15 Mo. App. 256 | Mo. Ct. App. | 1884
delivered the opinion of the court.
This is an action upon twenty-six special tax bills executed and delivered to the plaintiff by the president of the board of public improvements of the city of St. Louis, for constructing a sewer and branch sewers in what is known as the Arsenal Street Sewer District No. 9. The ordinance authorizing the construction of this sewer and branch sewer describes its location in the following words : “ The main sewer shall be located on the east and west alley, through blocks num-'
Among the general stipulations of this contract were the following: —
“ 11. The first party shall not be entitled to any claim for damages for any hindrance or delay, from any cause whatever in the progress of the work, or auy portion thereof; but such hindrance may entitle said first party to an extension of the time for completing this contract sufficient to compensate for the detention, the same to be determined by the sewer commissioner, provided he shall have immediate notice in writing of the cause of detention.
“ 12. The work embraced in this contract shall be begun within one week after written notice to do so shall have been given to the contractor by the sewer commissioner, and car
The plan of the work, as originally made in the office of the sewer commissioner, required the branch sewer to be located, not in block 2050, but in block 2051. The ordinance was drawn up in the office of the president of the board of public improvements, before being submitted to the municipal assembly, and, by a clerical error in drawing it, the branch sewer was located in block 2050, and not in block 2051; and the ordinance, as thus drawn, passed, was approved, and the contract was let under it. Now, it seems that the contractor followed the plan of the work, as he found it oxx file in the office of the sewer commissioner, and it resulted that he constructed the branch sewer in block No. 2051, instead of block 2050. It seems that the mistake was not discovered uixtil after the work was completed. At all events, the work, as thus completed, was approved, and special tax bills therefor were issued to the plaintiff by the president of the board of public improvements, upon which the plaintiff brought an action against the same parties defendant who are parities defendant to the px'esexxt action. In that action, the coux’t gave an instruction to the effect that if the ordinance provided for the construction of a branch sewer on the north and south alley in block 2050, and no sewer had ever been constx-ucted in said north and south alley, the plaintiff could not recover; and judgment was thereupon rendered for the defendaixts. The date of that judgment was December 14, 1881.
I, The first is that the court erred in refusing to give the following instruction : “ The court declares the law to be, that if the contract alleged by plaintiff was made with and subject to the following condition : ‘ That the work embraced in said contract should be begun within one week after writ
The decision of this court in Prendergast v. Richards (2 Mo. App. 187), is decisive authority against such a conclusion. In that case, as in this, a mistiike had been made in executing the work; the contractor had performed a portion of the work outside the sewer district mentioned in the ordinance. The work, as in this case, had been approved by the proper authority, the city engineer; tax bills had been issued for it, and upon one of these the contractor had brought an action, and judgment had been rendered for defendant. Then, a new assessment of the cost of the work was made, embracing only so much of it as was situated within the sewer district named in the ordinance; and upon one of these tax bills, the contractor brought a second action against the same party. It was held that the former judgment was no bar to the second action. The first tax bills were merely void, and the city engineer, by making an erroneous assessment of the cost of the work and issuing these void tax bills, did not exhaust his power or disable himself from afterwards making a correct assessment, and issuing correct bills.
It is not denied to be a sound principle that, when a special tribunal is created with a particular jurisdiction and with limited powers, whenever it exerts its power upon a given subject-matter, its jurisdiction becomes exhausted and at an end; in other words, it becomes fundus officio. Ex parte Randolph, 2 Brock. 447 ; Re Brown, 4 Colo. 438 ; Mills v. Collett, 6 Bing. 85 ; Crepp v. Durden, Cowp. 640. But this principle has been generally invoked in favor of liberty, and to prevent oppressive action on the part of inferior jurisdictions ; and even here, its application has been.by no means uniform. Ex parte Reed, 100 U. S. 13. The decision of the supreme court of the United States in the case last cited, and the decision of this court in Prendergast v. Richards (supra), show that it is not a principle of uniform application. In the present case we are asked to apply it so as to produce bald injustice and serious public inconvenience. We decline so to do. If we are to decide such a question upon technical analogies, we can find analogies which will support the action of the sewer commissioner and of the president of the board of public improvements, as well as analogies which will overturn their -action. It has been held that, where a naval court-martial, assembled to try a particular officer upon a particular charge, renders its judgment, it does not thereby exhaust its power so that it can not, afterwards, in conformity with the recommendation of the admiral, alter the same; such an alteration of its original sentence may be irregular, but the sentence, as thus altered, is not thereby rendered void. Ex parte Reed, supra. Another analogy
II. The next proposition seems to be merely a different way of stating the preceding objection. It is that the plans and specifications showing the work to be done were essential ; that these must necessarily conform to the ordinance, or else the contract requiring them to be complied with is
The learned counsel for the defendants, however, press upon our consideration the argument that the work which was advertised was the work embraced in the plan and specifications in the office of the sewer commissioner to which the advertisement referred ; that the contract for the doing of the work was also a contract for the doing of it in accordance with the same plan and specifications ; and that, as this plan and these specifications did not conform to the ordinance in respect of the location of the branch sewer, the contract is wholly void? and could not become the foundation of any valid charge against the property owners, because it was not a contract to do the work which was required by the ordinance. This is all true, and yet it was a contract to do the work which was required by the ordinance. The advertisement for bids did not, it is true, refer to the ordinance, but it did refer to drawings and specifications which might be seen in the office of the sewer commissioner. It is equally true, that' the plaintiff’s bid did not refer to the ordinance, but it was a proposition to do the work “ in accordance with printed form of contract and specifications for said work,” etc. But the contract itself, after reciting the number and date of the ordinance refers to the work to be done as “ a district sewer within Arsenal Street Sewer District No. 9, as by the above mentioned ordinance specified.” It thus appears that the
