FINDINGS OF FACT & CONCLUSIONS OF LAW
■ On February 10, 2014, this Court commenced a non-jury trial in the above-entitled matter. During the course of- the thirteen-day proceeding, the Court received evidence and heard sworn testimony.
I. BACKGROUND
On December 13, 2010, Plaintiffs Environment Texas Citizen Lobby, Inc. (“Environment Texas”) and Sierra Club (“Sierra Club”) (collectively, “Plaintiffs”) brought suit under the citizen suit provision of the federal Clean Air Act (the “CAA”), 42 U.S.C. § 7604, against Defendants Exxon-Mobil Corporation, ExxonMobil Chemical Company, and ExxonMobil Refining and Supply Company (collectively, “Exxon”). The case concerns Exxon’s operation of a refinery, olefins plant, and chemical plant located in Baytown, Texas (the “Complex”), which is a suburb of Houston and within Harris County. Plaintiffs seek a declaratory judgment, penalties,
II. FINDINGS OF FACT
The following facts have been established by a preponderance of the evidence:
A. Exxon and the Complex
1. ExxonMobil Chemical Company and ExxonMobil Refining and Supply Compa
2.Exxon owns and operates the Complex, which consists of a refinery, olefins plant, and chemical plant.
3. The Complex is located in Baytown, Texas, which is a suburb of Houston. The nearby area in which the Complex operates is populated with numerous other refineries, petrochemical plants, and industrial facilities.
B. Title v. Permits
4. The Complex is governed, in part, by operating permits issued by. the Texas Commission on Environmental Quality (the “TCEQ”) pursuant to Title V of the CAA.
5.Exxon documents noncompliance and indications of noncompliance with its Title V permits in three ways.
D. Investigation, Enforcement, and Corrective Actions
6. The TCEQ investigates each reportable emissions event.
7. In addition to the TCEQ’s investigation, for each of the Reportable Events, Exxon conducted an extensive internal investigation, evaluated the root cause of the event, and implemented corrective actions to try to prevent recurrence.
8. After investigating, the TCEQ assessed $1,146,132 in penalties against Exxon for some of the Events and Deviations.
9. Moreover, after investigating, the TCEQ elected not to pursue enforcement on 97 Reportable Events because the TCEQ determined the- applicable affirmative defense criteria were met.
10. The distinction the TCEQ makes between reportable emissions events and recordable emissions events demonstrates the agency’s belief that emissions from recordable emissions events are less serious and less potentially harmful to human health than emissions from reportable emissions events.
11. Of the 901 Deviations, 45% involved no emissions whatsoever.
E. Agreed Enforcement Order
12. On February 22, 2012, Exxon and the TCEQ agreed on an enforcement order regarding the Complex (the “Agreed Order”).
a.Plant Automation Venture. Install computer applications to improve real-time monitoring, identification, diagnostics and online guidance/management of .operations. The project is intended to provide early identification of potential events and/or instrumentation abnormalities, allowing proactive response.
b. Fuels North Flare System Monitoring/Minimization- Additional instrumentation, including monitoring probes and on-line analyzers are intended to improve the identification and characterization of flaring events. The development of flare minimization practices ... are intended to reduce loads on the flare system.
c. BOP/BOPX Recovery Unit Simulators. Develop, implement and use high-fidelity process training simulators ... intended to improve operator training and competency, resulting in reduced frequency and severity of emissions events.
d. Enhanced Fugitive Emissions Monitoring. ... The program will use infrared imaging technology to locate potential VOC and HRVOC leaks....60
The Agreed Order states these projects “will reduce emissions at the Baytown Complex, including emissions from emissions events ....”
F. Efforts to Improve Environmental Performance and Compliance
13.■ The Complex has a governing philosophy that all employees work toward plant reliability and environmental compliance.
14. The Complex employs a wide variety of emissions-reduction equipment such as wet gas scrubbers, selective catalytic reduction, amine treating towers, flares, flare gas recovery systems, external floating roof tanks, sulfur recovery units, a regenerative thermal oxidizer, and more than one hundred low nitrogen oxide (“NOx”) burners; the Complex also employs emissions-detection equipment such as continuous emissions monitoring systems and forward-looking infrared cameras.
15. Both the TCEQ and the EPA recognize it is not possible to operate any facility — especially one as complex as the Complex — in a manner that eliminates all
G. Improvement
16.In the Agreed Order, the TCEQ recognized the Complex’s historical reductions in emissions when making the following finding of fact:
The annual emissions inventory reports that ExxonMobil has submitted for the Baytown Complex under 30 Tex. Admin. Code § 101.10 reflect a positive trend of reductions in actual emissions, including unauthorized emissions associated with emissions events and scheduled MSS activities, from Baytown Complex. From 2000 to 2010, ExxonMobil has reported a 60 percent reduction in aggregate emissions of VOC, HRVOC, CO, S02 and NOx from the Baytown Complex. Over that same time period, reported emissions of VOC from the Baytown Complex have dropped by 44 percent, reported emissions of CO have dropped by 76, and reported emissions of NOx have dropped by 63 percent.78
Likewise, evidence in this case shows the total amount of emissions at the Complex generally declined year-to-year over the years at issue in the case.
17. In addition, each year at issue, total emissions were far below the annual emissions limits.
H. Plaintiffs and Plaintiffs ’ Members
18. Environment Texas is a non-profit corporation with a purpose “to engage in activities, including public education, re
19. First, Diane Aguirre Dominguez is a member of Environment Texas and Sierra Club.
20. Second, Marilyn Kingman is a member of Sierra Club.
21. Third, Richard Shae Cottar is a member of Sierra Club.
22.Fourth, Sharon Sprayberry is a member of Sierra Club.
I. Baytown Residents Called by Exxon
23. Exxon called three residents of the Baytown community to testify. First was Fred Aguilar, who has lived approximately eight blocks from the Complex for 35 years.
24. Second was Billy Barnett, who has lived across the street from the Complex for 17 years and in close proximity to the Complex for a total of 37 years.
