Eua Cogenex Corp. v. North Rockland Central School DistrictEua Cogenex Corp. v. North Rockland Central School District
MEMORANDUM DECISION AND ORDER GRANTING AND DENYING IN PART PLAINTIFF AND DEFENDANT’S MOTION FOR SUMMARY JUDGMENT
EUA Cogenex (“EUA”) asserts three causes of action against the North Rock-land Central School District (“the District”) arising from the District’s failure to pay EUA under an energy savings performance contract: (1) breach of contract; (2) breach of an implied covenant of good faith and fair dealing; and (3) unjust enrichment. Plaintiff moves for summary judgment on those claims. Defendant cross moves for summary judgment on plaintiffs claims of breach of the covenant of good faith and fair dealing and unjust enrichment. Defendant counterclaims, alleging violation of N.Y.Gen.Bus.L. § 349, and plaintiff moves for summary judgment on that claim.
PROCEDURAL HISTORY
At the outset of this litigation, the District moved to dismiss this action on the ground that EUA had not served a notice of claim as required by New York Education Law. EUA cross-moved for leave to file a late notice, pursuant to N.Y.Edue.L. § 3813(2-a). This Court granted such leave, and EUA served the required notice of claim.
The District now moves to dismiss the action, claiming that the notice of claim was defective because only state courts have jurisdiction to grant leave to serve a late notice. Defendant is incorrect.
The cases cited by the defendant all support the proposition that a federal court may not grant leave to serve a late
There is no such requirement for a contract action brought under the New York Education Law. This Court is empowered to grant leave to file a late notice of claim by Education Law § 3813(2-a). Unlike § 50-e of the General Municipal Law, the Education Law sets no jurisdictional requirements for applying for a late notice of claim. It simply states that “[u]pon application, the court, in its discretion, may extend the time to serve a notice of claim.” N.Y.Educ.L. § 3813(2-a). If a formal application is made by a Plaintiff, as was done in this case, a federal court can give it proper consideration.
See Courtem-anche v. Enlarged City Sch. Disk of the City of Middletown,
Defendant’s motion to dismiss is denied.
FACTS PERTINENT TO THE MOTION
1. Proposal For The Energy Services Lease Agreement
EUA and the District signed an Energy Services Lease Agreement (“ESLA”) as part of an energy conservation program sponsored by Orange and Rockland Utilities (“ORU”) on August 28, 1991. The ESLA is an energy performance contract, under which a contractor such as EUA agrees to install and maintain energy savings equipment on the owner’s premises and then is paid a portion of the energy savings in consideration for installation of the equipment. ORU hired EUA under a bidding program to install such equipment throughout Rockland County.
EUA undertook a review of the District’s then-existing lighting fixtures and estimated the savings that the District would expect to receive based on EUA’s installation of energy-saving equipment. Plaintiff then forwarded a proposal letter to the District, dated June 6, 1991, that summarized the savings that the District could expect to receive as a result of the contract. (Hammel Aff. at Exh. 10; Lennon Dep. at 50-53.) In the letter, EUA stated:
The enclosed reflects installation of Demand Side Management measures which will reduce your electrical energy cost for installed lighting measures by approximately $218,018 for the first year and representing a total over the fifteen years term of $2,117,894- These savings are provided to you at no cost for installation of measures. EUA will pay for all engineering, design, installation, and supervision of work to be performed.
(Hammel Aff. at Exh. 10.) (emphasis added). The proposal letter was signed on the same day as the original ESLA and was incorporated by reference in the ESLA. The Proposal also offered a $30,000 “signing bonus” for the District for agreeing to the terms of ESLA. The ESLA was signed by William H. Sullivan, Assistant Superintendent of the District, and Arthur P. Lennon, Vice President of EUA.
The representations made in EUA’s proposal letter to the District as to the dollar
The ESLA required Cogenex to install high efficiency lighting and other energy conservation measures (the “Equipment”) at the Thiells Elementary School, Gerald Neary Elementary School, North Gerner-ville Elementary School, BOCES Elementary School, West Haverstraw Elementary School, Haverstraw Middle School Annex, Maintenance Building, North Rockland High School, Haverstraw Middle School, James A. Farley Middle School, and Tompkins Cove Warehouse. The ESLA provided that Cogenex would lease the Equipment to the Defendant for a fifteen-year term.
