Lead Opinion
Opinion of the Court filed by Circuit Judge SENTELLE. Concurring Opinion filed by Circuit Judge TATEL.
Electricity utility companies Entergy Services, Inc., Southern Company Services, Inc., and Nevada Power Company, Inc., petition for review of various orders of the Federal Energy Regulatory Commission in which the Commission held that certain costs incurred by customers connecting generators to petitioners’ networks must be “spread” across all customers and not “directly assigned” to the respective generator companies. Specifically, the Commission found that because the connection facilities in each case were located “at or beyond” the point of connection to the network, they constituted “network upgrades” not directly assignable to individual generators.
Petitioners contend (1) that the Commission’s orders should be reversed because they are unsupported by substantial evidence, and (2) that the Commission’s orders should be reversed because the “At or Beyond” rule constitutes an arbitrary de
I. Background
A. Regulatory Background
Petitioners in this case — Entergy Services, Inc. (“Entergy”), Southern Company Services, Inc. (“Southern”), and Nevada Power Co. (“Nevada Power”) — are electricity utility companies that own transmission systems providing electricity to large geographic regions. In order to foster a more competitive, efficient market for electricity, federal regulation requires that such “transmission providers” open their networks to transmission customers — other sellers of electricity seeking to supply power to their own customers. See Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996), 61 Fed. Reg. 21,540 (“Order No. 888”), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274 (1997), on reh’g, Order No. 888-B,
In implementation of Order No. 888, the Commission promulgated a pro forma Open Access Transmission Tariff (“OATT”) that sets forth the minimum terms and conditions under which transmission providers may offer their services to would-be customers. See Order No. 888-A at 30,503-43 (including the final OATT); 18 C.F.R. § 35.28(c)(1) (requiring public utilities owning, controlling, or operating facilities transmitting electricity in interstate commerce to “have on file with the Commission a tariff of general applicability for transmission services” or a tariff approved by the Commission consistent with Order No. 888).
Under this tariff regime, some costs incurred by an interconnecting customer are borne by the respective customer, while other costs are spread across all customers on the network. In general, when a Generator of electricity connects to a Transmission Provider’s network consistent with Order No. 888, the Transmission Provider cannot require the Generator to bear costs incurred for the development of equipment that benefits all users of the network. Duke Energy Co.,
The specific tariff and other interconnection details are finalized in an Interconnection Agreement (“LA”) between the Transmission Provider and the Generator. IAs are drafted by the parties and are submitted to the Commission for approval.
The consolidated cases before this court arise from the Commission’s disapproval of four IAs submitted for its approval.
Entergy submitted an unexecuted IA to the Commission on November 14, 2001. Amelia Energy Center, LP (“Amelia”) was the other party to the agreement. At issue were two connection facilities: (1) a new Switching Station section to accommodate two new 230 kV radial power lines from the Generators; and (2) the re-routing of three existing power lines. The Commission held that the IA could not directly assign costs for the facilities at issue to Amelia, because the facilities were located “at or beyond” the point of interconnection with the grid, and as such provided benefit to all users. See Entergy Gulf States, Inc.,
Southern submitted two IAs for Commission approval. It submitted its first IA, between its Alabama Power transmission system and Blount County Energy, LLC (“Blount”), on November 30, 2001. At issue was a replacement breaker at the Miller Steam Plant substation. The Commission held that the cost of the breaker could not be directly assigned to the Generator, in light of the “At or Beyond” rule. Southern Company Services, Inc., Letter Order, Docket No. ER02-430-000 (Jan. 25, 2002), reh’g denied,
Southern submitted its second IA, between its Georgia Power transmission system and Athens Development, LLC (“Athens”), on June 5, 2002. At issue were three 115 kV breakers at two Georgia Power substations. The Commission held that the cost of the breakers could not be directly assigned to Athens, in light of the “At or Beyond” rule. Southern Company Services, Inc., Letter Order, Docket No. ER02-2015-000 (July 30, 2002), reh’g denied,
Nevada Power submitted an unexecuted IA to the Commission on May 29, 2002. GenWest, LLC (“GenWest”) was the other party to the agreement. At issue was a “one line terminal” to be added to Nevada Power’s Harry Allen 500 kV Switchyard. The Commission held that the cost of the one line terminal could not be directly assigned to GenWest, in light of the “At or Beyond” rule. Nevada Power Co.,
Following these administrative proceedings, Entergy, Southern, and Nevada Power filed these petitions for review.
