Eric M. Enos v. John O. MarshEric M. Enos v. John O. Marsh
Eric Enos appeals a district court order
BACKGROUND
Under section 301 of the River and Harbor Act of 1965 (Title III of P.L. 89-298), Congress authorized construction of a deep draft harbor at Barbers Point on the island of Oahu, Hawaii. Barbers Point is located on the southwest coast of the island in the Ewa district, adjacent to the district of Waianae. The project is to provide a second deep draft harbor for commercial and industrial use on Oahu.
As authorized, the project is the joint responsibility of the United States Army Corps of Engineers (Corps) and the State of Hawaii (state), through its Department of Transportation. The Corps is responsible for the construction of the project’s principal features: an entrance channel 4280 feet long, 450 feet wide, 38-42 feet deep and a 92 acre inner harbor. The State of Hawaii is to provide all lands, easements, rights of way, and a portion of the project costs. In addition, the state plans to fund and construct shoreside terminal and transfer facilities.
In 1975, before the start of construction, the Corps initiated environmental studies pursuant to the National Environmental Policy Act of 1969 (NEPA),
The Corps awarded the construction contract in March, 1982, and construction began in August of that year.
On October 5, 1982, certain residents of Waianae filed a complaint to enjoin construction of the harbor project. Waianae residents sought relief from the Secretary of the Army, the District Engineer for the
On December 29, 1982, the district court imposed a temporary restraining order enjoining all blasting operations. Waianae residents moved for a preliminary injunction which was heard February 3-5, 1983. Following that hearing, the court dissolved the temporary restraining order on February 9. The Ninth Circuit denied Waianaе residents’ emergency motion for a stay of execution of that order. Plaintiffs also moved the district court for a permanent injunction and for partial summary judgment.
On January 5, 1984, in a thorough and well-reasoned order, the district court denied Waianae residents’ motions and granted the federal defendants’ cross-motion for summary judgment on all claims.
Eric Enos, a resident of Waianae, alone appeals the judgment from the district court.
STANDARD OF REVIEW ON SUMMARY JUDGMENT
In reviewing a grant of summary judgment, we view the evidence in the light most favorable to the opposing party and determine whether any genuine issue of material fact remains for trial and whether the substantive law was correctly applied.
DISCUSSION
I. The Endangered Species Act
In mid-1976 a plant species thought to be extinct, the Euphorbia skottsbergii var. kalaeloana (’akoko), was found in the vicinity of the Barbers Point harbor project. At that time, the United States Fish and Wildlife Service (FWS) had proposed that the ’akoko be designated as endangered under the ESA. 41 Fed.Reg. 24523 (June 16, 1976). The ’akoko was officially listed as an endangered species on August 24, 1982. 47 Fed.Reg. 36847 (1982).
A. Standard of Review
This court interprets
de novo
the statutory provisions of the ESA.
United States v. McConney,
B. The FWS and the Corps did not violate the Endangered Species Act,
Enos first argues that the ’akoko plant should have been given the same protections during the period that it was
proposed
to be listed as endangered as when the plant was officially
designated
as endangered.
1
Plaintiff contends specifically
The ESA contains both substantive and procedural provisions.
See Thomas v. Peterson,
In its 1978 amendments to the ESA, Congress prescribed a three-step process to ensure compliance of this substantive provision.
See
Act of Nov. 10, 1978, Pub.L. No. 95-632, 1978 U.S.Code Cong. & Ad. News (92 Stat.) 3751; 3752-53 (codified within
Third, if the assessment determines that an “endangered species or a threatened species” is likely to be adversely affected,
In contrast, the ESA, as amended in 1979, requires that a federal agency “confer” with the FWS on action likely to ad
The two provisions that expressly provide for protection for species proposed for listing require that a federal agency issue a biological assessment,
Legislative history confirms this interpretation of the Endangered Species Act. A report from the House and Senate confеrence committee adopted during the 1978 amendments explains that
Enos observes that in its Environmental Impact Statement, the Corps assured that it would treat the ’akoko as if it were listed as an endangered species. Enos claims that the Corps, therefore, should be estopped from denying it owed the ’akoko the protections under the ESA.
