Plaintiff owns a tract of land near Rainy Lake. Some of it abuts upon Jackfish Bay, an arm of Rainy Lake. The outlet of Rainy Lake into
Plaintiff makes these claims:
That his land was overflowed and that the cause of the flowage was the negligent operation of the dam.
That the defendant is an owner or joint owner of the dam and is responsible for its operation.
Defendant denies both claims and alleges:
That the dam was constructed under the authority of the United States and Canada and that the owners thereof were authorized to construct it so as to raise the water to a certain level, which level has not been exceeded, and that by virtue of such authority no private right of damage can bo sustained.
. That plaintiff acquired his land from the United States government after the government authorized the dam, and took it subject to the right conferred by the government to raise the water as above stated.
That plaintiff failed to prove any damage.
The dam was constructed on the American side by the Eainy Eiv.er Improvement Company, a Minnesota corporation, and on the Canadian side by the Ontario and Minnesota Power Company, Limited, a Canadian corporation, and it is operated by these two corporations. Both are doubtless liable for any unlawful or negligent act incident to its operation, or if defendant is responsible for the doings of the Eainy Eiver Company, then it is liable for such unlawful or negligent acts.
Congress granted, first to the Koochiching Company, its successors, or assigns and later to its successor, the Eainy Eiver Improvement Company, the right to construct a dam on this site. 30 St. 398, c. 238; 31 St. 167, c. 346; 32 St. 485, c. 1305; 33 'St. 814, c. 797; 34 St. 386; 35 St. 273, c. 194. On October 1, 1908, defendant acquired, and has since owned, the land at the American end of the dam. On that day it entered into a contract with the Eainy Eiver Improvement Company, by which it gave to that company the right to construct and perpetually maintain the dam abutting upon the land in Minnesota. Work on the dam had already been begun, under what arrangement it does not appear. The construction of the dam proceeded and the dam was completed and lias since been operated, so far as the American portion was concerned, pursuant to 'said contract.
By the terms of this contract defendant approved the plans adopted for the construction of the dam. By its terms defendant agreed to advance the entire cost of the dam in the form of an interest bearing loan secured by a mortgage. The money was advanced and the mortgage given. The mortgaged property is described as the dam and all rights and easements in and upon the land upon which it is located, and all privileges arising out of the instruments mentioned or acquired by virtue of flie acts of Congress. No other property is described, though the mort
Are these facts such as to sustain a finding that defendant is liable for the acts of the Bainy Biver Improvement Company in the operation of the dam ? We are of the opinion that they are. There is no doubt that the two corporations are separate entities. The fact that defendant owns all the stock in the Bainy Biver Improvement Company does not make them the same. State v. Chicago & N. W. Ry. Co.
The decisions in this state upon this subject are not altogether in harmony.
In Potter v. Mellen,
In U. S. Express Co. v. Koerner,
In Harris v. Kerr,
In Palmer v. Degan,
In Knowles v. Steele,
In Nickerson v. Wells-Stone Mercantile Co.
In Warner v. Lockerby,
We think there is nothing in any of these decisions to interfere with our adopting what we conceive to be the proper rule, that is: Where there is no other right involved, a new trial should not be granted to a plaintiff because of an erroneous dismissal of his cause where it is plain that he could recover no more than nominal damages, or where, though the amount of the damage does not appear, there is nothing to make it appear that the damage that he suffered was substantial.
Where, however, plaintiff has made out a prima facie case and the evidence shows that substantial damages have been suffered, but through inadvertence or misjudgment, competent proof of the amount has not been made, a new trial should be granted. This principle is laid down in trenchant language in Thompson-Houston Electric Co. v. Durant Land Improvement Co.
And, where a verdict in plaintiff’s favor would determine some matter of substantial right, a new trial should be granted whether the amount of the damages proven is nominal or substantial. Harvey v. Mason City & Ft. Dodge R. Co.
Order reversed and new trial granted.