{¶ 1} Plaintiff-appellant, Evans, Mechwart, Hambleton & Tilton, Inc. (“EMH & T”), appeals from a judgment of the Franklin County Court of Common Pleas in favor of defendant-appellee, Triad Architects, Ltd. (“Triad”). For the following reasons, we reverse the judgment and remand the cause.
{¶ 2} In January 2007, Triad entered into an agreement with Centurion Development Group, L.L.C. (“Centurion”) to provide architectural and engineering plans for a residential development that Centurion wanted to build. Triad asked EMH & T to supply civil-engineering services on the project. On January 22, 2007, Triad and EMH & T executed a contract whereby Triad agreed to pay EMH & T $128,550 for environmental- and engineering-due-diligence work, surveys, and development plans, as well as additional specified services.
{¶ 3} Centurion also hired Triad to work on another development project. In a second contract with Centurion, Triad agreed to provide architectural and engineering plans for a nine-story condominium building. Again, Triad turned to EMH & T for the civil-engineering work on the project. On July 9, 2007, Triad and EMH & T entered into a contract whereby Triad agreed to pay EMH & T $60,200 for a construction plan, landscape plan, topographical survey, geotechnical investigation, and other services.
{¶ 4} For the most part, Triad and EMH & T relied on the American Institute of Architects (“ALA”) Standard Form of Agreement Between Architect and Consultant (Document C141-1997) to supply the terms of their January 22 and July 9, 2007 contracts. Thus, both contracts provided:
§ 12.5 Payments to the Consultant shall be made promptly after the Architect is paid by the Owner under the Prime Agreement. The Architect shall exert reasonable and diligent efforts to collect prompt payment from the Owner. The Architect shall pay the Consultant in proportion to amountsreceived from the Owner which are attributable to the Consultant’s services rendered.
In both contracts, the parties added the following term to the ATA form agreement:
§ 13.4.3 * * * The Consultant shall be paid for their services under this Agreement within ten (10) working days after receipt by the Architect from the Owner of payment for the services performed by the Consultant on behalf of their Part of the Project.
{¶ 5} EMH & T substantially completed all services required under the two contracts by December 11, 2007. EMH & T then billed Triad a total of $150,482.29. Triad, however, refused to pay. In response to EMH & T’s attempts to recover payment, Triad contended that sections 12.5 and 13.4.3 of the parties’ contracts required it to pay EMH & T only when and to the extent that Centurion paid it. Centurion canceled both projects and refused to pay Triad. Because Triad never collected payment from Centurion, Triad disclaimed any obligation to pay EMH & T.
{¶ 6} EMH & T filed suit against Triad, asserting claims for an account stated, professional services rendered, breach of contract, and unjust enrichment. Both parties moved for summary judgment. On November 17, 2010, the trial court entered a decision and final judgment granting Triad’s motion for summary judgment and denying EMH & T’s motion for summary judgment. EMH & T now appeals from that judgment, and it assigns the following errors:
The trial court erred in overruling Plaintiff-Appellant’s Motion for Summary Judgment when it failed to consider established Ohio case law and construction industry standards in deciding that the language contained in the parties’ contracts with respect to payment by Appellee constituted a “pay-if-paid” rather than “pay-when-paid” obligation as a matter of law.
The trial court erred in sustaining Defendanb-Appellee’s Motion for Summary Judgment since the pleadings and affidavits filed by DefendantAppellee are inadequate and inadmissible as parol evidence, but even if considered, create rather than eliminate genuine issues of material fact.
{¶ 7} Because EMH & T’s two assignments of error are interrelated, we will address them together. Both assignments of error challenge the trial court’s ruling on the parties’ motions for summary judgment. Entry of summary judgment is appropriate when the moving party demonstrates that (1) there is no genuine issue of material fact, (2) the.moving party is entitled to judgment as a matter of law, and (3) reasonable minds can come to but one conclusion when viewing the evidence most strongly in favor of the nonmoving party, and that conclusion is adverse to the nonmoving party. Hudson v. Petrosurance, Inc., 127
{¶ 8} The parties’ dispute centers on the meaning of the contractual language setting forth Triad’s obligation to pay EMH & T. Triad argues that sections 12.5 and 13.4.3 create a condition precedent: it must receive payment from Centurion for its duty to pay EMH & T to arise. According to Triad’s interpretation of the parties’ contracts, it owes EMH & T nothing because Centurion did not pay it. EMH & T disagrees, and instead contends that sections 12.5 and 13.4.3 impose on Triad an absolute duty to pay EMH & T within a reasonable time. Under EMH & T’s interpretation, Centurion’s failure to pay Triad does not negate Triad’s obligation to pay EMH & T.
