209 Mass. 474 | Mass. | 1911
This is an action of contract. The declaration contains five counts, only four of which are now material. The first count is upon a written contract between the plaintiffs and the defendant, by which the former undertook to erect a power electric and heating plant for the defendant, and alleged partial performance by the plaintiffs and unreasonable refusal by the defendant to permit them to complete it. The third and fourth counts are for work done and materials supplied, as extras to the contract. The fifth count is upon a quantum meruit for the same work claimed under count one. The answer sets up that the contract did not comply with St. 1898, c. 170, or St. 1897, c. 137, and that the work under the contract was not done as required by it to the satisfaction of the architect, who for this reason acting under the contract stopped further performance of it. The case was sent to an auditor, who found the facts in favor of the plaintiffs. It was thereafter tried upon the auditor’s report and additional evidence, part of which was oral, before a judge of the Superior Court, who found generally for the defendant. The case is brought here by the plaintiffs’ exceptions to the refusal of the trial judge to grant certain rulings.
The contract provided that the work was “ A. ... to be done and materials furnished under the direction of an engineer selected by the architect and to the satisfaction of the architect and such engineer. . . . And in case . . . said work or materials . . . shall be unsatisfactory to the said architect, then the said party of the second part shall, on being notified thereof, in writing, by the said architect, immediately remove such unsatisfactory work or materials, and supply the place thereof with other work and materials satisfactory to the architect.” “ B. . . . all work contemplated and described by the plans and these specifications and this contract shall be done to the satisfaction of the said architect and engineer . . . and who shall be the sole judges as to the fitness of the work and materials as herein set forth. If any objection is made by the architect or engineer to any work or materials, then the said party of the second part shall remove such unsatisfactory work and materials.” “ C. And if, at any time, any of the work mentioned in said specifications is not progressing, or any materials are not in accordance with the said'
The first ruling asked for by the plaintiffs, which was a general one, that they were entitled to recover, could not have been given properly. The burden of proof was upon the plaintiffs, and where an affirmative issue must be made out by one party upon evidence, a part of which is oral, ordinarily such a ruling cannot be given as matter of law.
The second ruling called for a finding of fact, which, by refusing to give, the trial judge apparently decided adversely to the plaintiffs. In view of the finding which must have been made in order to refuse the second prayer, the third was also properly refused. Moreover this prayer was not quite an accurate statement of the law. It might be that “ the covering furnished by the plaintiffs was not inferior in quality or otherwise to that of the Asbestos Paper Company,” and yet a rejection of it might be within the legal right of the architect and engineer acting in good faith and not whimsically, even though somewhat ignorantly or mistakenly.
The fourth, fifth, seventh and eighth requests ask for findings of fact, which by its refusal the court seems not to have been able to make.
The sixth prayer called for a ruling of law which was correct in its terms but for a finding of fact which it appears from the other findings of fact requested the court was unable to make.
The eighth and ninth prayers were requests for rulings of law based upon a certain construction of all the evidence. But, as there was some slight evidence that a five-ply covering alone would satisfy the terms of the contract, it does not appear that the facts existed which were assumed in the prayer.
The contract also provided that the plaintiffs should not be entitled to demand payment for any portion of the work done or materials furnished “ until each and all of the stipulations ” contained in the contract “ are complied with and the architect shall have given his certificate to that effect, and until all disputes, disagreements, and questions between the parties hereto, affect
Although the case appears to be one of great hardship to the plaintiffs, the governing rules of law make no other result possible upon these exceptions.
Exceptions overruled.