II. Analysis
A. Jurisdiction
Three of the four IAs at issue in these consolidated cases have been can-
A challenge to a specific Commission order regarding an interconnection agreement is moot when the contract is terminated. Northwest Pipeline Corp. v. FERC,
Petitioners treat the justiciability analysis as a question of mootness. Under the mootness analysis, Petitioners argue that a challenge to agency action is not moot “where there is a reasonable chance of the dispute arising again between the government and the same [petitioner].” Legal Assistance for Vietnamese Asylum Seekers v. Dep’t of State,
These Petitioners cannot take refuge under the broader doctrine of “capable of repetition yet evading review.” See, e.g., Weinstein v. Bradford,
Southern and Entergy claim that they are nonetheless before the court with a justiciable controversy because they are asserting facial challenges to the ongoing policy as well as seeking review of their underlying contracts. This argument also fails to keep them in court. While it is true that a petitioner with a mooted individual controversy may at times have standing to challenge an ongoing policy, such a petitioner must demonstrate standing to obtain each type of relief sought. See City of Houston v. HUD,
To meet “the irreducible constitutional minimum for standing,” petitioners must show, inter alia, that they suffer an actual injury in fact which is caused by the Commission’s policy. Lujan v. Defenders of Wildlife,
Entergy and Southern lack standing to proceed before this Court. This Court therefore lacks jurisdiction over the Enter-gy and Southern petitions.
B. Limitation of Issues
The elimination of the Entergy and Southern cases limits the matters remaining for this Court’s consideration. This Court’s power to review FERC peti
We construe § 825i narrowly. In Kelley ex rel. Mich. Dep’t of Nat’l Resources v. FERC, we held that objections not explicitly presented in proceedings below, but arguably “implicit” in other objections, were not properly preserved: “Suffice to say that an argument ‘implicit’ in prior requests before the Commission’s staff does not satisfy the strict standard of § 313(b) [of the Federal Power Act, codified at 16 U.S.C. § 825Z].”
While § 825£ offers petitioners an exception — i.e., a “reasonable ground for failure” to urge the objection below — Nevada Power offers no such reasonable ground for its failure to raise several objections in its petition for FERC rehearing. Therefore, any objections raised by Petitioners’ consolidated briefs but not raised by Nevada Power in its administrative proceedings are not properly before this Court.
The only issues raised by Nevada Power in its petition for rehearing and preserved in Petitioners’ consolidated briefs are whether: (1) the Commission’s determination that the facilities at issue benefit the entire network was not supported by substantial evidence, and (2) the Commission’s “At or Beyond” rule represents an unjustified departure from past precedent. Request for Rehearing at 6-12, Nevada Power Co., Docket No. ER02-1913-001 (Aug. 16, 2002). A different version of these arguments advanced by Entergy or Southern that was not advanced by Nevada Power — e.g., that the Commission ignored evidence that the facilities in question actually decrease network stability — -is not properly before this Court in our consideration of Nevada Power’s case. Such an argument was not even implicit — let alone explicit — in Nevada Power’s objections before the Commission. Indeed, the evidence allegedly ignored by the Commission — a sworn affidavit — was introduced in Southern’s proceedings, not Nevada Power’s.
C. Substantial Evidence
Nevada Power argues that the Commission’s finding that facilities located “at or beyond” the point of interconnection to the network benefit the entire network was not supported by substantial evidence. See 5 U.S.C. § 706(2)(E) (2004) (“The reviewing court shall ... hold unlawful and set aside agency action, findings, and conclusions found to be ... unsupported by substantial evidence .... ”). It argues that GenWest was the sole beneficiary of the facilities at issue, and that geographic location of the additions to the Harry Allen Switchyard is not itself sufficient justification for a finding to the contrary.