2. Savings and Measurement Terms Under ESLA
William Sullivan led all ESLA negotiations with EUA. Under the ESLA, the District and EUA agreed to the following two-part procedure to measure savings (the “Measurement Terms”):
(a) Prior to installing the Equipment, [EUA] would determine the energy demand, measured in kilowatts (“kw”), of the Premises’ existing lighting system.
(b) After the Equipment was installed, [EUA] would determine the Premises’ post-installment energy demand for the lighting system, again measured in kw. By comparing this figure to the pre-installation kw demand, [EUA] would determine the reduction in kw resulting from the Equipment.
(Hammel Aff. Exh. 2 (ESLA, Append.II.))
EUA performed a room by room survey of lighting fixtures before and after the installation of the Equipment. The survey included the type and number of lighting fixtures, and tested a sample of each type of fixture with a wattmeter to determine average energy demand required by each fixture type. To determine total kilowatt demand, EUA multiplied the average kilowatt demand for each type of fixture, as measured by a sampling process, by the total number of fixtures of that type. (Id.) EUA then added the total kilowatt demand determined through this process for each type of fixture to determine the total energy demand for lighting equipment. (Id.)
EUA discussed the ESLA Measurement terms with the District both before the ESLA was signed and again before significant work pertaining to the ESLA was performed. (ESLA; Lennon Dep. at 55, 58, 79.) The parties agreed to the ESLA Measurement terms by signing Appendix II. (ESLA Append. II; Hammel Aff. at Exh. 4 (Sullivan Dep.) at 43.)
The ESLA also provided terms for the District’s payment obligation. The District’s payments were to equal a percentage of energy cost savings attributable to the Equipment, as measured by the method described in ESLA. It provided that “[t]he amount of payment made by [the District] for energy savings shall be equal to 0% for year 1, 60% for years 2 through 4, 55% for years 5 through 10 and 50% for years 11 through 15 of the savings as shown on the ECR each month for a term of 15 years.” (Id.) To determine energy cost savings effected by the Equipment, the parties agreed that they would multiply the kilowatt and kilowatt hour reduction determined in the manner agreed to in the ESLA by ORU’s published kilowatt and kilowatt hour charges. (Id. at Append. II, subpart d.) The ESLA also provided that if the District failed to operate its lighting system for at least 95% of the hours set forth in the Proposal, Cogenex could invoice the District as if the District
3. Post-Installation Audits
After execution of the ESLA, EUA began installation of the energy saving lighting at the District’s premises. According to EUA, post-installation audits performed by EUA confirmed that kilowatt savings attributable to the Equipment was 905.23 kilowatts, an amount higher than the 639 kilowatts which was estimated in the Proposal. (Aronson Aff. at Exh. 8.) Plaintiff alleges that these audits were confirmed by ORU. Defendant disputes that fact, claiming that the verification was done by ANC Enercom, a contractor unaffiliated with ORU. (Hammel Aff. at Exh. 1 (Thorpe Dep.) at 128.).
By letters dated May 18, 1992, August 12, 1992 and October 2, 1992, ORU informed EUA that it approved all of EUA’s post-installation reports. (Hammel Aff. at Exh. 12.) As approved by the ORU-sponsored energy conservation program of which ESLA was a part, ORU paid EUA installments of $196,622.73, $119,121.04 and $37,415.79 for achieving the verified kilowatt reduction. (Hammel Aff. at Exh. 13; Thorpe Dep. at 85.)
The term of the ESLA began in March 1992 upon certification that the installation of the Equipment was “substantially complete.” In accordance with the ESLA, no payment was due from the District for the one-year period after installation of the equipment — March 1992 to March 1993. (ESLA, Hammel Aff. at Exh. 2.) In March 1993, EUA began invoicing the District for monthly payments under the ESLA, and the District began paying EUA for its share of energy savings.