{¶ 9} This dispute is an iteration of a long-standing disagreement between general contractors and subcontractors over the enforcement of “pay-when-paid” and “pay-if-paid” contractual provisions. “ ‘A typical “pay-when-paid” clause might read: “Contractor shall pay subcontractor within seven days of contractor’s receipt of payment from the owner.” ’ ” MidAmerica Constr. Mgt., Inc. v. MasTec N. Am., Inc. (C.A.10, 2006),
{¶ 10} Under the custom in the construction industry, the risk of an owner’s nonpayment rests on the general contractor. Power & Pollution Servs., Inc.,
{¶ 11} Unlike a pay-when-paid provision, a pay-if-paid provision transfers the risk of an owner’s nonpayment from the contractor down through the contracting tiers. Chapman Excavating Co. at ¶ 22. See also Sloan & Co.,
{¶ 12} A pay-if-paid provision must clearly and unambiguously condition payment to the subcontractor on the receipt of payment from the owner. Kalkreuth Roofing & Sheet Metal, Inc. v. Bogner Constr. Co. (Aug. 27, 1998), 5th Dist. No. 97 CA 59,
{¶ 14} The majority approach to pay-when-paid and pay-if-paid provisions stems from the general disfavor in the law towards conditions precedent. A condition precedent is an event that must occur before an obligation in the contract will become effective. Moody v. Ohio Rehab. Servs. Comm., 10th Dist. No. 02AP-596,
{¶ 15} Because the law disfavors conditions precedent, “ ‘whenever possible courts will avoid construing provisions to be such unless the intent of the agreement is plainly to the contrary.’ ” Hiatt at ¶ 23, quoting Rudd v. Online Resources, Inc. (June 18, 1999), 2d Dist. No. 17500,
{¶ 16} As the Restatement explains, a forfeiture, in this context, is the denial of compensation that results when the obligee loses its right to the agreed exchange after he has relied substantially, as by performance, on the expectation of that exchange. Restatement of the Law 2d, Contracts, Section 227, Comment b and Section 229, Comment b. To illustrate the rule disfavoring forfeiture, the Restatement offers the following example:
[Ujnder a provision that a duty is to be performed “when” an event occurs, it may be doubtful whether it is to be performed only if that event occurs, in which case the event is a condition, or at such time as it would ordinarily occur, in which case the event is referred to merely to measure the passage of time. In the latter case, if the event does not occur[,] some alternative means will be found to measure the passage of time, and the non-occurrence of the event will not prevent the obligor’s duty from becoming one of performance. If the event is a condition, however, the obligee takes the risk that its non-occurrence will discharge the obligor’s duty.
Restatement of the Law 2d, Contracts, Section 227, Comment b. See also Franklin Consultants, Inc. (“ ‘The time of performance is sometimes * * * made to depend upon the happening of some event which the parties to the contract do not covenant to cause to happen. The tendency of the courts is to hold that unless the contract shows clearly that such an action is an express condition, the
{¶ 17} This example mirrors the situation presented by a typical pay-when-paid provision. A pay-when-paid provision is susceptible to two interpretations; namely, (1) as setting a condition precedent to payment or (2) as fixing the point in time when payment would ordinarily occur. In the face of this ambiguity, courts avoid forfeiture by construing the pay-when-paid provision as a promise to pay and making payment due within a reasonable time. R.N. Robinson & Son, Inc. at 886; Lafayette Steel Erectors, Inc. at 587; Brown & Kerr, Inc. v. St. Paul Fire & Marine Ins. Co. (N.D.Ill.1996),
{¶ 18} Here, the parties’ contracts contain two contractual provisions that Triad claims qualify as pay-if-paid provisions: sections 12.5 and 13.4.3. We will deal with section 13.4.3 first. That section, which the parties themselves drafted and added to the AIA form agreement, states:
The Consultant shall be paid for their services under this Agreement within ten (10) working days after receipt by the Architect from the Owner of payment for the services performed by the Consultant on behalf of their Part of the Project.
Contrary to Triad’s argument, this provision is a prototypical pay-when-paid provision. See, e.g., Chapman Excavating Co. at ¶ 4, 34 (holding that contractual language requiring “[p]artial payments of the Subcontract Sum shall be made within ten (10) days after payment is received by [the general contractor] from Owner” constituted a pay-when-paid provision); R.N. Robinson & Son, Inc. at 885, 887 (holding that contractual language requiring “[p]ayment to [the subcontractor] will be made at a reasonable time after receipt of payment from the Owner; approximately 10 working days” was a pay-when-paid provision); G.E.L. Recycling, Inc. at 432, 434 (holding that contractual language stating “[p]ayments will be made for the value of the work installed each week within 7 business days after receipt of payment from the owner” was a pay-when-paid provision).
Payments to the Consultant shall be made promptly after the Architect is paid by the Owner under the Prime Agreement. The Architect shall exert reasonable and diligent efforts to collect prompt payment from the Owner. The Architect shall pay the Consultant in proportion to amounts received from the Owner which are attributable to the Consultant’s services rendered.
