic’s lien because, in its view, the work done on that date did not constitute lienable “services.” General Statutes § 49-33 (a), however, provides in relevant part: “If anyperson has a claim for more than ten dollars for materials furnished or services rendered in the construction . . . or repairs of any building . . . the building, with the land on which it stands ... is subject to the payment of the claim.” (Emphasis added.) We recognize that we concluded that under the circumstances of Martin Tire & Rubber Co. “preparation for removal and the removal of the [contractor’s] equipment . . . was [not] the rendition of such service as would warrant the filing of a mechanic’s lien . . . .’’Id., 403. In the present case, however, removal of the roofing brackets from the building’s roof was a necessary predicate to removing the plaintiffs equipment from the property. The
The judgment of the Appellate Court is reversed and the case is remanded to that court with direction to affirm the judgment of the trial court.
In this opinion the other justices concurred.
General Statutes § 49-34 provides: “A mechanic’s lien is not valid, unless the person performing the services or furnishing the materials, (1) within ninety days after he has ceased to do so, lodges with the town clerk of the town in which the building, lot or plot of land is situated a certificate in writing, which shall be recorded by the town clerk with deeds of land, (A) describing' the premises, the amount claimed as a lien thereon, the name or names of the person against whom the lien is being filed and the date of the commencement of the performance of services or furnishing of materials, (B) stating that the amount claimed is justly due, as nearly as the same can be ascertained, and (C) subscribed and sworn to by the claimant, and (2) within the same time, or prior to the lodging of the certificate but not later than thirty days after lodging the certificate, serves a true and attested copy of the certificate upon the owner of the building, lot or plot of land in the same manner as is provided for the service of the notice in section 49-35.”
“Persons entitled to claim a mechanic’s lien ... are those who have provided ‘services’ or ‘materials’ in connection with ‘the construction, raising, removal or repairs of any building or any of its appurtenances or in the improvement of any lot or in the site development or subdivision of any
We express no opinion as to whether the work subsequently done by the plaintiff in removing the scaffolding materials and the roofing brackets from the property constitutes lienable services under § 49-33.