Enos lacks authority for this position. 6 We decline to hold the Corps to the standards of the ESA because it stated that it intended to treat the species as endangered. 7 Such a ruling could deter voluntary efforts which could both work in the best interest of the species and permit agency action to go forward if the species does becomе listed.
C. The Secretary did not violate the Act by failing to designate a critical habitat.
Plaintiff next contends that the Secretary of the Interior abused his discretion by failing to designate a critical habitat for the ’akoko plant subsequent to its listing as an endangered species.
The Secretary’s determination not to designate a critical habitat for the ’akoko concurrent with its listing as an endangered species will be set aside if “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
Under the relevant ESA provision, the Secretary of the Interior is to designate “to the maximum extent prudent” a critical habitat for an endangered species concurrent with its listing.
(i) the specific areas within the geographical area occupied by the species, at the time it is listed ... on which are found those physical or biological features (I) essential to the conservation of the species and (II) which may require special management considerations; and
(ii) specific areas outside the geographical area occupied by the species at the time it is listed ..., upon a determination by the Secretary that such areas are essential for the conservation of the species.
At the time the ’akoko became listed as an endangered species, the Secretary declined to designatе a critical habitat for it. 47 Fed.Reg. 346846, 346848 (Aug. 24, 1982). The Secretary reasoned that since the ’akoko had been found in a non-native habitat, the biological and physical features essential to its existence could not be known. Id. Therefore, its critical habitat could not be determined. Id.
Enos concedes that the statutory phrase “to the maximum extent prudent” gives the Secretary some discretion not to designate a critical habitat. However, based
The legislative history does indicate that the Secretary may only fail to designate a critical habitat under rare circumstances. Id. However, we conclude that the relevant provision does not mandate a determination based on inadequate information, and therefore conclude that the Secretary did not abuse his discretion. 9
Furthermore, since the listing of the ’akoko, approximately 5200 ’akoko plants have been found outsidе the project’s vicinity in a protected area of Barbers Point Naval Air Station. Several hundred more are being nursed and grown in various arboreta. The ’akoko remaining in the harbor project area number approximately 50. Because only 2% of the ’akoko plant population was to be found in the harbor project area when the ’akoko became listed, the Secretary’s failure to designate that site as a critical habitat cannot be said to be arbitrary or capricious.
II. National Environmental Policy Act
Enos challenges the Corps’ preparation of its Environmental Impact Statements under the National Environmental Policy Act on three grounds.
The Corps did not violate NEPA by failing to disсuss the environmental effects of state-planned shoreside facilities. A.
Enos first argues that the Corps violated NEPA by failing to discuss the environmental effects of the state-planned shoreside facilities in its 1976 EIS and 1977 Supplement. The shoreside facilities include berthing areas, terminals, roadways, and utility improvements.
An EIS is required for “major Federal actions significantly affecting the quality of the human environment.”
Citing
La Raza Unida of Southern Alameda County v. Volpe,
Two other important factors convince us that the action by the state cannot be
B. The Corps adequately discussed the secondary effects of the project in its EIS.
Enos argues that the Corps did not adequately detail the secondary or socio-economic effects of the Barbers Point harbor projeсt. He contends that the Corps merely acknowledged the possible secondary effects, such as increased urbanization, but did not sufficiently analyze or document their impact to the extent necessary under NEPA to inform decision-makers or the public. Defendants acknowledge that they are obligated to discuss secondary impacts which significantly affect the environment,
see Coalition for Canyon Preservation v. Bowers,
The district court reviewed the Corps’ discussion in the EIS, and concluded that the “highly speculative nature of the potential effects and ability of state and local authorities to limit ... such effects ... render the EIS ‘minimally acceptable.’ ”
Thе adequacy of an agency’s preparation of an EIS is reviewed under the Administrative Procedure Act (APA),
The cases relied upon by Mr. Enos do not support his position. In
City of Davis v. Coleman,
In contrast, the Corps repeatedly alerted decision-makers and the public to the potential secondary effects of the harbor project. Discussion was not extended; however, such consequences are speculative, and dependent upon local development and zoning policies.
