Evatt v. Dulaney

151 P. 607 | Okla. | 1915

In our opinion there was error in refusing to direct a verdict for the defendants in the court below. In Miller v.Stewart, 9 Wheat. 680, 6 L.Ed. 189, in which the opinion was by Mr. Justice Story, it is said:

"Nothing can be clearer, both upon principle and authority, than the doctrine that the liability of the surety is not to be extended, by implication, beyond the terms of his contract. To the extent, and in the manner, and under the circumstances pointed out in his obligation, he is bound, and no further. It is not sufficient that he may sustain no injury by a change in the contract, or that it may even be for his benefit. He has a right to stand upon the very terms of his contract; and if he does not assent to any variation of it, and a variation is made, it is fatal."

In Justice v. Empire State Surety Co., 218 Fed. 802, 134 C. C. A. 490, it is held:

"Where a building contractor's bond provided that the owner should make specified payments during the progress of the work, but should retain not less than 10 per cent. of *86 all payments for work performed and materials furnished until the complete performance of the contract, but the owner did not retain the 10 per cent., and prior to the contractor's default he paid $2,000 more than the advance payments, there was a material alteration of the contract, for which the surety was discharged."

The case of Eager v. Seeds et al., 21 Okla. 524, 96 P. 646, is almost directly in point. That was, as is the case at bar, a suit on a contractor's bond, and the second point of the syllabus is as follows:

"A surety is bound only by the strict terms of his undertaking. Having assumed such burden without sharing its benefits, he necessarily has the right to prescribe the exact terms upon which he will enter into such undertaking. It is not a question whether he is harmed or benefited by a disregard of the terms of his undertaking; and where by such terms the principals or other parties are to be paid by the obligors in certain proportion or at a certain time, when approved by the principals, and such payments are made in advance of such time or without such approval, the sureties will be discharged."

In the case at bar the contract provided that estimates of material and lumber were to be made each Saturday evening by the two parties, and the amount of the estimates to be paid at these times. The evidence shows that this was not done. The estimates were not made by the two parties, as is clearly shown by the plaintiffs' own testimony, and this is such a variation of the contract as brings it directly within the facts of the case of Eager v. Seeds, supra, and vitiates the undertaking as to the sureties.

In Lamm v. Colcord, 22 Okla. 493, 98 P. 355, 19 L. R. A. (N. S.) 901, a guaranty was given to extend credit to O. C. Scoresby, and it appeared that the credit was extended to Scoresby Tailoring Company, and, there being *87 no proof to show that O.C. Scoresby comprised the Scoresby Tailoring Company, the court held that the guarantors were released, saying:

"The guarantor has the right to prescribe the exact terms upon which he will enter into a guaranty obligation, and to insist upon a discharge in case these terms are not strictly observed."

In the case at bar the terms of payment were not strictly observed, and this case is also directly in point. We are also of the opinion that the insertion of the 60 days, within which the building was to be completed, in the contract after its signing and the signing of the bond, relased the sureties. Under the contract as it existed when they signed it no time limit was fixed for the completion of the building, and this would be construed to give the contractor a reasonable time within which to complete it. Without plaintiffs' consent the time limit of 60 days was inserted in the contract. InRichardson v. Fellner, 9 Okla. 513, 60 P. 270, it is held that any alteration of a written instrument, after its execution, without the consent of the parties, which varies the legal effect of the contract, changes the operation of the contract, or the rights or liabilities of the parties, though no fraud results, is a material alteration, and vitiates the contract.

Clearly a guarantee to complete the building within a reasonable time, which must have been the construction of the contract in the absence of the 60 days put in without the consent of the sureties, is a very different obligation from a guaranty to complete the building within 60 days. There is no evidence in this case that the sureties were interested or received any benefit for becoming sureties on this bond. If such were the case, the burden was on the plaintiffs below to show these facts, so as to take the case *88 out of the general rule. That the rule strictissimi juris does not apply when the surety is remunerated for going on the bond is settled in this state by section 1346, Rev. Laws 1910, construed in Columbia Bank Trust Co. v. United StatesFidelity G. Co., 33 Okla. 535, 126 P. 556. See, also,American Surety Co. v. Scott, 18 Okla. 264, 90 P. 7. And even in the absence of a statute this rule is now followed by the great weight of modern decisions. See Justice v. Empire StateSurety Co. (D.C.) 209 Fed. 105; City of Topeka v. Federal UnionSurety Co., 213 Fed. 958, and cases cited on page 962, 130 C. C. A. 364; Philadelphia v. Fidelity Deposit Co., 231 Pa. 208, 80 A. 62, Ann. Cas. 1912B, 1985; United States Guaranty Co.v. Pressed Brick Co., 191 U.S. 422, 24 Sup. Ct. 142, 48 L.Ed. 242, in which the question is not decided, but the arguments pro and con are presented with great clearness.

It is argued for the defendant in error Dulaney that the alteration in the contract, by inserting the time limit of 60 days, was done by Hughes without his knowledge or consent, and therefore is not binding on him. But Dulaney has expressly affirmed this change in the contract in his petition, for one of his allegations is that the building was not finished in 60 days, whereby he was injured. Even if Hughes did not have authority from Dulaney to insert this provision in the contract, yet every ratification is equivalent to a prior command, and Dulaney has in the most explicit manner possible affirmed the act of Hughes. See Fleckner v. United States Bank, 8 Wheat. 363, 5 L.Ed. 631; Broom's Legal Maxims, p. 672.

We therefore recommend that the judgment be reversed, and this case remanded for a new trial.

By the Court: It is so ordered. *89