This is аn arbitration dispute between on the one side, two condominium associations, and, on the other side, the defendants — the developеr, the general contractor, the architect, and related subcontractors. Inverness Construction Company, Inc., Surf Side Shores, Inc., Ocean House, Inc., Cable Concrete Structures, Inc., Samuel F. Johnson, Jr., P.E., Milco Building Products, Inc., Service Supply Systems, Inc., and Henry Norris and Associates, Inс., seek mandamus review of the orders of Judges Charles C. Partin and Robert Wilters in the Baldwin Circuit Court denying their motions to compel arbitration. For the reasons stated infra, we deny the petitions.
On or about March 1, 1994, and July 8, 1991, the defendant Henry Norris and Associates, Inc., entered into agreements with Bill Littrell and Gordon Henderson *155 (оwners of the land to be developed) to provide architectural services for developments that were to become "Ocean House, Phase I" and "Surf Side, Phase I"; both are nine-story condominiums. Those agreements were contained in a document prepared by the American Institute of Architecture, known as AIA Document B161 and entitled "Standard Form of Agreement Between Owner and Architect for Designated Services (1977 Edition)."
The developers, Ocean House, Inc., and Surf Side Shores, Inc. (referred to hereafter collectively as "the devеlopers"), entered into construction contracts with the J.W. Hartlein Construction Company, Inc. ("Hartlein"). By the terms of those contracts, Hartlein was to construct "Ocean House, Phase I" and "Surf Side, Phase I." In the interim between the construction and the filing of the present petitions for the writ of mandamus, Hartlein merged into Inverness Construction Company, Inc.
Without question, the contract between Henry Norris and Associates, Inc., Bill Littrell, and Gordon Henderson, and the contracts between the developers and Hartlein contained provisions explicitly requiring the partiеs to these contracts to submit disputes arising under the contracts to binding arbitration. Less certain, however, is whether disputes between the pаrties and nonparties arising under these contracts must be submitted to arbitration, even if the nonparties are third party beneficiaries of thе contracts.
Ocean House Condominium Owners Association, Inc., and Surf Side Shores Condominium Owners Association, Inc. (referred to collectivеly as "the Associations"), filed complaints in the Baldwin Circuit Court against the architect, the general contractor, developers, and various subcontractors on December 24, 1997, and July 2, 1998 respectively. The complaints allege breach of warranties; negligence; wantonness; a violation of the Alabama Uniform Condominium Act, Ala. Code 1975, §
On or about March 3, 1999, Henry Norris and Associates, Inc., filed motions to compel arbitration in both cases.1 Henry Norris and Associates alleged in its motions that the agreеments between the landowners (Littrell and Henderson) and the architect, contain provisions requiring that any claims and/or disputes arising out of thеse contracts be submitted to arbitration. Norris contends that even though the Associations are not signatories to any of the contracts between the defendants, the Associations raised claims as third-party beneficiaries of those contracts, and, therefore, that thе Associations should be equitably estopped from avoiding arbitration.
The Associations filed responses to the motions to compеl arbitration, contending that they were not signatories to any of the contracts and that they were not successors-in-interest to Oceаn House, Inc., and Surf Side Shores, Inc., the developers. Therefore, the Associations argued, the motions to compel arbitration should be denied. The judge assigned to the Surf Side Shores case denied the motions to compel arbitration, on April 2, 1999. The trial judge assigned to the Ocеan House case also denied the motions to compel arbitration, on May 25, 1999. The May 25, 1999 order stated:
"All motions to compel arbitrаtion are denied because the plaintiff was not a signatory to the contract which contained the arbitration agreement. It is the Court's opinion that the arbitration agreements apply only to the architect, *156 [the] general contractor and the owner and any subсontractors[,] but not to the property owners' association."
Inverness and Cable Concrete Structures, Inc. filed motions to "reconsider" in both cases, on June 10, 1999 and June 16, 1999, respectively. The trial court denied the motions to reconsider in the Ocean House case on June 21, 1999. It is unclear from the record when the motion to reconsider was denied in the Surf Side Shores case; however, both Inverness and Surf Side Shores Condominium Association state in their briefs that the motion to reconsider was denied. The petitioners filed these mandamus petitions on July 9, 1999, in the Surf Side Shоres case and on August 3, 1999, in the Ocean House case. They seek an order requiring the trial judges to grant their motions to compel arbitratiоn.
"Mandamus is an extraordinary remedy and requires a showing that there is: `(1) a clear legal right in the petitioner to the order sought; (2) an imperative duty upon the respondent to perform, accompanied by a refusal to do so; (3) the lack of another adequate remedy; аnd (4) properly invoked jurisdiction of the court.' Ex parte Edgar,
This Court has held that an appeal is the proper procedural vehicle by which to seek appellate review of a trial court's order dеnying a motion to compel arbitration:
Dean Witter Reynolds, Inc. v. McDonald,"A direct appeal is the proper procedure by which to seek review of a trial сourt's denial of a motion to compel arbitration. See Crimson Industries, Inc. v. Kirkland,
, 736 So.2d 597 600 (Ala. 1999); A.G. Edwards Sons, Inc. v. Clark,, 558 So.2d 358 360 (Ala. 1990); see also Federal Arbitration Act (`FAA'),9 U.S.C. § 16 (providing that an appeal may be taken from an order denying a motion to compel arbitration)."
The petitioners asks this Court to order the trial judge in each case to enter an order compelling thе parties to arbitrate. However, "[m]andamus is an extraordinary remedy, and it is not proper where the petitioner has some other adequate remedy."Allred v. Shirley,
WRITS DENIED.
Hooper, C.J., and Houston, See, and Johnstone, JJ., concur.
Maddox, Cook, and Lyons, JJ., concur in the result.