Now, it is not claimed that either the charter or any general or special ordinance requires the letting of contracts for public work to be in conformity with plans and specifications on file in any departmental office of the city. Such plans and specifications are not required by law in order to the validity of such a contract. There is, however, great propriety in requiring every letting of public work to be made in accordance with definite plans and specifications previously made and open to the inspection of bidders, .in order that those proposing to bid may see beforehand exactly what their contract will require them to do. Such a plan and specifications were, it seems, open to the inspection of bidders in this case, and it is difficult to say that this contract was not made with reference to the same. It must also be conceded that a contract conforming to the ordinance is necessary to the protection of the public in respect of the letting of public work. But when we consider the powers of the board of public improvements in respect of the construction of lateral sewers, and the powers reserved to the sewer commissioner by the terms of this contract, and the fact that the bidding is for specified elements of work according to measurement, and is not a lumping bid, it is difficult to see how the location of this lateral sewer in •one block, rather than in the other, could have had any influence on the amount of the bid. The charter of the city contains this provision in regard to the powers of the board in the construction of branch sewers: “ Public sewers shall be established and constructed along the principal courses of drainage, at such times, to such extent, of such dimensions and material, and under such regulations
“For earth excavation per cubic yard, thirty-two cents $ 32
“ For brick masonry “ “ $7.......7 00
“ For twelve inch pipe sewers per foot, linear, complete, $1.20...............1 20
“ For fifteen inch pipe sewers per foot, linear, complete, $1.40 . 1.40
“For sixinch junctionlaid, each $1-.......1 00
“ For nine inch “ “ “ 1.......1 00
‘ ‘ For twelve inch “ 1 ‘ “ 1.......1 00
“For fifteen inch “ “ “ 1.......1 00
“For inlet stone, per square foot, furnished and set, $1.....,...........1 00
V For cast iron in inlets and manholes per lb., five cents . 5
“ For wrought iron in inlets and manholes per lb., ten cents . 10 ”
III. The defendant offered and the court refused the following instruction: —
“The court declares the law to be that if a petition of property holders resident in block No. 2051 was presented to the board of public improvements, that said petition was referred by said board to the sewer commissioner, and the report thereon by said commissioner shows upon its face that the petition was not the petition of the majority of the property holders resident in the block or blocks therein mentioned ; that said report is indorsed on said petition; that said petition is referred to in the indorsement on said ordinance No. 11,036, providing for the construction of a district sewer, as communicated to the municipal assembly by said board; that the said boai’d made no recommendation concerning said ordinance other than to prepare and present the same pursuant to said petition; that then said ordinance, No. 11,036, providing for the construction of a district sewer in Arsenal Street Sewer District No. 9, is void, and plaintiff can not recover.”
We see no error in refusing this instruction. 1. We do not gather from the face of the report of the sewer com
IV. A point is made that the court erred in refusing an instruction to the effect that if, in the former suit, it has been found- that the work had been done in conformity to plans at variance with the ordinance, and judgment had been given in that suit for the defendants, then the plaintiff could not recover. There is nothing in this point that has not already been answered. For reasons already stated, this instruction was properly refused.
Y. The next objection is that the president of the boai’d had no authority to issue these bills. We think this objection is sufficiently answered in what has already been said. The former bills were not valid, because the work had not been completed in conformity with the ordinance. This was conclusively adjudged by the judgment of the circuit court in favor of the defendants in the former suit. The case then stood as though the work had not been completed, and as though no bills had been issued. The sewer commissioner thereupon directed the completion of the work, and, upon this being done, the present bills were issued. As the former bills were of no validity, they did not exhaust the power of the president of the board of public improvements to issue the present bills. Prendergast v. Richards, 2 Mo. App. 187.
«.The court declares the law to be that if one of the defendants has a life estate in the lots of ground described in plaintiff’s petition, and that the other defendants have but a remainder in said lots after said life estate, and demand for the payment of said bills herein sued upon was made only of one of the remainder-men, that then plaintiff can not recover.”
It appears that demand was made before the bringing of the suit only upon one of the defendants, and the court treated the bringing of the suit as the first demand, and made the accruing of interest commence accordingly, having reference to the language of the charter. This language is as follows : “ Said tax bill shall be and become a lien on the property charged therewith, and may be collected of the owner of the land, in the name of and by the contractor, as any other claim in any court of competent jurisdiction,, with interest at the rate of ten per cent per annum after thirty days from demand of its payment date; and if not paid within six months after such demand, then at the rate of fifteen per cent per annum from the date of said demand. In case the owner of the ground is a non-resident of the state, suit may be brought by attachment, which shall be a demand of its payment.” Charter St. Louis, art. VI., sect. 25. The object of the demand here provided for evidently was to give the property-owner an opportunity, by paying the bill, of stopping the running of interest. We see nothing to take the case out of the general rule that the bringing of a suit is, of itself, a demand. The language of the charter does not imply that a demand prior to the bringing of a suit is to be a condition precedent to a recovery on the tax bill.
The judgment of the circuit court is affirmed.
Note. — In furtherance of justice, sheriffs are allowed to amend their returns after they have gone out of office, and after the lapse of many years. Spellinger v. Gaff, 112 Ill. 29, and cases cited; Muldrow v. Bates, 5 Mo. 214; Miles v. Davis, 19 Mo. 408; Blaisdell v. Steamboat, 19 Mo. 157; Scruggs v. Scruggs, 46 Mo. 271.