25. Third, Gordon Miles has lived very close to the Complex for 28 years.
III. CONCLUSIONS OF LAW
A. Standing
1. An organization “has standing to bring suit on behalf of its members when: (1) its members would otherwise have standing to sue in their own right; (2) the interests it seeks to protect are germane to the organization’s purpose; and (3) neither the claim asserted nor the relief requested requires the participation of individual members.” Texans United for a Safe Econ. Educ. Fund v. Crown Cent. Petroleum Corp.,
2. In order for a member to have standing to sue in his or her own right, (1) he or she must have suffered an actual or threatened injury, (2) that is fairly traceable to the' defendant’s action, and (3) the injury must likely be redressed if the plaintiff prevails in the lawsuit. Id. The plaintiff has the burden to prove these requirements by the preponderance of the evidence. Lujan v. Defenders of Wildlife,
a. Injury-in-Fact
3. To satisfy the injury-in-fact requirement, the plaintiff'must prove injury to himself or herself, not injury to the environment. Friends of the Earth, Inc. v. Laidlaw Envtl. Sens. (TOC), Inc.,
4. In this case, four members of either Environment Texas or Sierra Club
b. Traceability
5. So long as there is a fairly traceable connection between a plaintiffs injury and the defendant’s violation, the traceability requirement of standing is satisfied. Comer v. Murphy Oil USA,
6. Even though Plaintiffs’ members’ injuries do not have to be linked to exact dates that the Events and Deviations occurred, Plaintiffs’ members correlated some of the experiences described supra, such as odor and noise, to five Events or Deviations.
c. Redressability
7. A plaintiff must prove re-dressability “for each form of relief sought.” Laidlaw,
8. Because the injury-in-fact, traceability, and redressability requirements are satisfied, Plaintiffs’ members have standing to sue in their own right, and Plaintiffs have standing.
B. Actionability
9. It is undisputed Exxon violated some emission standards or limitations under the CAA.
(1) “to have violated”: repeated violation of the same emission standard or limitation before the complaint was filed; or
(2) “to be in violation”:
(a) violation of the same emission standard or limitation both before and after the complaint was filed; or
(b) continuing likelihood of recurrence:
(i) likelihood of recurring violations of the same parameter; or
(ii) likelihood that the same inadequately corrected source of trouble will cause recurring violations of one or more different parameters.
See 42 U.S.C. § 7604(a)(1); Carr,
10. Here, Plaintiffs claim Exxon either (1) repeatedly violated the same emission standards or limitations in its Title V permits before the complaint was filed, or (2)(a) violated the same emission standards or limitations in its Title V permits both before and after the complaint was filed. Plaintiffs do not claim satisfaction of the third method of proving actionability: method (2)(b) continuing likelihood of recurrence.
12. As evidentiary support for the ac-tionability of the alleged violations in each count of their complaint, Plaintiffs cite to the stipulated spreadsheets of Events and Deviations;
a. Count I
13. Count I alleges Exxon violated the provision of the Complex’s Title V permit that prohibits emissions from upset events. Exxon disputes that these events constitute violations of an emissions standard or limitation. As to specific standards or limitations violated, Plaintiffs’ contentions have been inconsistent. In
14. The evidentiary support cited to by Plaintiffs for Count I is Plaintiffs’ Exhibits 1A and IB (stipulated spreadsheets), 587 and 588 (Plaintiffs’ corresponding spreadsheets), and 9 (tallied table). Violation of the aforementioned conditions is not corroborated by these spreadsheets. These spreadsheets reference permit 18287, but the spreadsheets do not appear to reference any specific conditions of permit 18287 or any other permit, such as general conditions 8 or 15, or special conditions 38 and 39.
15. Plaintiffs do not contend every upset event is actionable because the condition that does not authorize upset emissions was repeatedly violated. Therefore, the Court need not address whether the sole fact that there are allegedly multiple upset ■ events makes those upset events actionable under the CAA or whether the condition referencing upset emissions constitutes a standard or limitation under the CAA. Rather, Plaintiffs base the actiona-bility of upset events under Count I on alleged repetition of violations of conditions or limitations that apply to separate air contaminants.
17. For all of these reasons, Plaintiffs have not met their burden to prove either repeated violation pre-complaint or violation both before and after the complaint of the same emission standard or limitation under Count I.
b. Count II
18. Count II alleges Exxon violated hourly emission limits. Count II is similar to Count I, except Count II is divided by different permits. The Court will consider each permit in turn.
i. Refinery Flexible Permit 18287
19. Under Count II/Refínery Flexible Permit 18287, Plaintiffs allege “violations of general conditions 8 and 15, special condition 1, and MAERT limits in permit 18287/PSD-TX-730M4 for emissions of’ various air contaminants.
20.Also as in Count I, Plaintiffs claim “each regulated air contaminant ... is counted separately for purposes of repeated violations,” and their tallied table is divided by air contaminant.
21. For these reasons, Plaintiffs have not met their burden to prove either repeated violation pre-complaint or violation both before and after the complaint of the same emission standard or limitation under Count II/Refinery Flexible Permit 18287.
ii. Olefins Plant Flexible Permit 3452
22. Under Count 11/Olefins Plant Flexible Permit 3452, Plaintiffs allege “violations of general conditions 8, special condition 1, and MAERT limits in permit '3452/ PSD-TX-302M2 for emissions of’ various air contaminants.
23. Also as in the previous counts, Plaintiffs claim “each regulated air contaminant ... is counted separately for purposes of repeated violations,” and their tallied table is divided by air contaminant.
24. For these reasons, Plaintiffs have not met their burden to prove either repeated violation pre-complaint or violation both before and after the complaint of the same emission standard or limitation under Count 11/Olefins Plant Flexible Permit 3452.
iii. Chemical Plant Permits: 4600 (Flare Stack 23), 5259 (Furnaces), 20211 (Flare Stack 12, Butyl Units, Aromatics Units), 36476 (Flare 28, Syngas Fugitives), and No Permit Authorization
25. Under Count II/Chemical Plant Permits, Plaintiffs allege violations of different chemical plant permits for various emissions sources, as well as violations with no permit authorization. The evidentiary support cited to is Plaintiffs’ Exhibits 2E and 2F (stipulated spreadsheets), 593 and 594 (Plaintiffs’ corresponding spreadsheets), and 10 (tallied tables). As in the previous counts, Plaintiffs claim “each regulated air contaminant ... is counted separately for purposes of repeated violations,” and their tallied table is
c. Count III
26. Under Count III, Plaintiffs allege violations of the rule that limits plant-wide emissions of highly reactive volatile organic compounds to no more than 1,200 pounds per hour (the “HRVOC
d. Count TV
27. Under Count IV, Plaintiffs allege violations of the rule that prohibits^ visible emission from flares except for periods not to exceed five minutes in two consecutive hours (the “Smoking Flares Rule”).
e. Count V
28. Under Count V, Plaintiffs allege violations of the rule that requires flares to operate with a pilot flame present at all times (the “Pilot Flame Rule”).
f. Count VI
29. Under Count VI, Plaintiffs allege fugitive emissions are actionable. Specifically, Plaintiffs contend violations of permits 18287, 3452, 20211, 28441, 36476, and 9571; general conditions 8 and 14/15; special condition 1; and MAERT limits for emissions of various air contaminants
g. Count VII
30. Under Count VII, Plaintiffs allege Exxon’s Deviations are actionable.
C. Declaratory Judgment
31. Plaintiffs request a “declaratory judgment that Exxon violated its Title V permits and thus the CAA.”
D. Penalties
32. Having found only a few — but not the vast majority — of the Events and Devi
33. “In determining the amount of any penalty to be assessed under” the CAA in a citizen suit, the Court “shall take into consideration (in addition to such other factors as justice may require)” the following penalty assessment factors:
the size of the business,
the economic impact- of the penalty on the business,
the violator’s full compliance history and good faith efforts to comply,
the duration of the violation as established by any credible evidence...,
payment by the violator of penalties previously assessed for the same violation,
the economic benefit of noncompliance,
and
the seriousness of the violation.