Accord Concerned Citizens on I 190 v. Secretary of Transportation,
C. The Corps did not violate NEPA by failing to file another EIS Supplement.
Enos contends that the Corps was required to supplement its 1976 EIS and 1977 Supplement in light of nеw information.
A federal agency has a continuing duty to gather and evaluate new information relevant to the environmental impact of its actions even after release of an EIS.
Stop H-3 Association v. Dole,
1. Increase in harbor size. Enos contends that the change in harbor size from 246 to 360 acres requirеs an EIS supplement. Plaintiff concedes this change was noted in the 1977 Supplement. Enos does not explain how the environmental effects of the increased acreage differ from those assessed. As discussed, the Corps has adequately outlined the secondary environmental effects of the harbor.
2. •
Archeological discoveries.
Plaintiff indicates that certain archeological deposits, not identified in the EIS, should be incorporated into an EIS Supplement. Plaintiff acknowledges there is disagreement among the experts over the deposits’ scientific value, but contends that the Corps has a duty to incorporate conflicting viewpoints in its EIS.
See California v. Block,
Defendants’ duty to incorporate conflicting viewpoints only аrises if the information is significant enough to require discussion in an EIS. In connection with the National Preservation Act, the Corps
3. Revised population statistics. Enos notes that the Oahu population projections used by the Corps in determining the feasibility of the harbor have been revised downward 11.7% by the year 2000 (from 1,039,000 to 917,400 persons) and asserts that failing to account for this population change arbitrarily inflates shipping demand for the harbor. Population projections are necessarily speculative; the significance of this new information uncertain. Moreover, the significance goes to the need for the harbor, not to its potential environmental effects. The Corps’ decision not to supplement was a reasonable one.
4. Proposed development plans. The Waianae District proposed a development plan calling for the maintenance of agricultural and rural land use patterns. The decision not to supplement an EIS based on a land development proposal is not unreasonable.
5. Impact on Lifestyles. Plaintiff contends that the EIS fails to mention the project’s effect upon the lifestyles of those living on the rural Waianae coast. As stated in the Corps’ 1976 EIS, “[gjrowth can be viewed as adverse or beneficial.” The urbanization plaintiff views as adverse has been adequately addressed by the Corps.
6. Designation of the ’akoko plant as an endangered species. The plant’s existence in' the harbor area and proposed endangered status were indicated in the 1976 EIS. Upon official designation as an endangered species, the Corps initiated consultation with the Fish and Wildlife Service and has complied with the requirements of the Endangered Species Act {see discussion supra Part I). In view of the Corps’ compliance with that act and the fact that only 2% of the known ’akoko population еxists in the harbor vicinity, the Corps’ decision not to supplement its EIS is reasonable.
III. Water Resources Development Act
Plaintiff also claims that the Corps invalidly applied a 3V4 percent discount rate in its cost-benefit computations for the Barbers Point harbor project.
The Water Resources Development Act of 1974 (WRDA),
Under the WRDA and regulations promulgated thereunder, the Corps is required to use a current discount rate determined by a formula and published by the Water Resources Council.
Enos contends that the Corps did not receive the required “satisfactory assurances” from state authorities, and therefore may not base future cost-bеnefit calculations upon the 374% rate.
12
Although un
Violations, based upon invalid use of the WRDA discount rate formula under NEPA and the WRDA are distinct. From the record of the pleadings below, it is clear that Enos challenges the use of the 3V4 рercent discount rate in the EIS for the first time on appeal.
13
We decline to entertain this challenge at this stage in the proceedings.
