125 Mo. 72 | Mo. | 1894
On the twenty-second day of May, 18.89, Col. George S. Park and James Rider & Son entered into a written contract whereby Rider & Son agreed to furnish all the material and erect for Park building at Parkville in this state, for the use of Park College. The contract provides that the building shall be a frame structure, and shall be erected according to specifications prepared by Mr. Hogg and certain other specifications prepared by Mr. Park. Park agreed to pay Rider & Son $5,800, Rider & Son “not drawing at any time over seventy per cent, of the work done, the whole work to be completed” by October 1, 1889. On the same day Rider & Son gave bond to secure the performance of the contract, with the defendant Graden and others as sureties. Rider & Son abandoned the work on September 1, 1889, so that Park was obliged to complete the building himself. The amount paid by him to Rider & Son and for completing the building, exceeds the contract price some $1,408. Park died, and the plaintiff, as his administrator, brought this suit against the defendant surety on the bond to recover the last named sum. He claims other damages for other alleged breaches of the contract, but no question is made in this court over the other alleged breaches.
The defendant, by his answer, admits the execution of the contract and bond, and then follows a general denial. For a further defense he sets up the same contract pleaded by the plaintiff, and states facts to the effect that Park, from time to time, paid Rider & Son more than seventy per cent, of the value of the work done. For $ further affirmative defense, he says Park
At the close of the evidence the court gave four instructions at the request of the plaintiff, ten at the request of the defendant, and of its own motion contributed nineteen more, in all covering some twenty pages of printed matter. Thus enlightened as to the law, the' jury found for the defendant.
1. The liability of a surety is not to be extended beyond the terms of his contract. He is bound to the extent of his contract, but no further. He is also entitled to the benefit of the securities taken by the creditor from the principal debtor. These principles of law are applicable to sureties on these bonds given by contractors to secure the performance of their contracts for the erection of buildings. The defendant, as a surety, has a right to stand upon the agreement that Park would not pay Rider & Son during the progress of the work more than seventy per cent, of the value of the work done; and if Park, during the progress of the work, paid Rider & Son more than seventy per cent, of the value of the work done, without the consent of the sureties, he thereby discharged the defendant. Taylor v. Jeter, 23 Mo. 244; Ryan v. Morton, 65 Texas, 258; Bragg v. Shain, 49 Cal. 131. If the defendant surety consented to the overpayments, if any there were, then he is not discharged. These principles-of law are set forth in the instructions given, and we see no objection to them so far as they relate to this branch of the case.
Mr. Byers, agent for Park and a witnessforthe plaintiff, testified on direct and on cross-examination to the
2. Some of the instructions informed the jury that if there was an agreement between Park and Rider & Son, made after the execution of the bond, whereby the main doorway was to be, and was, cut down, and this agreement was contrary to the specifications, then the finding should be for the defendant. This instruction should not have been.given for this reason, among others: There was no evidence,'whatever, tending to show any change in the main entrance of the doorway. The giving of this instruction is reversible error.
3. By another instruction the court made it the duty of the jury, in passing upon an alleged change in the terms of the contract, to first “determine what the contract and specifications required as to the construction.” The ninth and more specific instruction is to this effect: If the jury find from the evidence that the contract and specifications agreed upon for the construction of the building provided for heating by
If changes were made in the contract after it was executed, in either of the respects mentioned in this instruction, without the consent of the defendant, then the defendant ceased to be bound as a surety on the bond. Such changes would discharge the surety, unless he gave his consent thereto. Beers v. Wolf, 116 Mo. 179. But there are several objections to these instructions. In the first place the court should have told the jury what the terms of the contract were in these respects, instead of leaving it to the jury to say whether the specifications called for hot air flues, or for a gravel roof. The specifications are in writing, and they constitute a part and parcel of the contract. It is useless to cite authorities to show that it is the duty of the court, and not of the jury, to construe written contracts.
In the next place, on turning to the specifications prepared by Mr. Hogg, we find that the roof was to be a mansard roof, the “rake” of the sides to be covered with shingles, and the deck with I. C. tin. There is not a thing in the specifications prepared by Mr. Park to modify or change this call for a tin roof. The specifications prepared by Park and made a part of the contract, contain this as the last clause: “A door may be made at the foundation at the proper place for heating the building, and the tin piping through the house at necessary places, to be in readiness for the hot air furnace.” It is, therefore, plain that the contract for the performance of which the defendant
But it is said they were properly submitted to the jury because there was evidence tending to show that the specifications had been altered by erasures and interlineations, after the execution of the contract, so as to make them call for a gravel roof and hot air pipes. The evidence bearing upon this subject is to the foliowing effect: Mr. Park was a man advanced in years. He resided in the state of Illinois. He concluded to build an addition to Park College at his own expense, and procured Mr. Hogg, an architect, to prepare plans and specifications for a brick structure, but to reduce the expense concluded to use wood instead of brick. He did not have new specifications prepared, but prepared some himself, making a few changes only, generally such as became necessary by the change from brick to wood. The specifications prepared by him and those prepared by the architect are mentioned in the contract. On May 13, 1889, he and Mr. Byers examined the specifications prepared by himself, and concluded they were too indefinite in several respects. Several alterations and interlineations were made by Byers and Mr. Park at that time. Byers then took all of the specifications from Parkville to Kansas City, and there went over them with Rider, one of the contractors. Byers was to consult Rider in regard to hot air flues. During the consultation, the last clause of the specifications was changed so as to read as before set out. Rider took the specifications as thus changed for the purpose of making a copy, and at a subsequent date executed the contract at Parkville. Byers says the interlineations and erasures were all
The further testimony of Mr. Byers is that he was the agent of Mr. Park for the purpose of paying out money, and he went to Parkville about oncea month to see the building as work progressed. Kahm looked after the same matters for Park at Parkville. Mr. Byers states in his cross-examination that Rider & Son were to have $60 extra for putting on a tin roof, but he says he does not know whether this agreement was made before or after the execution of the written contract. He says Rider was to have $75 for putting in hot air flues, but it is evident that in making this statement he speaks of his negotiations with Rider before the execution of the contract.
The defendant places some stress on the following letter from Park to Rider, dated in July, 1889:
“I am glad that you are progressing finely with the house. I am thinking perhaps we had better put up the furnace either by steam or heat when we are about it. What will be the price, either by heat or steam, put up complete and leveled down? Please write to me. I will write Mr. Byers about it in a day or two. It will save stoves, etc.”
Now the call for a tin roof is found in the specifications prepared by the architect and nowhere else, and these specifications were never changed by erasures or interlineations. The specifications prepared by Mr. Park do not now, and never did, mention the material of which the roof was to be made. There is no evidence showing, or even tending to show, any change of the specifications on this subject. The evidence is all to the effect that the changes made in the specifica
The judgment is reversed and the cause remanded for a new trial.