42 U.S.C. § 7413(e)(1).
34. The Court is not required to assess a penalty for violations. 42 U.S.C. § 7413(e)(2) (“A penalty may be assessed for each day of violation.” (emphasis added)); Luminant Generation Co. v. EPA,
a. Size of the Business and Economic Impact of the Penalty on the Business
35. Plaintiffs contend the large size and profitability of Exxon weigh towards imposing a penalty. Specifically, Plaintiffs contend Exxon will only be impacted by a large penalty and has the ability to pay the alleged maximum penalty. Exxon does not dispute these contentions, and the Court agrees given the facts found supra in paragraph II.1. Accordingly, both the size and economic impact factors weigh towards assessing a penalty.
b. Violator’s Full Compliance History and Good Faith Efforts to Comply
36.’ Quantitatively, the number of Events and Deviations at issue in this case
37. Moreover, the number of Events and Deviations does not alone mean Exxon did not make a good faith effort to comply. Despite good practices, it is not possible to operate any facility — especially one as complex as the Complex — in a manner that eliminates all Events and Deviations.
c. Duration of the Violation
38. Plaintiffs claim the duration of the violations warrants the total maximum penalty because — in total — the number of hours and days of violation are high. In so claiming, Plaintiffs made no effort to differentiate- the duration of each of the different Events and Deviations. The total maximum penalty requested by Plaintiffs is the sum of the maximum penalty for each day of violation.
d. Payment by the Violator of Penalties Previously Assessed for the Same Violation
39. Exxon has paid $1,423,632 in monetary penalties for the Events and Deviations at issue in this case to either the TCEQ or Harris County.
e. Economic Beneñt of Noncompliance
40. Generally, economic benefit of noncompliance is the financial benefit obtained by “delaying capital expenditures and maintenance costs on pollution-control equipment.” CITGO Petroleum Corp.,
41. Plaintiffs claim Exxon’s economic benefit of noncompliance is $657 million as of June 2014. This number is based on Bowers’s opinion that the Events and Deviations would not have occurred if (1) if Exxon would have spent $90 million more annually on maintenance and (2) if Exxon would have installed certain capital equipment (an additional sulfur unit costing $100 million, an additional sour gas flare costing $10 million, and two additional compressor stations costing $50 million each). Plaintiffs offered the testimony of an economist, Jonathan Schefftz, who used Bowers’s inputs as to maintenance and capital expenditure costs delayed to calculate present-day economic benefit using the weighted-average cost of capital. The Court finds Schefftz’s method of calculating economic benefit to be reliable. However, Schefftz made it very clear that he had no opinion as to the reliability of the inputs given to him by Bowers. For reasons explained infra, the Court finds Bowers’s inputs to be neither reliable, credible, nor persuasive. Therefore, Schefftz’s economic benefit of noncompliance figure is equally unreliable.
42. Bowers is a retired refinery and chemical plant engineer. Bowers’s opinions and the bases for his opinions were vague and undetailed. Of the $90 million Bowers opined should have been spent on maintenance, Bowers opined half of the $90 million needed to be spent to hire 900 new employees to “run[] around inspect
43.After carefully considering all of the evidence, the Court determines the most reasonable estimate of Exxon’s economic benefit of noncompliance is $0. Because Exxon received no economic benefit from not complying, this factor weighs against assessing a penalty.
f. Seriousness
44. The CAA does not define “seriousness” in relation to the penalty assessment factors. See 42 U.S.C. § 7413(e)(1). Some circuit courts, not including the Fifth Circuit, have held that “a court may still impose a penalty if it finds there is a risk or potential risk of environmental harm” even if there is “a lack of evidence on the record linking [a defendant’s] CAA violations to discrete damage to either the environment or the public.” Pound v. Airosol Co.,
45. Plaintiffs have made no effort to differentiate the degree of seriousness for the different Events and Deviations. Rather, Plaintiffs ask the Court to assess the maximum penalty allowed by law for each Event and Deviation, regardless of degree of seriousness. Such an approach is inappropriate in this case because each of the Events and Deviations differ tremendously. For example, some of the Recordable Events emitted as little as 0.02 pounds of emissions, while some of the Recordable Events emitted over 500 pounds of emissions.
46. Generally, reportable emissions events are more serious and more potentially harmful to human health than recordable emissions events.
47. Plaintiffs claim the Events and Deviations were serious because they adversely affected public health. To support this claim, Plaintiffs submitted evidence of the potential health effects caused by the types of pollutants emitted during the Events and Deviations. For example, hydrogen sulfide, which smells like rotten eggs or feces, can cause sore throat, cough, fatigue, headaches, nausea, and poor memory at low concentrations.
48. Plaintiffs also claim the Events and Deviations were serious because they created “nuisance-type impacts” to the community that interfered with daily life.
49." As to Deviations not involving emissions, those Deviations typically relate to late reports or incomplete reports.
50. For all of the aforementioned reasons, overall the greater weight of the credible evidence does not support a finding that the Events or Deviations were serious. Accordingly, the seriousness factor weighs against assessing a penalty.
g. Balancing the Factors
51. The maximum penalty for each day of violation is $32,500 for violations occurring before January 13, 2014, and $37,500 for violations occurring on January 13, 2009, and thereafter. 42 U.S.C. § 7413(e)(2); 40 C.F.R. § 19.4. Plaintiffs contend the total maximum penalty, after deducting for overlapping violations, is $642,697,500. Plaintiffs ask the Court to assess Exxon this maximum penalty amount, less the $1,423,632 Exxon has already been penalized for some of the Events and Deviations. Exxon contends it should not be assessed a penalty.
52. After carefully considering all of the penalty assessment factors discussed supra, the Court finds no amount of penalty is appropriate in this case even if all the Events and Deviations are actionable.
E. Injunctive Relief
53. “The party seeking a permanent injunction must meet a four-part test. It must establish (1) success on the merits; (2) that a failure to grant the injunction will result in irreparable injury; (3) that said injury outweighs any damage that the injunction will cause the opposing party; and (4) that the injunction will not disserve the public interest.” VRC LLC v. City of Dallas,
54. Plaintiffs request Exxon be enjoined for five years from violating the emission standards and limitations found by this Court to be actionable. The CAA provides that district courts have jurisdiction to enforce emission standards or limitations. 42 U.S.C. § 7604(a). However, “[t]he grant of jurisdiction to ensure compliance with a statute hardly suggests an absolute duty to do so under any and all
55. Enjoining Exxon from violating CAA standards and limitations would do nothing more than require Exxon to obey the law in the future. The Court finds that such an injunction is unnecessary and that Plaintiffs have not established injury to the public outweighs damage to Exxon. Exxon — without an injunction ordering it to comply with the CAA — already faces threat of TCEQ enforcement actions, including penalties, and threat of citizen suits should it not comply with the CAA. The Court believes any additional benefit the public would gain from Exxon having the additional threat of judicial contempt and punishment for violation of a court order is minimal. Additionally, for reasons explained supra in paragraphs III.47-48, the greater weight of the credible evidence does not support a finding that the Events or Deviations were harmful to the public or the environment, and there is no evidence that any potential future emissions events or deviations will be more harmful to the public or the environment than past Events and Deviations allegedly were. To the contrary, the number of Reportable Events, the total amount of emissions, and the amount of unauthorized emissions of-criteria pollutants have all decreased over the years at issue.
