Enplanar, Inc. v. MarshEnplanar, Inc. v. Marsh
This case involves the grant of summary judgment against a suit for unspecified damages from a three-month suspension of a discretionary minority set-aside program. E.J.A., Inc. (EJA); Enplanar, Inc. (Enplanar); Dragon Limited, Inc. (Dragon); and V. Keeler & Co., Inc. (Keeler) appeal the district court‘s grant of summary judgment in favor of the United States Army Corps of Engineers (the Corps). We affirm.
Facts and Proceedings Below
This case relates to the Corps’ administration of its set-aside program for minority businesses (the 8(a) program), as described in the
Prior to the case sub judice, three nonminority small-business contractors challenged the Corps’ joint administration of the 8(a) program with the SBA. Specifically, these contractors challenged the Corps’ submission practice whereby it set aside one-hundred percent of its small-business contracts for minority businesses. These contractors contended that in setting aside one-hundred percent of the contracts, the agencies failed to consider the effect a minority enterprise set-aside would have on competing nonminority small-business contractors. The district court initially dismissed the suit on mootness grounds, and we reversed. Valley Constr. Co. v. Marsh, 714 F.2d 26 (5th Cir.1983) (Valley I). On remand, the district court held that the Corps’ administration of the 8(a) program impermissibly excluded the nonminority small-business contractors in violation of
In early November 1990, in response to the Fordice decision and the withdrawal of the government‘s appeal, the Corps sought legal guidance from Army Headquarters concerning the continuing legality of its administration of the 8(a) program, and the possible personal liability of the contracting officers in submitting contracts to the SBA under the program. While awaiting advice, the Corps continued to abide by previously awarded 8(a) contracts, and exercised the options on all 8(a) contracts for extending performance by the minority contractor into later years. Although the Corps did not terminate any pre-existing 8(a) contracts, it did hold in abeyance any ongoing activity in reference to 8(a) contracts not yet awarded. This abeyance continued until January 22, 1991, when the Corps received guidance from Army Headquarters notifying it that, as to the currently administered 8(a) program, there existed no legal impediment to awarding contracts to the SBA through the 8(a) program.2
On January 8, 1991, EJA, Enplanar, Dragon, and Keeler (collectively, the Contractors) brought suit in Louisiana seeking injunctive and declaratory relief against, inter alia, the Corps and its personnel in their official capacities, and the SBA (collectively, the Defendants), claiming that the Corps’ suspension of their 8(a) referrals to the SBA discriminated against the Contractors in violation of
Specifically, EJA alleged that, prior to the abeyance, the Corps failed to renew the Southwest Pass program even though EJA had worked on the project during the previous year. The Corps did not dispute that in April of 1990, it had decided not to place the project in the 8(a) program because it already had four of its ten small-business projects in the program, and was concerned about the potential legal liability of adding more small-business projects to the 8(a) program. EJA alleged that it had a reasonable
On February 8, the district court directed the parties to brief whether the SBA was a necessary party in light of the fact that the suspension had been lifted. On February 27, in its responsive brief, the Contractors stated that the SBA was not a necessary party, and indicated in the summary of its argument that all injunctive relief was moot. However, in the argument itself, they asked for injunctive relief as to the Cotton Meade project. On March 13, the district court denied the Contractors’ partial motion for summary judgment seeking injunctive relief finding that all such relief was moot.
The Defendants then filed motions for summary judgment and for change of venue. On March 26, the magistrate stayed discovery pending a ruling on the venue motion. The Contractors made a Rule 56(f) motion to compel discovery, which was denied. Subsequently, the Contractors filed an amended complaint alleging post-suspension claims for retaliation and unconstitutional interference with the Contractors’ rights of access to the courts, based on the Corps engineers’ refusal to meet with the Contractors during the pendency of this suit. This amended complaint added as defendants Corps’ engineers Stephenson W. Page (Page) and Robert Green (Green) in their individual capacities (the original complaint had included them in their official capacities). It also requested attorneys’ fees, claiming that the Contractors’ lawsuit caused the Corps to lift its suspension. In response, the Defendants filed a supplemental memorandum in support of their motions for summary judgment, addressing the new claims.4 On July 15, the district court granted summary judgment on all of the Contractors’ claims except for Keeler‘s claims concerning the Cotton Meade project. These latter claims were transferred to Mississippi based on the Defendants’ motion for change of venue.