14
Taylor v. Sentry Life Ins. Co.,
A principal purpose of the WRDA is to provide Congress and the Corps with accurate data by which to evaluate water resource projects such as the Barbers Point Harbor.
See Environmental Defense Fund v. Marsh (EDF),
In order for this court to review past agency action and order the requested relief, a plaintiff must first establish standing under the APA,
CONCLUSION
Enos appeals the district court order on claims brought under the Endangered Species Act, the Environmental Policy Act, and the Water Resources Development Act. None of his claims is meritorious. The district court’s denial of preliminary injunction to plaintiff and grant of summary judgment to defendants on all claims are therefore affirmed.
AFFIRMED.
Notes
.
See
. The FWS acts pursuant to the authority of the Secretary of the Interior, the named party in this action.
See Romero-Barcelo v. Brown,
. On December 10, 1979 the FWS withdrew its proposal to list the 'akoko because certain statutory time requirements imposed by 1978 amendments to the ESA had not been met. 45 Fed.Reg. 58166 (1980). On September 2, 1980, the FWS again proposed to list the ’akoko as an endangered species. 45 Fed.Reg. 58167. During the period the 'akoko was neither listed nor proposed to be listed, we agree with the District of Columbia Court of Appeals that the 'akoko did not come within the protections of the ESA.
Wilson v. Block,
. By not limiting federal agencies from making resource commitments, Congress has chosen to allow federal agencies to go forward with projects which may affect species proposed for listing. Therefore, it would make little sense to require formal consultation and the issuance of a biological opinion requiring alternative agency action as plaintiff suggests. In explaining subsection 1536(a)(4), a House Conference Report obsеrves that federal agencies which do commit resources and foreclose alternative action do so with the risk that the species will eventually be listed and the prohibitions of the ESA will apply. H.Conf.Rep. No. 96-697, 96th Cong., 1st Sess. 13, reprinted in 1979 U.S.Code Cong. & Ad.News 2557, 2572, 2577.
. We are not unaware of the difficulties in using subsequent legislative interpretations of prior statutes,
see Consumer Product Safety Commission v. GTE Sylvania,
.
Sierra Club v. Sigler,
. Although transplant efforts of the Corps proved highly unsuccessful, the district court did not find that defendants had acted in bad faith or in an attempt to evade the requirements of the Act. Enos does not contest this finding.
. Subsequently, Congress amended this provision.
See
. This provision has been subsequently amended to take account of the possibility that sufficient information may not be available to make a critical habitat determination. The section now provides that the designation be made to the maximum extent prudent and
determinable.
. Nor has there been an attempt, as in La Raza Unida and Sierra Club v. Volpe, to circumvent the prescriptions of NEPA. As a matter of fact, the state has filed an EIS outlining the environmental impact of its planned shoreside facilities.
. The EIS did not have to treat the shoreside facilities as part of the federal action. The environmental effeсts of the state action were not ignored, for the state project was taken into account as one of the secondary effects of the federal action.
Enos also urges most strongly that because the Corps includes the economic benefits of a harbor with shoreside facilities in operation in its cost-benefit analysis in the EIS, it must also include the costs of those facilities, otherwise the analysis will be arbitrarily skewed.
See Sierra Club v. Sigler,
. Plaintiff contends that the Corps should be required to use the 1983 discount rate of 77/s percent, which would provide a more accurate
. Throughout the pleadings and memoranda, plaintiffs challenge the discount rate as a violation of the WRDA, not the NEPA. In its lengthy and thorough order, the district court only addressed the propriety of the use of the discount rate under the WRDA, and not under NEPA.
. We do note that in its 1976 EIS, the Corps also included a cost-benefit ratio based upon the discount rate of 6/s percent, thereby fulfilling the substantive purpose of NEPA to inform decision-makers and the public of the realistic consequences of agency action.
See Johnston v. Davis,
. The WRDA was enacted in 1974, P.L. 93-251. While there is no reported legislative history of the Act, it appears as if the relevant provision,