These invoices were based upon EUA’s calculation that the installation of its equipment ultimately resulted in a reduction of the District’s overall electrical demand by a total of 879.7 KW and 2,573,319 KWH based on the District’s hours of operation of the lighting equipment. (Ar-onson Dep. at 187-190; Porter Dep. at 151-155.) The District paid EUA’s invoices for a period from March 1993 to October 1993 in the total amount of $114,421.00.
4. Amendment to Initial Contract
By letter dated February 16, 1994, EUA notified the District that it was not meeting the required minimum operating hours specified in the ESLA. (Hammel Aff. at Exh. 16.) The District had previously stopped payments to EUA in late 1993 because of concerns about EUA’s performance under the contract (Sullivan Dep. at 139-140.). It contacted EUA to request a review of the District’s concerns about the installation and performance of the equipment, as well as the amount of energy savings the District was enjoying under the ESLA.
EUA’s representatives met with William Sullivan in June 1994, the District’s then-Assistant Superintendent for Business, and Edmond R. Nolin, the District’s then-Director of Facilities to discuss a possible amendment to the ESLA under which the District would pay a fixed monthly payment in lieu of monthly payments that varied with the District’s hours of use. Nolin signed the amendment to the ESLA (“the Amendment”), which provided that the District would make monthly payments in the amount of $15,315 to EUA for the remaining term of the ESLA. It also provided that the District would pay the outstanding balance of then-overdue invoices under ESLA amounting to $99,999.95. (Hammel Aff. at Exh. 18.) The amendment required that all other terms of the ESLA remain in full force and effect. (Hammel Aff. at. Exh. 18.) No resolution of the District’s Board of Education was ever passed authorizing execution of the amendment. (Sullivan Dep. at 163.)
The District subsequently remitted to EUA the overdue payments, totaling $100,693.68. Because the monthly payment had been fixed by the Amendment at
Defendant thereafter made monthly payments to EUA until May 1998. Since execution of the ESLA, the District has paid more than $934,000 to EUA (Pretrial Stipulation ¶ 17). During this period, each monthly payment made by the District to EUA was approved by the District’s Director of Facilities, Superintendent for Business, and Board of Education.
5. The Alleged Breach
The District did not make payment on EUA’s June 1998 invoice, which was due by the end of that month. It did not make any further payments due on the ESLA. Defendant alleges that in May 1998, as a result of a review of the EUA contract conducted by an independent energy consultant, it concluded that EUA had substantially overbilled the District by failing to produce the energy savings that were called for in the parties’ proposal and upon which EUA’s invoices to the District were based.
Defendant specifically points to EUA’s representation in its June 6, 1991 letter that it would reduce the District’s electric bill by $213,018 in the first year after implementation of the contract. In the year prior to the contract, the District’s electric bills were $543,513 for the buildings covered by the contract. (Feinstein Aff. at Exh. 3) In the one year after, the District’s bills were $446,010, representing a reduction of just $97,503. Defendant claims that when the District’s payments to EUA were factored in, the District’s overall expenditures for electricity substantially increased, contradicting the terms of the ESLA under which the District was only to pay EUA a percentage of its savings resulting from installation of the equipment.
Plaintiff contends that the 1994 Amendment requires that the District remit $15,315 to EUA for the remainder of the contract term. Paragraph 14(c) of the ESLA provides that the District shall be in default of the Agreement if it fails to make payment to EUA as invoiced by EUA. (ESLA, Hammel Aff. at Exh. 2.) Paragraph 16(a) of the ESLA provides: “In the event of a default by [the District], [EUA] shall have the right to ... Receive from [the District] any amount that is due, or which would become due if [the District] did not default and the Equipment remained installed and active for the term of this Agreement, including all monthly payments due for the remainder of the term of this Agreement, plus costs to remove the Equipment.” (Id.)
DISCUSSION
A party is entitled to summary judgment when there is no “genuine issue of material fact” and the undisputed facts warrant judgment for the moving party as a matter of law. Fed.R.Civ.P. 56(c);
Anderson v. Liberty Lobby, Inc.,
The primary objective of a court in interpreting a contract is to give effect to the intent of the parties as revealed by the language of their agreement.