F. Special Master
56. Plaintiffs request the Court appoint a special master to monitor compliance with the injunctive relief granted in this Order. Plaintiffs request the special master be paid for by Exxon; have full access to the Complex, its personnel, and records;
57. Moreover, even if the Court had granted the requested injunctive relief, a special master would still not be warranted. Plaintiffs did not show by the preponderance of the credible evidence that a special master could do a better job at reducing emissions events and deviations than the Complex’s existing workforce. In addition, a special master would be excessively intrusive to Exxon’s operations. Accordingly, Plaintiffs’ request that the Court appoint a special master is denied.
G. Affirmative Defenses
58. Exxon contends the proclamations of the Texas governor, the related TCEQ directive, and a statutory “act of God” defense provide a legal bar to citizen suit liability for the Events and Deviations that occurred during Exxon’s Hurricane Ike preparation and response efforts. In addition, Exxon contends the affirmative defense provided under title 30, section 101.222 of the Texas Administrative Code is a defense to the assessment of penalties for some of the Reportable Events. Having found no penalties or other relief is warranted, the Court declines to address Exxon’s affirmative defenses.
IV. CONCLUSION
Based on the foregoing, the Court hereby
ORDERS that all of Plaintiffs Environment Texas Citizen Lobby, Inc. and Sierra Club’s requests in this case, including their request for a declaratory judgment, penalties, injunctive relief, and appointment of a special master, are DENIED. Judgment for Defendants ExxonMobil Corporation, ExxonMobil Chemical Company, and Exx-, onMobil Refining and Supply Company is GRANTED.
The Court will issue a separate Final Judgment.
APPENDIX
As explained in paragraphs III.25-27 of this Order, below is the list of actionable violations under Counts II, III, and IV, with selected information from the stipulated spreadsheets. (All violations under Count V, which are listed, in Plaintiffs’ Exhibit 5, are actionable. None of the alleged violations under Counts I, VI, or VII are actionable.)
“PX” refers to Plaintiffs’ Exhibit
Notes
. The parties submitted 1,148 exhibits that span thousands of pages, and 25 witnesses testified.
. The post-trial submissions considered by the Court' include the plaintiffs’ and the defendants’ original proposed findings of fact and conclusions of law, which are 455 pages and 361 pages in length, respectively.
.Plaintiffs originally requested $1,023,845,000 in penalties, but they later reduced their request to $642,697,500 to account for overlapping violations alleged in the various counts of the complaint.
. Defendant ExxonMobil Corporation, Exxon-Mobil Chemical Company, and ExxonMobil Refining and Supply Company’s Original Answer, ¶¶ 12-13.
. Trial Transcript at 5-61:6-9.
. Trial Transcript at 5-60:5-21.
. Trial Transcript at 5-61:11-13.
. Defendant ExxonMobil Corporation, Exxon-Mobil Chemical Company, and ExxonMobil Refining and Supply Company’s Original Answer, ¶¶ 11-13.
. Trial Transcript at 3-74:21-25, 4-171:21 to •4-172:6, 4-173:3-5.
. Plaintiffs’ Exhibit 556 at 25.
. Trial Transcript at 3-71:14 to 3-72:6-9, 8-50:20-22.
. Trial Transcript at 3-77:5 to 3-80:1.
. Trial Transcript at 3-56:2-18, 3-60:16-18.
. Trial Transcript at 3-24:19-21, 3-25:4-5, 3-250:5-11, 7-238:23 to 7-239:10, 372:20 to 3-73:24.
. Trial Transcript at 3-75:15-18.
. Trial Transcript at 11-33:19 to 11-39:16.
. Trial Transcript at 2-207:18 to 2-208:9, 2-212:1-3; see 30 Tex. Admin. Code § 122.142(b).
. Trial Transcript at 1-245:9-17, 2-208:13 to 2-209:13.
. Trial Transcript at 3-81:9 to 3-82:1.
. Trial Transcript at 2-205:13 to 2-206:14, 2-216:3-20.
. 30 Tex. Admin. Code §§ 101.1(88), 101.201; Trial Transcript at 2-232:13-20, 2-236:3-24, 12-164:11-23.
. 30 Tex. Admin. Code §§ 101.1(71), 101.201(b); Trial Transcript at 2-232:21 to 2-233:16, 12-164:11-23. The terms "non-reportable emissions event” and "recordable emissions event” are interchangeable.
. 30 Tex Admin. Code §§ 122.10(6), 122.145(2); Trial Transcript at 2-217:4 to 2-218:19.
. Trial Transcript at 1-246:3-15.
. Plaintiffs’ Exhibits 1A-7E.
. Defendants' Exhibit 546 at 8, ¶ 24; Trial Transcript at 2-241:14-21, 2244:10-18, 4-5:21-23, 8-85:11-16.
. 30 Tex. Admin. Code § 101.222; Defendants' Exhibit 546 at 3-4, ¶ 10, 4-5, ¶ 12; Trial Transcript at 2-242:19-25, 12-160:2 to 12-162:8; see Trial Transcript at 12-161:10 to 12-162:8.
. Defendants’ Exhibit 546 at 5-7, ¶¶ 13-18.
. Trial Transcript at 3-114:25 to 3-117:4, 4-26:4-16.
. Trial Transcript at 3-117:5-22, 10-39:24 to 10-40:8, 10-219:11 to 10-220:13.
. Trial Transcript at 10-231:15 to 10-232:14.
. Defendants' Exhibit 546 at 6, ¶¶ 16-17.
. Defendants' Exhibit 546 at 6, ¶ 17; Trial Transcript at 10-232:15 to 10-233:10, 10-234:25 to 10-277:15, 11-5:17 to 11-21:18.
. Plaintiffs’ Exhibit 337.
. Defendants’ Exhibit 502 at 1-10.
. Exxon claims it has paid $2,022,288 in penalties, while Plaintiffs claim Exxon has paid $1,423,632 in penalties. After thoroughly reviewing all of the evidence submitted to support each amount, the Court finds Plaintiffs' claim ($1,423,632) to be better supported by the evidence.
