delivered the opinion of the court:
Defendant in error, Oscar Erikson, (hereafter called plaintiff,) filed his statement of claim in the municipal court of Chicago on March 17, 1911, against plaintiff in error, James R. Ward, hereafter called defendant. Plain- ' tiff’s right of action was based upon a certain building contract entered into by the respective parties July 9, 1907, wherein plaintiff agreed to furnish the material and construct a building for defendant according to certain plans, specificaitions and ordinances, for an agreed price of $4800, the building to be finished by November 1, 1907. The statement of claim alleged $2300 to be due and unpaid under the contract and $195 due for extras not included in the contract, together with interest thereon from November 1, 1907. Defendant filed his affidavit of merits denying plaintiff’s demand, and assigned as reasons that plaintiff had not completed the building according to- plans, specifications and ordinances, setting out in much detail what constituted the failure, and setting up a counter-claim for various items necessary to be done to- complete the building in conformity with the plans and specifications, together with rents lost because the building was not completed as per the contract, amounting in all to $3017. Defendant further filed a motion to dismiss plaintiff’s suit, and assigned as the reason therefor that January 16, 1908, plaintiff instituted a mechanic’s lien proceeding against defendant in the superior court for the same amount here claimed, and that much testimony had been taken in such proceeding, which suit was still pending and undetermined. The motion of defendant to dismiss was denied and trial of the issues had by jury October 31, 1911. On November 2, 1911, and during the progress of the trial, plaintiff filed an amended statement of claim admitting some sixteen changes had been made from the plans and specifications, and alleging the same were made at the request of defendant during the progress of the work. On the same day the defendant filed an amended affidavit of merits denying the allegations of plaintiffs amended statement of claim. November 14, 1911, the jury returned a verdict in favor of plaintiff for $2000, and after a remittitur of $45 by the plaintiff the court overruled defendant’s motions for a new trial and in arrest of judgment and entered judgment against defendant for $1955 and costs of suit. Upon appeal to the Appellate Court the judgment of the municipal court was affirmed, and the case comes to this court for review upon a writ of certiorari issued by this court.
The principal errors alleged going to the merits of the case are the rulings of the court in the giving and refusing of instructions and in the admission and rejection of testimony. It is also urged the court erred in denying defendant’s motion to dismiss or abate the suit on account of the pendency of the mechanic’s lien suit; also- it is claimed the proof shows the building was not constructed in compliance with the ordinances of the city of Chicago, and that this should have been held sufficient to defeat plaintiff’s right to a recovery.
The contract provided that plaintiff was to furnish the labor and material and construct the building for $4800. It was to be completed on or before November 1, 1907, and was to be constructed according to plans and specifications made by architect Walter, in a good, workmanlike and substantial manner, “to the satisfaction” of defendant, under the direction of the architect, the consideration to be paid in sums in proportion to the progress of the work. On the first day of August defendant paid, in accordance with the architect’s certificate, $600. On the fifth of August •he discharged the architect and did not employ any other architect or superintendent but thereafter superintended the building himself. August 15 he paid plaintiff $1400 on the contract and October 17 $500, making a total paid on the contract of $2500. He thereafter refused to make further payments, for the reason he claimed the work had not been done in accordance with the contract, plans and specifications.
It is insisted the court erroneously construed the provision of the contract that the work was to- be done according to the drawings and specifications, to the satisfaction of the defendant, under the direction o'f the architect, and erroneously instructed the jury as to the rights of the parties under the terms of the agreement.
Whether plaintiff honestly and in good faith performed the contract was an issue of fact made by the pleadings and submitted to the jury. (Shepard v. Mills,
This court has adopted the rule sustained by the weight though not by all of the authorities, that where there has been no willful departure from a building contract in essential points but the contractor has honestly performed the contract in all its substantial and material particulars, he will not be held to have forfeited his right to recover by reason of technical, inadvertent or unimportant omissions. (Peterson v. Pusey,
The instructions given on behalf of plaintiff were in' : harmony with the law laid down in the cases cited, which, "in our judgment, announce a just and proper rule.
The court did not err in overruling defendant’s motion 'to dismiss or abate the suit in this case on account of the pendency of the mechanic’s lien suit. They were concurrent remedies, and a recovery and satisfaction in one.case would operate as a bar to the other. Templeton v. Horne,
It is further contended by defendant that no recovery was authorized because it was not shown plaintiff had a contractor’s license, as required by the ordinances of the city of Chicago. Whether there is any merit in this contention. we think is not here open to review. Defendant filed a written motion in the trial court for a new trial, assigning twenty-two reasons therefor, but in none of them was it stated that a new trial should be granted for the reason that it was not proven the plaintiff had a license. Where a party files a written motion for a new trial he will be held to have waived all causes therefor not set forth in his written motion. Ottawa, Oswego and Fox River Valley Railroad Co. v. McMath,
A careful investigation of this record fails to disclose to us any meritorious ground for reversing the judgment, and it is affirmed.
Judgment affirmed.