See Compagnie Financiere De Cic Et De L’UNION Europeenne, Management Invest Funding Ltd v. Merrill Lynch, Pierce, Fenner & Smith Inc.,
1. Breach of Contract
a. Performance Under the ESLA
Under New York law, the elements of a breach of contract claim are as follows: (1) the existence of an agreement; (2) adequate performance of the contract by the plaintiff; (3) breach of the contract by the defendant; and (4) damages.
See Harsco Corp. v. Segui,
The District argues that EUA has failed to make out a prima facie case that it performed under the contract by producing the energy savings called for by its proposal. The District points to the Proposal Letter of June 6, 1991, incorporated by reference into the ESLA, that set forth the savings that the District could expect to receive. (ESLA; Hammel Aff. at Exh. 10.) That letter provided that the installation of the Demand Side Management measures would “reduce your energy cost for installed lighting measures” by $213,018 for the first year, and $2,117,394 over fifteen years. (Hammel Aff. at Exh. 10; Lennon Dep. at 50-53.) Defendant argues that it paid EUA based on the invoices submitted by EUA, obligating EUA to produce the savings. Defendant claims that it achieved no savings under the ESLA.
Plaintiff responds that the defendant’s suggestion that EUA was bound to deliver $213,018 in costs savings during the first year completely ignores the express terms of the ESLA. EUA states that this figure was an estimate — not a contract term — • and maintains that the ESLA itself recognizes that actual energy savings from the Equipment might fluctuate. The kilowatt-hour savings projections by EUA were based on both the kilowatt reduction to be achieved by EUA’s equipment as measured under the ESLA and the number of hours that the Premises used their lighting system.
Finally, the District reviewed a consultant’s report that concluded that the District experienced an average reduction of 22% in energy demand was directly attributable to the performance contract. This was in contrast to the 42% decrease predicted by EUA. (Hammel Aff. at Exh. 28.) The consultant concluded that the District had overpaid EUA by approximately $747,214. (Id.) Defendant argues that when the payments to EUA were factored in, the District’s overall expenditures for electricity substantially increased, even though the District did not undergo significant capital projects. Because under the terms of the ESLA the District was only to pay EUA a percentage of savings resulting from installation, defendant argues that plaintiff did not perform under the contract.
b. ESLA’s 199U Amendment
The question of whether the parties performed under the contract is determined, in part, by whether there was a valid amendment to the ESLA in 1994. The 1994 Amendment had the effect of setting a flat-fee for use of the energy saving equipment, and possibly freeing EUA from specific obligations to produce savings before being compensated. EUA alleges that the amendment was signed and duly executed by a representative of the District with apparent authority to do- so. The District responds that only the School District itself could authorize such a contract; that the plaintiff knew this from past dealings; and that the amendment therefore was not a valid term of the ESLA.
Because the District is the only party with actual authority to enter such contracts, see N.Y.Educ.Law § 1725(2) (McKinney 2000) (“Before executing any such agreement, the board of education must adopt a resolution determining that such agreement is in the best financial interests of the school district and stating the basis of that determination”), the questions are (1) whether Edmond Nolin had the apparent authority to amend the ESLA, and if not, (2) whether the District ratified the 1994 Amendment. For the reasons stated below, I find that the 1994 Amendment formed a part of the ESLA as a matter of law.
1. Apparent Authority
A principal drapes its agent with apparent authority by holding its agent out in such a way that causes a reasonable third party to believe that the agent is authorized to enter into the transaction in question.
See Lehman Bros. Commercial Corp. v. Minmetals Int'l Non-Ferrous Metals Trading Co.,
Defendant argues that William Sullivan and Edmond Nolin lacked the apparent authority to amend the ESLA in 1994. It references the deposition testimony of Arthur Lennon, EUA’s former vice president, who stated that he knew it was “customary for school districts to bring matters of this type to the board for approval.” (Hamell Aff. at Exh. 6 (Lennon Dep.) at 62.) Plaintiff disputes that Lennon stated at any point that he knew that the contract would not be valid and binding absent board approval. Accordingly, the record reveals the existence of issues of fact as to whether Nolin had implied authority to enter the contract on behalf of the District.