. E.g., Defendants’ Exhibits 472 at 3-4, 475 at 2, 486 at 2, 488 at 2.
. Defendants’ Exhibits 18-20; Trial Transcript at 3-202:14 to 3-206:3.
. 30 Tex Admin. Code § 101.222.
. Defendants’ Exhibits 24-29; Trial Transcript at 3-200:9 to 3-202:13.
. Defendants’ Exhibits 26, 26E.
. Defendants’ Exhibit 26E.
. Defendants’ Exhibit 26E.
. Defendants’Exhibits 26, 261.
. Defendants’ Exhibit 261.
. Defendants’Exhibit 261.
. Defendants’ Exhibit 261.
. Trial Transcript at 12-164:11-23.
. Defendants’ Exhibit 1007A at 1; see Plaintiffs'Exhibits IB, 2B, 2D, 2F.
. Defendants’ Exhibit 1007A at 2; see Plaintiffs’Exhibits IB, 2B, 2D, 2F.
. Plaintiffs' Exhibit IB at row 800; Trial Transcript at 10-216:17 to 10-218:6, 12234:3-12.
. Plaintiffs' Exhibit 2D at row 2432.
. Trial Transcript at 3-118:9-13, 10-204:11-13, 10-208:1-8.
. Trial Transcript at 10-208:9 to 10-209:17; see Plaintiffs' Exhibits 7A-E.
. Plaintiffs’ Exhibit 7C at row 36, 142; Trial Transcript at 10-207:1-7.
. Trial Transcript at 10-209:18 to 10-210:1.
. Trial Transcript at 10-203:11 to 10-204:10, 10-210:7-12.
. Defendants’ Exhibit 222.
. Defendants’ Exhibit 222 at ¶¶1.13, III.3, III.4, III. 10, III.12; Trial Transcript at 3-'32:25 to 3^10:5, 12-205:15 to 12-207:8.
. Defendants’ Exhibit 222 at ¶ III. 12.
. Defendants’ Exhibit 222 at ¶ III.12.
. Defendants’ Exhibit 222 at ¶ III.10.
. Defendants’ Exhibit 222 at ¶ III.12; Trial Transcript at 3-190:6-24, 12-177:12 to 12-178:6.
. Trial Transcript at 3-32:25 to 3-40:5.
. Defendants' Exhibit 222 at ¶¶ III. 12, 13.
. Defendants’ Exhibit 222 at ¶ III. 14.
. Trial Transcript at 3-82:2 to 3:83:20, 3-273:20 to 3-274:20.
. Trial Transcript at 2-195:1-2, 2-203:8-12, 3-89:22 to 3-90:9, 12-214:19 to 12215:5, 12-226:4-13.
. Trial Transcript at 12-239:22 to 12-240:6.
. Defendants’ Exhibit 413.
. Trial Transcript at 10-47:5 to 10-78:19.
. Trial Transcript at 10-56:13-16.
. Trial Transcript at 10-61:5-17.
. Trial Transcript at 12-231:16 to 12-232:1.
. Trial Transcript at 7-225:3-14, 11-274:25 to 11-275:7, 12-15:4 to 12-16:9, 1220:15-20, 12-25:14-25, 12-26:16-23.
. Defendants'Exhibit 190 al 7-8, 14-15; Defendants' Exhibit 546 at 11, ¶¶ 32-34; Trial Transcript at 3-112:2-8.
. Defendants’ Exhibit 190 at 7-8, 14-15; Defendants' Exhibit 546 at 11, ¶¶ 32-34; Trial Transcript at 3-112:2-8.
. Defendants’ Exhibit 22 at ¶ 1.12.
. Defendants' Exhibits 1004, 1008.
. Defendants’ Exhibit 1002. Under the CAA, the EPA establishes minimum air quality levels in the form of "national ambient air quality standards” for six pollutants (known as “criteria pollutants”) to protect public health. 42 U.S.C. § 7409. The six criteria pollutants are sulfur dioxide, particulate matter, carbon monoxide, ozone, oxides of nitrogen/nitrogen dioxide, and lead. 40 C.F.R. §§ 50.4-17.
. Defendants’ Exhibit 1000 at 1.
. Defendants’ Exhibit 547 at 12:11-12.
. Defendants’ Exhibits 1004, 1008. Emissions from “event emissions” are at issue in this case, not “permitted emissions.”
. Defendants’ Exhibit 1004 at 1.
. Defendants’ Exhibits 1004, 1008.
. Defendants’ Exhibit 1004 at 1.
. Plaintiffs’ Exhibit 338 at 1Í 11(2); Trial Transcript at 1-227:16-25.
. Trial Transcript at 1-234:24 to 1-235:4.
. Trial Transcript at 2-125:11-22.
. Trial Transcript at 2-125:23 to 2-126:4.
. Trial Transcript at 1-192:2-22.
. Trial Transcript at 1-193:8 to 1-194:16.
. Trial Transcript at 1-194:17-20.
. Trial Transcript at 1-196:6 to 1-199:9.
. Trial Transcript at 1-199:8-9.
. Trial Transcript at 1-199:10-25.
. Trial Transcript at 1-200:1 to 1-201:15, 1-205:6-25, 1-219:1-14.
. Trial Transcript at 1-205:19 to 1-206:11.
. Trial Transcript at 1-207:25 to 1-209:23, 1-220:1 to 1-222:4.
. Trial Transcript at 1-202:2 to 1-203:8, 1-218:6-17.
. Trial Transcript at 1-203:9 to 1-204:9.
. Trial Transcript at 1-218:3-24.
. Trial Transcript at 1-204:10 to 1-205:5.
. Trial Transcript at 6-69:11-14.
. Trial Transcript at 6-71:3 to 6-75:6.
. Trial Transcript at 6-75:2 to 6-76:15.
. Trial Transcript at 6-76:16-23, 6-83:6-12.
. Trial Transcript at 6-76:24 to 6-77:24.
. Trial Transcript at 6-78:13 to 6-80:5.
. Trial Transcript at 6-95:14-20.
. Trial Transcript at 6-91:23 to 6-95:9. On February 13, 2014, Kingman smelled an odor she attributed as emanating from the Complex, and a Recordable Event occurred that day; however, February 13, 2014, is outside the time frame of this case.
. Trial Transcript at 1-98:18 to 1-99:13.
. Trial Transcript at 1-102:7 to 1-103:6.
. Trial Transcript at 1-102:3-4, 1 — 106:5— 11.
. Trial Transcript at 1-108:5-24, 1-109:12-20, 1-118:13-24, 1-121:7 to 1123:18, 1-128:2-3.
. Trial Transcript at 1-109:21 to 1-112:3, 1-131:5 to 1-132:4, 1-176:6-9.
. Trial Transcript at 1-119:5-18.
. Trial Transcript at 1-111:10-20.
. Trial Transcript at 1-148:3 to 1-149:19, 1-187:12 to 1-188:1.