But Nevada Power’s view of “benefit” is too narrow. Like the petitioners in another recent challenge to the Commission’s policy, this Petitioner suffers from a “cramped view of what constitutes a ‘benefit.’ ” Entergy Services, Inc. v. FERC,
The justifications that this Court accepted for the Commission’s application of the pre-existing cost allocation policy to those specific facilities also warrant this Court’s approval of the policies’ application to the facilities here. As we noted, “[o]ur conclusion that the Commission has adequately set forth its rationale rests ... on its explanation in the Consumers Energy decisions that the Commission relied upon in the order to review.” Id. at 543.
The Consumers Energy explanation was the Commission’s justification of “a standard policy that requires credits for customer-funded network upgrades,” Consumers Energy Co.,
The Commission’s policy regarding credits for network upgrades associated with the interconnection of a generating facility has been, and continues to be, that all network upgrade costs (the cost of all facilities from the point where the generator connects to the grid), including those necessary to remedy short-circuit and stability problems, should be credited back to the customer that funded the upgrades once delivery service begins.
Consumers Energy Co.,
Petitioners urge us to read Entergy I narrowly, restricting it to the facilities at issue in that case: short-circuit and stability network upgrades.
The only difficulty — and though it is a small one, it is one upon which potentially millions of dollars of cost allocation rest-is whether “from” as a test of allocation justified by the Commission in Consumers Energy I equates to “at or beyond” as the Commission urges in the present controversy, or merely, to “beyond.” Either is a natural reading of “from.” For example, when a bridal couple declares their fealty “from this day forward,” we would not likely interpret this as a declaration of faithfulness to begin the next day. The Commission’s “at or beyond” test is consistent with such an immediate beginning inclusive of everything from the point of commencement including that point. On the other hand, if a travel guide tells us that it is “one hundred miles from City A to City B,” we would not necessarily assume that any distance within the city of commencement is included within that one hundred miles. Neither construction would be unreasonable. Normally, we would defer to the Commission’s interpretation of its own pri- or ruling. Cassell v. FCC,
As we noted above, FERC’s explanation of its policy application to the present contract depends upon its adoption of its rationale from the Consumers Energy decisions. As we further discussed above, justification by adoption of a prior ruling is perfectly appropriate and adequate. The difficulty is that the Commission’s explanation in Consumers Energy, at least on its face, is not consistent with the Commission’s application of the test to the facts before us. Nevada Power’s petition does not depend on any inherent flaw in the “from” test as applied to improvements beyond the point of interconnection, but only as to those precisely “at” the interconnection. It appears from the face of Consumers Energy II that the Commission’s application of its test to the facts before it in that case may have been consistent with Nevada Power’s interpretation rather than the one FERC advances now. The total interconnection cost at issue in Consumers Energy was $13.2 million. Of that total, the Commission permitted (albeit almost sub silentio) direct assignment of the “$3 million ... attributable to the physical interconnection of the generating facility with consumers’ transmission grid,” and approved credit for the “remaining $10.2 million in network upgrade costs .... ” Consumers Energy I, 95 F.E.R.C. at 61,082. If the Commission had intended “from” to mean “at or beyond” rather than simply “beyond,” then it is not at all clear what accounts for the $3 million in direct assignment, as the interconnection presumably is “at” the determinative point. We therefore must vacate the order under review and remand the controversy to the Commission for further proceedings.
The progression of Commission pronouncements of its network upgrade policy demonstrates that the “At or Beyond” test is the product of regulatory evolution— marked by change, not consistency — beginning with Consumers Energy. The Commission issued Consumers Energy I on May 17, 2001. There it described “all network costs” as “the cost of all facilities from the point where the generator connects to the grid.” 95 F.E.R.C. at 61,804 (emphasis added). As we noted, supra, in that analysis the Commission did not consider “the physical interconnection of the generating facility with ... the grid” to be a “network upgrade.” Consumers Energy I itself was a clarification, see Entergy I,
Less than one month after the issuance of Consumers Energy I, Commissioner Wood called for a change in policy. He proposed that “costs of transmission beyond the power plant busbar which are needed to accommodate the output of the new generation facility should be borne by the transmission service provider .... ” Detroit Edison Co.,
One month after Commissioner Wood’s statement in Detroit Edison, the Commission denied a rehearing in Consumers Energy, and it made no reference to either a “From” test or an “At or Beyond” test, but it referred only to network “upgrade” costs. Consumers Energy II, 96 F.E.R.C. at 61,561.