Triad focuses on the last sentence of this section and argues that it establishes a condition precedent to its duty to pay EMH & T. According to Triad’s interpretation of this sentence, only Triad’s receipt of some payment from Centurion will trigger its obligation to pay EMH & T a proportion of the amount received.
{¶ 20} We find that the language of section 12.5 is not explicit enough to indicate that the parties intended to create a condition precedent. Section 12.5 does not expressly make payment from Centurion a condition precedent to payment of EMH & T, address which party will bear the risk of Centurion’s nonpayment, or require Triad to pay EMH & T exclusively out of monies paid to Triad by Centurion. The last sentence of Section 12.5 directs Triad only on what to do upon payment from Centurion; it assumes that Triad will receive payment. The sentence, however, is silent as to the extent of Triad’s obligation if Centurion fails to pay. We will not infer from this silence an intent to create a condition precedent, particularly when the condition precedent would result in a forfeiture of any compensation for EMH & T’s work. See Wisznia v. Wilcox (Tex.App. 1969),
{¶ 21} Although not necessary to our analysis, AIA commentary complements our conclusion that section 12.5 is a pay-when-paid, and not a pay-if-paid, provision. According to the AIA’s Guide for Amendments to AIA Owner-Architect Agreements (Document B503-2007), “AIA Standard Architect-Consultant agreements do not contain a pay-if-paid clause.” The guide goes on to caution that “[a] pay-if-paid clause must clearly establish the intent of the parties to shift the credit risk of the Owner’s insolvency and should include the words ‘condition precedent.’ ” To modify the AIA form agreement between an architect and consultant to include a pay-if-paid provision, the guide recommends the following language:
It is specifically understood and agreed that the payment to the Consultant is dependent, as a condition precedent, upon the Architect’s receipt of paymentfrom the Owner. Consultant acknowledges the risk of non-payment to the Architect by the Owner which may result in non-payment to the Consultant by the Architect.
In the case at bar, the parties did not supplement their contracts with this language or any other similar language.
{¶ 22} In a final effort to convince this court that the parties intended to be bound by a pay-if-paid provision, Triad points to the parties’ spring 2007 negotiations regarding additional work that EMH & T performed on the project that was the subject of the parties’ January 22, 2007 contract. When EMH & T proposed the additional work, it attached to its proposal a form entitled “Terms and Conditions of Professional Service” and stated that the form “shall be considered as part of this proposal.” Among numerous other terms, the form provided, “Client is liable for timely payment of invoiced amounts without regard to whether Client has received financing, payments, or income from any source, including funds related to the project for which services were provided by EMHT.” In the letter authorizing the additional work, Triad replied that the January 22, 2007 contract governed the additional work and “supercede[d] any conflicting language in your attached proposal.” From this exchange, Triad concludes that EMH & T understood that each of the parties’ contracts contained a pay-if-paid provision.
{¶ 23} As we stated above, whether a contractual provision is a condition precedent is a matter determined by the parties’ intent, which a court ascertains from the language of the particular provision, the language of the entire agreement, and the subject matter of the agreement. Adkins,
{¶ 24} Moreover, even if Triad’s evidence was relevant, we find that it would be insufficient to convince reasonable minds that EMH & T construed sections 12.5 and 13.4.3 as pay-if-paid provisions. Triad characterizes the spring 2007 negotiations as an attempt by EMH & T to place a provision guaranteeing it payment in the parties’ July 9, 2007 contract. Triad then reasons that EMH & T would not have made this attempt if it truly believed that sections 12.5 and 13.4.3 protected its financial interests. Reasonable minds would find this interpretation of the evidence unpersuasive for two reasons. First, the parties were negotiating adding to the scope of work contemplated in the January 22, 2007 contract, not the wording of the terms for the July 9, 2007 contract. Second, during the
{¶ 25} As sections 12.5 and 13.4.3 are pay-when-paid provisions, Triad owed EMH & T a duty to pay it within a reasonable time after the completion of its work. Courts allow a delay of payment for a reasonable time to “afford[ ] [the contractor] the opportunity of procuring from the owner the funds necessary to pay the subcontractor.” Thos. J. Dyer Co.,
{¶ 26} Here, EMH & T substantially performed all services set forth in the contracts by December 11, 2007. Consequently, EMH & T has been waiting over three and one-half years for payment. Given this lengthy delay, we find that as a matter of law, Triad has had a sufficient opportunity to pursue payment from Centurion. Consequently, we conclude that Triad breached its contractual duty to pay EMH & T within a reasonable time. The trial court thus erred in granting Triad summary judgment and denying EMH & T summary judgment.
{¶ 27} Based upon the forgoing, we sustain EMH & T’s first and second assignments of error. We reverse the judgment of the Franklin County Court of Common Pleas, and we remand this matter to that court so that it may enter judgment consist with law and this decision.
Judgment reversed and cause remanded.