. Trial Transcript at 1-144:21 to 1-145:17.
. Trial Transcript at 1-152:11-21.
. Trial Transcript at 1-153:9-20.
. Trial Transcript at 1-153:9-13, 1 — 169:3— 18.
. Trial Transcript at 1-123:19 to 1-131:1, 1-168:17 to 1-181:12.
. Trial Transcript at 6-5:19-23.
. Trial Transcript at 6-11:23 to 6-13:13, 6-37:2-5, 6-40:3-10.
. Trial Transcript at 6-15:18 to 6-16:19, 6-33:12 to 6-36:13.
. Trial Transcript at 6-36:16 to 6-37:1.
. Trial Transcript at 6-15:7-17.
. Trial Transcript at 6-37:9-24.
. Trial Transcript at 6-38:2-19.
. Trial Transcript at 6-38:20-22.'
. Trial Transcript at 6-50:12-20.
. Trial Transcript at 6-17:7 to 6-23:8, 6-45:20 to 6-49:16, 6-65:20 to 6-67:24.
. Trial Transcript at 10-130:11 to 10-131:9.
. Trial Transcript at 10-140:8-24, 10-142:1-6, 10-155:4-12.
. Trial Transcript at 10-142:7-18.
. Trial Transcript at 11-101:8 to 11-102:3, 11-104:10-19.
. Trial Transcript at 11-114:13-18.
. Trial Transcript at 11-113:7-11, 11-114:19 to 11-115:1, 11-115:10-14.
. Trial Transcript at 11-115:5-9.
. Defendants’ Exhibit 545; Trial Transcript at 12-82:11 to 12-86:5.
. Trial Transcript at 12-89:22 to 12-90:14, 12-96:13-22.
. Supra ¶¶ II.19-22.
. Supra ¶¶ II.19-22.
. Supra ¶¶ II.19-22 (Dominguez-0, King-man-0, Cottar-3, and Sprayberry-2).
.Supra ¶¶ II.19-22.
. Supra ¶¶ II.19, 21-22.
. Supra ¶ II.21.
. Supra ¶¶ II.19, 21-22.
. For example, hydrogen sulfide can smell badly and cause headaches, and one of Plaintiffs’ members smelled strong, pungent odors that, on occasion, caused him headaches. Plaintiffs’ Exhibit 476 at 38-39; Plaintiffs’ Exhibit 540 at 1, 4, 10; Trial Transcript at 7-89:25 to 7-91:9, 9-161:24 to 9-162:8; supra ¶ 11.21.
. To the extent the redressability requirement in a CAA case is only satisfied as to penalties for ongoing violations, not wholly past violations, the Court notes Exxon has some ongoing violations. See infra ¶¶ III.9-30 (finding that because Exxon violated some of the same emission standards or limitations both before and after the complaint was filed, those violations are considered ongoing under the CAA and are thus actionable in a citizen suit).
.Specifically, Exxon does not dispute that the alleged violations under Counts II, III, IV, and V of Plaintiffs’ complaint constitute violations of an emission standard or limitation. However, Exxon does dispute that the alleged violations under Counts I, VI, and VII constitute violations of an emission standard or limitation.
. Carr is a Clean Water Act ("CWA”) case. The "to be in violation” provision in the CAA is identical to the "to be in violation” provision in the CWA. Compare 42 U.S.C. § 7604(a)(CAA), with 33 U.S.C. § 1365(a)(l)(CWA). Interpretations of the CWA provision are instructive when analyzing the CAA provision. See United States v. Anthony Dell’Aquilla, Enters. & Subsidiaries,
. Because Plaintiffs do not claim a continuing likelihood of recurrence for purposes of actionability, the Court declines to address in detail this method of proving actionability. However, the Court does find that the preponderance of the credible evidence does not support such a finding. The number of Events and Deviations does not alone prove a likelihood of recurring violations. See supra ¶ II.7; infra ¶¶ III.36-37, 42. The testimony of Keith Bowers, particularly his opinion that
Exxon contends that to be actionable, the law requires the violations to have involved the same equipment, the same emissions point, and the same root cause. Such considerations may be applicable to one way to prove actionability: method (2)(b) continuing likelihood of recurrence, particularly method (2)(b)(ii) likelihood that the same inadequately corrected source of trouble will cause recurring violations of one or more different parameters. However, such considerations are not required to prove actionability the other two ways: method (1) repeated violation of the same emission standard or limitation pre-complaint, or method (2)(a) violation of the same emission standard or limitation both before and after the complaint. For additional background on why violations are not required to have involved the same equipment, the same emissions point, and the same root cause to be actionable, see ExxonMobil Corp., ECF No. 126 at 11-13.
. Supra ¶ 11.4.
. Plaintiffs’ Exhibits 1A-7E; see supra ¶ II.5. These stipulated spreadsheets span hundreds of pages and contain thousands of rows of alleged violations. The Court has reviewed the details of all these spreadsheets.
. Plaintiffs’ Exhibits 587-603. Exxon contends Plaintiffs’ method of calculating the number of days of violation is legally incorrect. Reference in this Order to Plaintiffs’ calculation of the number of days of violation does not indicate the Court agrees on the accuracy of Plaintiffs’ calculations.
. Plaintiffs’ Exhibits 9-15.
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 117 (capitalization omitted).
. Plaintiffs' Revised Proposed Findings of Fact and Conclusions of Law at 58 (capitalization omitted).
. Plaintiffs' Exhibit 9 at 1 (capitalization omitted).
. Although unclear, Plaintiffs appear to be ' combining a condition incorporated into a flexible permit that does not authorize upset emissions with conditions incorporated into the same flexible permit that limit separate air contaminants. Plaintiffs have not met their burden to prove how any such combination is actionable.
. See Plaintiffs’ Exhibits 1A-1B, 587-88.
. See Plaintiffs’ Exhibit 9.
. Plaintiffs’Exhibit 9.
. Under Count I, when computing days of violations, Plaintiffs considered every hourly emission limit to be zero because they claim
. Plaintiffs’ Exhibits 1A-1B, 587-88 (capitalization omitted).
. Plaintiffs’ Exhibit 9 at 2.
. See Plaintiffs’ Exhibits 1A-1B, 587-88.
. Compare Plaintiffs' Exhibits 1A at row 133, and 587 at row 133; with 1A at row 158, and 587 at row 158; with 1A at row 544, and 587 at row 544. Plaintiffs counted each of these events as at least one day of violation.
As another example, Plaintiffs claim hydrogen sulfide limits were violated 1,068 days pre-complaint and 313 days post-complaint and thus such violations are actionable. Plaintiffs’ Exhibit 9 at 2. However, the hydrogen sulfide limit for the Recordable Event starting on October 23, 2005, was 15.78 pounds per hour; but the hydrogen sulfide limit for the Recordable Event starting on November 3, 2006, was 0 pounds per hour. Compare Plaintiffs’ Exhibits IB at row 69, and 588 at row'69; with IB at row 154, and 588 at row 154. Plaintiffs counted each of these events as at least one day of violation.
.Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 124 (capitalization omitted); see also Plaintiffs' Exhibit 10 at 2.
. Plaintiffs’Exhibits 2A-2B, 589-90.
. Plaintiffs' Exhibit 10 at 2-3.
. Plaintiffs’ Exhibit 10 at 2.
. See Plaintiffs' Exhibits 2A-2B, 589-90.
. Compare Plaintiffs’ Exhibits 2A at row 405, and 589 at row 405; with 2A at row 697, and 589 at row 697. Plaintiffs counted each of these events as at least one day of violation.
As another example, Plaintiffs claim carbon monoxide limits were violated 677 days pre-complaint and 256 days post-complaint and thus such violations are actionable. Plaintiffs’ Exhibit 10 at 2. However, the carbon monoxide limit for the Recordable Event starting on June 9, 2011, was 3,736.48 pounds per hour; but the carbon monoxide limit for the Recordable Event starting on June 29, 2011, was 0 pounds per hour. Compare Plaintiffs’ Exhibits 2B at row 8712, and 590 at row 8714; with 2B at row 8817, and 590 at row 8819. Plaintiffs counted each of these events as at least one day of violation.
. The fact that the permit is a flexible permit does not change the Court’s analysis because Plaintiffs must prove repeated violation of a specific condition or limitation of a Title V permit, not repeated violation of a Title V permit.
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 127 (capitalization omitted); see also Plaintiffs’ Exhibit 10 at 3.
. Plaintiffs’Exhibits 2C-2D, 591-92.
. Plaintiffs' Exhibit 10 at 2-3.
. Plaintiffs’ Exhibit 10 at 2.
. See Plaintiffs’ Exhibits 2C-2D, 591-92.
. Compare Plaintiffs' Exhibits 2C at row 51, and 591 at row 51; with 2C at row 81, and 591 at row 81. Plaintiffs counted each of these events as at least one day of violation.
As another example, Plaintiffs claim carbon monoxide limits were violated 538 days pre-complaint and 260 days post-complaint and thus such violations are actionable. Plaintiffs’ Exhibit 10 at 2. However, the carbon monoxide limit for the Recordable Event starting on October 31, 2005, was 6627.58 pounds per hour; but the carbon monoxide limit for the Recordable Event starting on January 6, 2006, was 0 pounds per hour. Compare Plaintiffs’ Exhibits 2D at row 13, and 592 at row 13; with 2D at row 22, and 592 at row 22. Plaintiffs counted each of these events as at least one day of violation.
.The fact that the permit is a flexible permit does not change the Court’s analysis because Plaintiffs must prove repeated violation of a specific condition or limitation of a Title V permit, not repeated violation of a Title V permit.
. Plaintiffs’ Exhibit 10 at 2-6.
. Plaintiffs’ Exhibit 10 at 4.
. Compare Plaintiffs' Exhibits 2E at row ■181, and 593 at row 181; with 2E at row 189, and 593 at row 189; with 2E at row 194, and 593 at row 194. Plaintiffs counted each, of these events as at least one day of violation.
. Compare Plaintiffs’ Exhibits 2E at row 181, and 593 at row 181; with 2E at row 189, and 593 at row 189; with 2E at row 194, and 593 at row 194.
. For example, under chemical plant permit 36476 (flare stack 28), Plaintiffs claim hydrogen cyanide limits were violated 3 days and thus such violations are actionable. Plaintiffs’ Exhibit 10 at 5. However, the hydrogen cyanide limit for the Recordable Event starting on December 23, 2009, was 3.31 pounds per hour; but the hydrogen cyanide limit for the Recordable Event starting on September 1, 2012, was 0.10 pounds per hour, even though the spreadsheets corroborate that both events involved permit 36476 and flare stack 28. Compare Plaintiffs’ Exhibits 2E at row 159, and 593 at row 159; with 2E at row 205, and 593 at row 205. Plaintiffs counted each of these’ events as at least one day of violation.
.The actionable violations are listed in the appendix to this Order.
. Plaintiffs' Proposed Findings of Fact and Conclusions of Law at 100.
. Plaintiffs’ Exhibit 11. Only violations at the olefins and chemical plant are listed; no violations at the refinery are listed.
. Plaintiffs’ Exhibits 3 at row 5, 595 at row 5.
. E.g., Plaintiffs’ Exhibits 3 at row 4, 595 at row 4.
. The actionable violations are listed in the appendix to this Order.
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 101.
. Plaintiffs’ Exhibit 12.
. Plaintiffs’ Exhibits 4 at row 21, 596 at row 21.
. E.g., Plaintiffs’ Exhibits 4 at row 6, 596 at row 6. An opacity limit of 0% cannot be assumed because varying opacity limits are listed on the spreadsheets.
. The actionable violations are listed in the appendix to this Order.
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 101.
. Plaintiffs ’ Exhibit 13.
. Plaintiffs’ Exhibits 5 at row 17, 597 at row 17.
. All the violations listed in Plaintiffs’ Exhibit 5 are actionable.
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 102; Plaintiffs’ Revised Proposed Findings of Fact and Conclusions of Law at 58-59; Plaintiffs’ Exhibit 14 at 1.
. Plaintiffs’ Exhibits 6 (capitalization omitted), 598 (capitalization omitted).
. See Plaintiffs’ Exhibits 6, 598.
. Plaintiffs’ Exhibit 598.
. The Court notes that Plaintiffs recognize violations under Count VI overlap with violations under other counts.
. The evidentiary support cited to is Plaintiffs’ Exhibits 7A-7E (stipulated spreadsheets), 599-603 (Plaintiffs' corresponding spreadsheets), and 15 (tallied tables).
. See also Trial Transcript at 10-203:3-13, 10-209:7-14 (discussing how deviations are indications of noncompliance with a permit condition).
. Plaintiffs’ Proposed Findings of Fact and Conclusions of Law at 405; Plaintiffs’ Revised Proposed Findings of Fact and Conclusions of Law at 58.
. Supra ¶¶ III.9-12.
. Supra ¶¶ III. 13-30.
. Because the penalty provisions in the CAA are similar to the penalty provisions in the CWA, "CWA cases are instructive in analyzing [penalty] issues arising under the CAA.” Pound v. Airosol Co.,
. See supra ¶ II.5.
. Supra ¶ II.2.
. See Trial Transcript at 10-220:14 to 10-223:16.
. Trial Transcript at 10-221:24 to 10-222:10.
. Supra ¶ 11.15. The Court understands impossibility is not a defense to penalties, except as it might apply to the applicable affirmative defense criteria. The Court does not consider the fact that it is not possible to operate the Complex in a manner that eliminates all Events and Deviations as a reason to not impose penalties. Rather, the Court notes this fact only to explain that the number of Events and Deviations does not alone mean Exxon did not make a good faith effort to comply.