The day after Consumers Energy II, however, the Commission stated its policy in a manner resembling an “At or Beyond Test” more than a “From” test of the sort suggested in Consumers Energy I, as it described the difference between a direct-assignment “interconnection facility” and a “network upgrade.” As the Commission noted: “Interconnection facility costs are those costs associated with facilities on the generator’s side of the interconnection with the grid, which traditionally have been directly assigned to the generator. Network upgrade costs are any upgrades necessary to grid facilities to allow the generator to inject its power at the interconnection.” Removing Obstacles to Increased Electric Generation And Natural Gas Supply In The Western United States,
Reading these cases, recounting the Commission’s development of a “From” test, tracing its transformation into an “At or Beyond” test, and keeping in mind the Commission’s subsequent assertions that the two tests are one and the same, we are left with the conclusion that the “At or Beyond” test represents an apparent departure from Consumers Energy’s “From” test. That departure may be slight, but it is a departure nonetheless.
We do not suggest that the Commission may not directly assign the costs at issue — as is apparent from our discussion in Part C, the same substantial evidence appears to support either test. But if the Commission does so, it must provide further explanation. The Commission may change its practices, but it must do so with “reasoned analysis indicating that prior policies and standards are being deliberately changed, not casually ignored.” Entergy I,
Although an agency’s interpretation of its own precedent is entitled to deference, Cassell v. FCC,
For the reasons set forth above, we conclude that the petitions of Southern and Entergy must be dismissed. However, as to the order from which Nevada Power petitions for review, we order that it be vacated and the case remanded to the Commission for further proceedings consistent with this opinion.
So ordered.
Notes
. In reaching this conclusion, we do not ignore Capitol Technical Servs., Inc. v. FAA,
Concurrence Opinion
concurring in part and concurring in the judgment.
I agree with the court on the merits and join Parts I and II.B-D of its opinion. I also agree that we lack jurisdiction over the Entergy and Southern petitions, but I cannot join Part II.A because, in my view, the court’s approach “incorrectly con-flatefs] our case law on initial standing to bring suit with our case law on postcom-mencement mootness,” Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc.,
. Two of the three petitions fail — unarguably, in my view — on standing grounds alone. Entergy filed its petition for review on June 24, 2002, ten days after FERC accepted ,the company’s proposed termination of its Interconnection Agreement (“IA”) with Amelia Energy Center. Southern filed its second petition for review on February 13, 2003, more than a month after the effective cancellation of its IA with Athens Development. Since neither IA remained in effect at the time the companies sought judicial review, precedent requires that we address jurisdiction as a question of standing, not mootness.
In Advanced Management Technology, Inc. v. FAA,
Given this case law, I believe this court had no reason to consider whether mootness exceptions apply to the Entergy and second Southern petitions, as the two companies lacked standing in the first place. Once their IAs had terminated, neither qualified as a party “aggrieved by an order issued by the Commission” within the meaning of section 313(b) of the Federal Power Act, 16 U.S.C. § 8251(b). “The requirement of aggrievement serves to dis
Southern’s first petition for review presents a different, more complex situation. Southern filed that petition on November 1, 2002, almost three months before FERC accepted the termination of the company’s IA with Blount County Energy. “[A]t the time the action eommence[d],” Laidlaw Envtl. Servs.,
We thus need to determine whether a justiciable controversy remains due to Southern’s broader reason for objecting to the challenged order — namely, the company’s claim that the policies underlying that order require it to revise other IAs, revisions that will cost it some $22 million. This court faced a similar issue in Capitol Technical Services, Inc. v. FAA,
Disregarding Capitol Technical Services, the court today holds that once a
As to mootness, we have typically applied the policy-challenge exception to mootness in situations where the specific requests became moot due to circumstances beyond petitioners’ control. See Capitol Technical Servs., Inc.,
To begin with, this case differs from Capitol Technical Services in a significant respect. There, the FAA “ha[d] not even suggested that any further policy evolution could be expected.”
Over a quarter century ago, Justice Brennan warned that “Art. Ill jurisprudence ... in such areas as mootness and standing is creating an obstacle course of confusing standardless rules to be fathomed by courts and litigants.” Kremens v. Bartley,