2. Estoppel and Ratification
But even if Nolin did not have apparent authority to enter into the 1994 Amendment to ESLA, defendants are es-topped from asserting lack of authority, because they performed under the amended contract for four years.
A governmental agency may be subject to estoppel if it is shown that a manifest injustice resulted from actions taken by the agency in its proprietary or contractual capacity.
See Branca v. Board of Education,
Defendant relies on
In Re Dayho Motel v. Assessor of the Town of Orangetown,
However, the District will be bound by the amendment if, with actual or imputed knowledge, it ratified Nolin’s actions.
See Prisco v. State of New York,
Defendant also cites
A.C. Transp., Inc. v. Board of Education,
In
A.C. Transp.,
The case at bar presents a different situation. The District’s agent Nolin may not have had actual or apparent authority to sign the 1994 Amendment on the District’s behalf. However, the District acted on that contract, remitting over $100,000 of overdue payments from a period prior to the amendment, and continuing to pay the fixed rate of $15,315 per month for nearly four years afterward. The District therefore had to know of Nolin’s actions,
see Prisco v. State of New York,
As a result of the District’s ratification of Nolin’s action, the District is estopped from denying that the 1994 amendment served as part of the ESLA.
c. The Integrated Contract Terms
The 1994 Amendment adds the following Section 4 of the ESLA, pertaining to “Payment Method (Energy Savings)”:
Customer agrees to make One (1) payment in the amount of $99,999.95 which Customer and Cogenex agree represents the amount currently owing under the Agreement and is due upon execution of this Amendment by Customer; and
Customer agrees to make One Hundred Fifty-Four (154) consecutive monthly payments each in the amount of $15,315.00 commencing with the invoice for the billing period of May 20 through June 20, 1994. This payment amount shall remain fixed throughout the Term of the Agreement. The value of any additional units of energy saved will be retained by the customer....
The effect of this First Amendment ... shall be the same as if the Agreement had been correct originally and in all other respects, all of the terms and conditions of the above captioned Agreement shall remain in full force and effect.
(Hammel Aff. at Exh. 18.)
The parties dispute the effect of the Amendment on the ESLA. Prior to the Amendment, “[t]he amount of payment made by [the District] for energy savings shall be equal to 0% for year 1, 60% for years 2 through 4, 55% for years 5 through 10 and 50% for years 11 through 15 of the savings as shown on the ECR each month for a term of 15 years.” (ESLA, Hammel Aff. at Exh. 2.) Despite changing the measurement terms, after the 1994 Amendment, all other terms of the ESLA “remain in full force and effect.”
The question of whether the District’s agreement to move to a flat-rate payment scheme relieved EUA from providing the “promised” savings is a material fact for a jury to consider. This court is empowered to resolve ambiguity in contractual language as a matter of law if the evidence about the parties’ meaning is so one-sided that no reasonable person could decide to the contrary.
See Compagnie Financiere De Cic Et De L’UNION Europeenne, Management Invest. Funding Ltd v. Merrill Lynch, Pierce, Fenner & Smith Inc.,
There is sufficient ambiguity in the language of the amended ESLA to deny plaintiffs motion for summary judgment. The ESLA is a contract requiring EUA “to survey, install, maintain and control Energy Conservation Equipment” for the purpose of reducing energy consumption at District schools. (ESLA, ¶ 1.) As originally conceived, EUA was to be paid as a percentage of the energy savings by the District. (Id-¶ 4(a).) The District bore the responsibility of sending on monthly electric bills to EUA for calculation of “the exact amount due and payable and the difference between such amount and the amount previously billed.” (Id-¶ 13.)
The defendant alleges that the flat-payment as specified in the Amendment did not relieve EUA of its responsibility to provide energy savings at a certain level. However, by changing the terms of the ESLA, the parties created an ambiguity as to EUA’s performance requirements under the contract. Furthermore, after the Amendment, EUA removed its measuring equipment from the District’s premises, which made calculation of energy savings impossible. For the foregoing reasons, I conclude that there remain material facts in dispute regarding the terms of the
Plaintiffs motion for summary judgment is therefore denied.
2. Covenant of Good Faith and Fair Dealing
Under New York law, there is a covenant of fair dealing and good faith implied in all contracts.
