83 Ga. App. 464 | Ga. Ct. App. | 1951
Code § 103-101 provides: “The contract of suretyship is one whereby a person obligates himself to pay the debt of another in consideration of credit or indulgence, or other benefit given to his principal, the principal remaining bound therefor. It differs from a guaranty in this, that the consideration of the latter is a benefit flowing to the guarantor.” This is but one of the distinctions between suretyship and
“Ordinarily, a guarantor can not be sued to judgment on a contract of guaranty in the absence of a prior, judgment against the principal and a nulla bona return, unless it is alleged and proved that the principal debtor is insolvent or that he can not be made to respond to a judgment that may be obtained against him by the plaintiff.” Arkansas Fuel Oil Co. v. Young, 66 Ga. App. 33 (16 S. E. 2d, 909).
Measured by the foregoing rules, it is clear that the contract sued upon is one of guaranty, and not one of suretyship, and we reach this conclusion without any relaxation of the rules for the construction of contracts. The defendant was not directly and primarily liable for the payment of the account due the plaintiff by the principal debtor, North Augusta Appliance & Plumbing Company. The goods or materials furnished on the account were not furnished upon the strength of, or the faith in, the defendant’s guaranty. The goods or materials had been sold and delivered and the account was due before the defendant executed and delivered his contract of guaranty to the plaintiff. The promises of the defendant and the principal debtor were not one and the same. The principal debtor promised payment of the account if the goods or materials were sold to it on credit. The guarantor promised that the account would be paid if the plaintiff would extend the time for payment. The consideration for the account was the delivery of the goods or materials to the principal debtor; the consideration for the guaranty was the extension of the time for payment of the account. The defendant was an officer and stockholder of the principal debtor corporation, and it is not unreasonable to assume that the extension of credit to the corporation was a benefit inuring to him personally. Etheridge v. Rawleigh Co., supra, at page 703.
The provision in the contract waiving “notice of the nonpayment of the said account by the said September 1, 1949, and of failure of the collection of the same,” implies nothing more than an understanding and agreement on the defendant’s part that the plaintiff was not required to enforce promptly the payment on September 1, 1949, of any demand it might have against the
After determining that the contract is one of guaranty and not of suretyship, nothing remains but to apply the rules of law applicable to contracts of that class, and it is a well-established principle applicable to actions on contracts of guaranty that, “before an action can be maintained against a guarantor, . . it must be shown that the principal is unable to perform.” Musgrove v. Luther Publishing Co., supra; Manry v. Waxelbaum, supra. The defendant's demurrer properly pointed out the petition’s- deficiency in failing to allege the principal debtor’s inability to respond to any judgment which the plaintiff might obtain against it, and thé trial court erred in overruling the demurrer.
Judgment reversed.