107 F. 204 | U.S. Circuit Court for the District of Washington | 1901
In February, 1897, the government of the United States, through the agency of Capt. W. L. Fisk, of the corps of engineers, United States army, entered into a contract with the plaintiff to prepare the ground and erect buildings for the Gray’s Harbor light station, in this state, under the supervision of the engineer for the Thirteenth light-house district, and according to plans and specifications and detail drawings attached to the contract. The contract included the furnishing of boilers and engines, but other ironwork necessary for the buildings and lantern glass for the light-house tower were to be furnished by other contractors. All the materials and workmanship were required to be inspected by an inspector to be employed by the engineer in charge, who was to be constantly on the ground for the purpose of seeing that all materials met the requirements of the contract, and that the work was properly done. Eight calendar months from the 18th day of February, 1897, were allowed for completion of the contract, and the contractor was subjected to a penalty of $30 per day for each day’s delay exceeding the time limited, and by subsequent agreements the time limit was extended to the 18th day of January, 1898, but the contract was not completed, and the work finally accepted, until March 26, 1898, and the government has retained 82,100 from the contract price as a forfeiture, under the penalty clause, for delay. The plaintiff sues to recover the amount so retained, also to recover from the government for extras, and for losses incurred in doing work and furnishing materials not specified or required by his contract, but which were exacted as the work progressed by the inspector, acting under the authority of the engineer in charge. The plaintiff claims that the delay in completing the contract beyond the time originally specified was caused entirely by capricious and unreasonable exactions and interference with the workmen on the part of the inspector assigned to the work, and delay on the part of other contractors in furnishing the ironwork and lantern glass, and delay on the part of the government officers in inspecting the boilers and other materials, and by bad weather, and that the fault of the government officers and agents and independent contractors has the effect to entirely abrogate the penalty clause of the contract. It is an admitted fact in the case that the iron materials required were not delivered until after the time fixed by the original contract for the completion of the work, and That the lantern glass was not delivered until 20 days after the limit
On the face of the contract, it appears that the contractor engaged to execute the contract during that part of the year when the weather would be most favorable for such work, and the evidence proves conclusively that he made his calculations and arrangements accordingly; he was prompt in providing materials of lumber, stone, bricx, gravel, and cement, and went upon the ground with laborers and teams in the month of April, but an inspector was not sent to the place until about three weeks afterwards, and stakes which had to be set by the engineer for the exact location of the different structures were not set until some days after the inspector arrived. The boilers were ready for inspection and notice given in August, but there was two months’ delay on the part of the officers of the government in performing their duty in that particular. Kiln-dried flooring lumber was delivered on the ground in good season, and it could have been inspected in time to have replaced any part of it which might have been found to be' unsatisfactory, without retarding the work, but, instead of acting fairly, the inspector waited until the floors were laid, and then condemned the material, and the engineer required part of the floors to be taken up and replaced with new lumber. The delay in delivering the ironwork necessarily prevented the completion of the work during the dry season of the year, and the delay in the delivery of the lantern glass prevented the inclosure-of the tower, so that the cementing and painting inside could not be completed until after the expiration of the time for completing the whole work, as fixed by the last extension granted. It is also an undisputed fact that from about the 1st of November the weather was wet and stormy, so that the work from that time was necessarily slow and expensive. It is 'my opinion that these conditions entitle the contractor to claim that the delay was caused by the fault of the government and by the elements, and constitute a legal bar to enforcement of any forfeiture for delay.
The claim for extras is supported by clear and positive testimony, and is -contradicted by the testimony of the inspector, and for the most part the questions at issue are questions of fact, which must be determined by consideration of contradictory evidence. The charge for an extra injector and an extra pump are the only items with relation to which the witnesses agree as to the facts. The contract plainly specifies that one injector and one pump should be supplied. It is admitted that two of each were furnished to satisfy the demands of the inspector and engineer, and it is claimed that two were necessary, because the contract required two boilers, and one clause-.of the.contract.provides that everything necessary to make the structures complete and., ready for use shall be furnished by the contractor, whether specified Or not, and'another clause provides that all
“Q. Did you have a dispute or argument witli Mr. Erickson as to whether the sills for the dwelling were fir or cedar? A. Sills for dwelling? Q. •Whether they were fir or cedar? A. There are no sills for the dwelling. Q. •Well, plates; is that another name for them? A. Well, plates; yes. Q. Did you have an argument with hirfi whether those that he had brought .there and was putting in were fir or cedar? A. Not that I know of. About a difference in the wood, — lümber? Q. Yes. A. No, sir. Q. Whether they were fir or cedar? A. No, sir; except in the quality, — yes. Q. But as to whether they were fir or cedar, that question was never mentioned? A. No. Q. What was it, — cedar? A. It was cedar. Q. Cedar was specified? A. I. think that it is. Q. At any time, in discussing that, did Mr. Erickson 'saw off a piece of it, and ask you to smell it? Á. No; I never saw Mr. Erickson have a saw in his hand. Q. This matter that I have been talking about that you call ‘wall plates’ are called ‘sill plates’ in the specifications? A. ‘Sills,’ X call them. 'Q. You said there were not any sills? A. No; ‘wall plates,’ I mean.”
I will refer to one other matter wbicb goes a long way towards impairing Mr. Leick’s credibility in my estimation. The contract requires a well to supply water for the station to be dug to the depth of IS feet. The evidence shows- that, after excavating for the well had commenced, Mr. Leick interfered, and required its location to be moved a distance of 18 inches, and after the work had further progressed he required another change, putting it back to about the .position where it was started. When the shaft was down 18 feet there was no water, and it had to be carried 3 or 4 feet deeper, and then an abundance of water was obtained. Mr. Leick insisted, however, in having the well- sunk still deeper, and kept the men digging the well deeper, when the water was coming in so rapidly that two men were unáble to keep it bailed out. On the trial, two witnesses swore positively that the depth of the well, after its completion, and after gravel-had been put,in to make the bottom solid, was a little
In all business transactions, the government, as a contractor, should be treated with the same fairness as private individuals, and should also be required to deal fairly on its part. The evidence as a whole shows that, in spite of all obstructions and annoyances, the plaintiff completed the work substantially and well, and that it was accepted as fulfillment of his contract by the government’s officers. To punish him by withholding part of the contract price for his work, as a forfeiture for delay, and by refusing to pay his bill for extras when the delay was entirely caused by the incompetency of the government’s agent and the failure of the other contractors, over whom he had no control, to deliver materials on time, and the bad weather in which he had to work in consequence of such delays, would be rank injustice.
I direct findings to be prepared by the plaintiff’s attorneys, sustaining the allegations of the complaint, and allowing the plaintiff’s claim for the full amount of the contract price for his work and the extras claimed and itemized in the complaint, making only the following deductions shown to be proper by the testimony of Mr. Hull, viz.: