99 Iowa 326 | Iowa | 1895
Lead Opinion
The findings of the referee are lengthy, and we summarize them as follows: That the contract was entered into for the construction of the house for seven thousand three hundred and fifty dollars, and its performance secured by bond of C. L. Poor, for two thousand dollars; that Evans proceeded to do the work until May 5, 1893, when, the work being unfinished, it was taken out of his hands, and finished by another; that the work dragged from the beginning; the plastering did not begin until the week before Christmas in 1891, and then McConnell stopped it for a time, claiming it was unsafe to plaster then; that on May 2,1892, McConnell, through the architect, served a notice upon Evans that, owing to his failure to comply with his contract, one Sanson would complete the work; that the latter completed it at an expense of six .hundred and fifteen dollars; that liens were filed as claimed by McConnell; and that the latter informed material men that they must not trust Evans on the credit of the building; that the delay in the work was caused by its taking more time to do the stone work than was anticipated; workmen were hard to get; time was lost in making changes, some because of errors of the contractor; Evans was without means,
IY. Evans contends that he had a right to rescind the contract, and to recover the reasonable value of his labor done, and materials furnished. We need not determine that question. The evidence shows very satisfactorily that Evans never undertook to rescind the contract. We cannot consider it in detail. Nor was the work taken out of Evans’ hands wrongfully. Indeed, there is evidence to show that he was not only not averse to having the job taken out of his hands, but recognized his own inability to complete it.
Y. Counsel file a stipulation in this court, showing that' the mechanic’s lien of Kemper has been settled, and the appeal, so far as it pertains to it, dismissed.
YI. Lastly, it is contended that the allowance of the five hundred dollar damages to McConnell for defects in the construction of the house, is more than the evidence warrants. We cannot recite these defects. They were many, and some of them serious. While the evidence did. not show in detail the damages as to each particular item, it was to the effect that in the aggregate it was five hundred dollars. Evans introduced no evidence whatever as to these matters. We discover no error in the holding of the court below in regard to this item.
After a review of the entire record, we conclude that the decree below should be affirmed.
Rehearing
Supplemental Opinion on Re-hearing.
A petition for re-hearing was filed in this case, in which it was urged that this court erred in applying section 8652 of the Code to the facts disclosed in the evidence. No other question was presented in the petition. Oral arguments were made by counsel for appellant and the appellee when the petition was submitted. A majority of the members of the court were of opinion that the record and evidence should be re-examined, as far as the third point in the opinion was involved, and the petition for re-hearing was sustained. After the petition was filed the appellant filed an additional argument, in which other questions in the case are discussed. The appellee, as was his right, filed a printed argument after the petition for re-hearing was granted. We mention this condition of the record for the purpose of saying that the only doubt entertained by any member of the court at any time was whether the appellant was, under the evidence, precluded from recovering extra compensation for the stone ashlar work, and whether the section of the Code above cited was applicable to the case. In view of the contention between counsel as to the weight of the evidence upon this question, we have given the whole record a careful examination. We desire to refer to the following statement in the opinion: “Now, we have a case where the meaning of the provision of the contract touching the stone work was a matter of contention between the owner and contractor from an early perio in the work.” Our re-examination of the evidence lea Is us to the conclusion that this statement is too broaa It should have been limited to contentions about oth> r part's of the work, and possibly to some disputes which occurred