. Supra ¶ 11.16.
. Supra ¶ II.7.
. In particular, the Court finds Bowers’s testimony regarding the Events and Deviations having "common causes” is neither credible nor persuasive. For example, the Events and Deviations that Bowers categorizes as having the same common cause of "power supply failures” include the following: moisture got into the connections of improperly installed lightening arresters, causing them to short out; a squirrel bypassed animal traps, causing some electrical equipment to short circuit; and a hawk dropped a snake on top of Substation One, causing an
. Supra ¶¶ II.7-9.
. Supra ¶ II.7.
. Supra H 11.14.
. Trial Transcript at 12-16:10-20.
. Defendants’ Exhibit 546 at 14 — 15, ¶¶ 40-44.
. In addition to the aforementioned issues, Plaintiffs contend Exxon's policy of always asserting the affirmative defense to penalties to the TCEQ is, in itself, bad faith. Based on the greater weight of the credible evidence, the Court disagrees such policy is in bad faith. Although Exxon initially asserts the affirmative defense when reporting an event to the TCEQ, the TCEQ, after investigation, determines whether the affirmative defense actually does apply.
. See 42 U.S.C.' § 7413(e)(2); 40 C.F.R. § 19.4; Plaintiffs' Revised Proposed Findings of Fact and Conclusions of Law at 68-69.
. See Plaintiffs' Exhibits 1A-7E.
. Supra ¶ II. 10.
. Supra ¶ II. 10.
.Supra ¶ II.8.
. Trial Transcript at 4-181:15 to 4-182:15.
. Trial Transcript at 4-182:4 — 7.
. Trial Transcript at 4-267:6-23.
. Trial Transcript at 10-56:17 to 10-57:25, 11-56:22 to 11-58:19, 12-26:24 to 12-34:8.
. Supra ¶¶ II.12-14.
. Supra ¶¶ II.12-14.
. The Fifth Circuit has not opined on this issue.
. Supra ¶ II.10.
. Supra ¶ II.10.
. See supra ¶ II.5.
. Supra ¶ II.5.
. See supra ¶ II. 10 ("58% [of Recordable Events] had total emissions of 20 pounds or less, 80% had total emissions of 100 pounds or less, 87% had total emissions of 200 pounds or less, and 93% had total emissions of 500 pounds or less.”).
One of Plaintiffs' experts, Ranajit Sahu, opined the actual quantities of emissions from Exxon’s flares are often greater than the quantity Exxon reports to the TCEQ. The Court was not persuaded by this opinion and finds it is against the preponderance of the credible evidence.
. Supra ¶ II. 10.
. Supra ¶ II.10.
. Supra HII.il.
. SwpraHII.il.
. Plaintiffs’ Exhibit 476 at 38-39; Plaintiffs’ Exhibit 540 at 1, 4, 10; Trial Transcript at 7-89:25 to 7-91:9, 9-161:24 to 9-162:8.
. See e.g., Plaintiffs’ Exhibit 539 at 25, 27-29; Plaintiffs' Exhibit 476 at 50-51; Trial Transcript at 7-90:11-16, 7-91:10 to 7-92:9.
. Plaintiffs’ claim Exxon’s own air dispersion modeling and stationary air monitor data showed that, in some instances, the predicted off-site concentrations of pollutants exceeded safety thresholds, such as Effects Screening
. Plaintiffs’ Revised Proposed Findings of Facts and Conclusions of Law at 68, ¶ 78.
. Supra ¶¶ 11.19-22.
. Supra ¶ II.3; see supra ¶¶1.19, 21-22 (finding Plaintiffs' members understood some emissions and flaring is authorized by permit).
. Supra ¶ 11.17.
. Supra ¶¶ 11.19-22 (Dominguez-O, King-man-0, Cottar-3, and Sprayberry-2). The Court notes this lack of a correlation, except for five Events or Deviations, only to help explain why Plaintiffs' proposition that the Events or Deviations were serious because they created nuisance-type impacts on the surrounding community, or adversely affected public health, is largely unsubstantiated. In doing so, the Court does not hold such link is required for a finding that the Events and Deviations were serious under a penalty analysis.
In addition to Plaintiffs’ members' testimonies, Plaintiffs claim in their post-trial submission that “[m]any times, Exxon personnel have noted on the complaint log that the date and time of a citizen complaint corresponds to the date and time of an emission event occurring at the Complex.” Plaintiffs' Proposed Findings of Fact of Fact and Conclusions of Law, ¶ 969. The only support Plaintiffs cited to in their post-trial submission for this proposition are complaints logged on the complaint log on 2/18/2008; however, Plaintiffs did not cite evidence that an Event or Deviation occurred on that day. Id. ¶¶ 969-70. Plaintiffs did not specifically reference any other correlations besides the one on 2/18/2008. See id. Therefore, Plaintiffs have not adequately shown any of the complaints on the complaint log correlated to any Events or Deviations in this case. Accordingly, the Court does not find the complaint log persuasive evidence that any of the Events or Deviations were serious.
.See supra ¶¶ 11.23-25.
. Supra ¶¶ 11.23-25.
. Although the impacts to Plaintiffs' members are traceable enough to the Complex to confer standing under standing law, this traceability is too tenuous to support a finding that the specific Events and Deviations caused impacts to Plaintiffs’ members under a penalty analysis.
. Supra ¶ 11.11.
. Trial Transcript at 4-161:10-25.
. Neither of the parties contend justice requires consideration of any other factors, and the Court finds none either.
. As explained supra in ¶ III.39, $1,423,632 ' will be deducted from any, penalty otherwise warranted. As explained supra in HIII.38, the duration of the violation factor weighs neither towards nor against assessing a penalty-
. The CAA does not prescribe a specific method for determining appropriate penalties. Some courts use the top-down approach, in which the court starts at the maximum penalty allowed by law and reduces downward as appropriate considering the factors as mitigating factors. CITGO Petroleum Corp.,
As to the top-down approach, Plaintiffs contend the maximum penalty is $642,697,500. Exxon contends Plaintiffs’ calculation of the maximum penalty is incorrect because they incorrectly counted the number of days of violation pursuant to the law. In this particular case, the Court does not need to decide whether Plaintiffs’ calculation of the total maximum penalty is legally correct because, even assuming it is correct and starting at $642,697,500 under the top-down approach, the Court finds $642,697,500 should be mitigated downward to $0 based on the factors. As to the bottom-up approach, the economic benefit of noncompliance is $0 for reasons explained supra in ¶¶ III.40-43. Starting at $0, the Court finds $0 should not be adjusted upward based on the factors. Therefore, whether taking a top-down approach, bottom-up approach, or simply relying upon the factors to arrive at an appropriate amount, the Court’s penalty finding is the same.
. Supra ¶ 11.16.
. See supra ¶¶ II. 12-14.