See Carvel Corp. v. Diversified Mgmt. Group,
Such a claim may be brought, if at all, only if it is based on allegations different than those underlying the accompanying breach of contract claim.
See Siradas v. Chase Lincoln First Bank,
Plaintiff argues that the District breached the covenant by failing to pay amounts due and owing under the ESLA. Plaintiff does not charge that this claim is different than the claims underlying the breach of contract action, see id., so it is plainly duplicative. Accordingly, Defendant’s motion for summary judgment on the breach of the covenant of good faith and fair dealing claim is granted.
3. Unjust Enrichment
In order to prevail on a theory of unjust enrichment, “the plaintiff must demonstrate that (a) the defendant has been enriched; (b) the enrichment was at the plaintiffs expense; and (c) defendant’s retention of the benefit would be unjust.”
Van Brunt v. Rauschenberg,
The existence of a valid and enforceable written contract governing a particular subject matter ordinarily precludes recovery in quasi-contract for events arising out of the same subject matter.
See Clark-Fitzpatrick, Inc. v. Long Island R.R. Co.,
Quasi contracts are not contracts at all, although they give rise to obligations more akin to those stemming from contract than from tort. The contract is a mere fiction, a form imposed in order to adapt the case to a given remedy. Briefly stated, a quasi-contractual obligation is one imposed by law where there has been no agreement or expression of assent, by word or act, on the part of either party involved. The law creates it, regardless of the intention of the parties, to assure a just and equitable result.
Clark-Fitzpatrick,
It is impermissible to seek damages in an action sounding in quasi contract where the suing party has fully performed on a valid written agreement, the existence of which clearly covers the dispute between the parties.
See id.
It is only available where the services alleged are sufficiently outside the terms of the contract,
see id.; D Accord Fin. Servs. v. Metsa-Serla Oy,
The governing document in this case is the ESLA. Plaintiff alleges that it fully performed under ESLA and its 1994 Amendment, which is part of the governing agreement between the parties as a matter of law. There is no allegation that the services provided by plaintiff were outside the contract,
see DAccord,
4. Counterclaim under N.Y. Gen Bus. L § 34-9
New York law prohibits the use of deceptive acts or practices in the conduct of any business, trade or commerce or in the furnishing of any service. N.Y.Gen. Bus.Law § 349. As a threshold matter, plaintiffs claiming the benefit of Section 349 must charge conduct of the defendant that is consumer-oriented — namely, that the acts or practices have a broader impact on consumers at large.
See Oswego Laborers’ Local 214 Pension Fd. v. Marine Midland Bank,
In
Oswego,
Although ostensibly directed at “any business,” Section 349 is in fact only
The typical violation contemplated by the statute involves an individual consumer who falls victim to misrepresentations made by a seller of consumer goods usually by way of false and misleading advertising. The consumer oriented nature of the statute is evidenced by the remedies it provides.... The New York cases where plaintiffs have recovered under section 349(h) further reflect its consumer orientation since they uniformly involve transactions where the amount in controversy is small. That the deceptive practices this statute seeks to combat involve recurring transactions of a consumer type is further supported by the origin of the statute. Section 349(h) is substantially modeled on the Federal Trade Commission Act.
Genesco Entertainment,
The District has made no showing that the contract for the provision of energy-saving equipment is “consumer-oriented” under § 349, nor could it under current case law. Although business-to-business transactions could in some rare cases have a wide enough impact on consumers to justify a § 349 claim,
see Oswego,
At issue in the present case is a fifteen year contract, negotiated with the assistance of counsel, involving over $1 million in Equipment. The District therefore cannot prove the first element of a § 349 claim, that EUA’s alleged deceptive practices were “consumer oriented.”
Plaintiffs motion for summary judgment of Defendant’s counterclaim under § 349 is granted. As a result, the Court need not address the other elements of § 349 or whether the District’s claim was filed within the relevant statute of limitations period.
CONCLUSION
There remains one single issue to be tried before a jury: whether the District should be held liable for breach of contract under the ESLA and its 1994 Amendment.
This constitutes the decision and order of the Court.