Discussion
The Contractors now argue on appeal that the district court erred by: (1) denying their motion for partial summary judgment on the merits for injunctive relief; (2) denying their additional discovery; (3) prematurely ruling on their claims; (4) granting summary judgment against their claims concerning the Defendants’ alleged suspension of the 8(a) program and retaliation; (5) dismissing their claim for attorneys fees; and (6) granting the change of venue motion regarding Keeler‘s Cotton Meade project claims.
I. Denial of Injunctive Relief
The Contractors contend that the district court erred in denying as moot their motion for partial summary judgment concerning injunctive relief. They admit that the resumption of the 8(a) program did moot their request for injunctive and declaratory relief which sought to lift the Corps’ suspension of the 8(a) program. However, they argue that the district court erred in ruling that they also were not entitled to injunctive relief concerning the Southwest Pass project and the Cotton Meade project. They contend that the district court erroneously found all of their requested injunctive relief moot
In Valley I, we held that as to the Corps’ administration of the 8(a) program, “injunctive relief would be improper because a necessary party to the suit is the SBA, which administers the overall § 8(a) minority enterprise set-aside program. The Small Business Act,
II. Discovery
The Contractors claim that the district court denied them proper discovery so that
As to the Cotton Meade project, these claims were not disposed of in summary judgment, but were rather transferred to another court based on the Defendants’ motion for change of venue.
Concerning the remaining claims, which were subsequently disposed of by the district court‘s grant of the Defendants’ summary judgment motion, the Contractors were entitled to receive a continuance for additional discovery if they: (i) requested extended discovery prior to the court‘s ruling on summary judgment; (ii) placed the district court on notice that further discovery pertaining to the summary judgment motion was being sought; and (iii) demonstrated to the district court with reasonable specificity how the requested discovery pertained to the pending motion. Chevron U.S.A., Inc. v. Traillour Oil Co., 987 F.2d 1138, 1155-56 (5th Cir.1993); Wichita Falls, 978 F.2d at 919 (citing Int‘l Shortstop, Inc. v. Rally‘s, Inc., 939 F.2d 1257 (5th Cir.1991)).
As to the first two requirements, we can review a claim alleging improperly de
Only in two motions, do the Contractors bring to the district court‘s attention a request for additional discovery concerning claims other than the Cotton Meade project. In their opposition motion and additional opposition motion to the Defendants’ motions for summary judgment and for change of venue, the Contractors note in passing that they have been refused a copy of the Justice Department‘s memorandum concerning its October 1990 determination not to appeal the Fordice decision.8 In these passing references, they do not explain how this requested discovery would or could create a fact issue to overcome the Defendants’ summary-judgment motion.9 Therefore, they have failed the third requirement which requires them to demonstrate to the district court with reasonable specificity how the requested discovery would likely pertain to the pending summary judgment motion. See Krim v. BancTexas Group, Inc., 989 F.2d 1435, 1442 (5th Cir.1993) (holding that a nonmovant‘s Rule 56(f) motion was insufficient where “absent from the affidavit was an explanation of ... how the materials listed in the plaintiffs first document request, or in the handwritten list appended to the affidavit, would enable plaintiff to oppose defendant‘s summary judgment motion by establishing a genuine issue of material fact“). Certainly, we are not requiring clairvoyance on the part of the Contractors. They do not need to know the precise content of the requested discovery, but they do need to give the district court some idea of how the sought-after discovery might reasonably be supposed to create a factual dispute. The mere fleeting mention of a matter, without a description of its likely relevance, will not suffice to alert the district court to the potential importance of that undiscovered item. Therefore, the district court did not abuse its discretion in denying additional discovery.
III. Summary Judgment Procedure
The Contractors complain that the district court prematurely dismissed their claims of retaliation against defendants Page and Green in their individual capacity, and that it prematurely granted summary judgment in favor of all of the Defendants without giving the Contractors notice. Specifically, the Contractors assert that the district court sua sponte dismissed their claims against Page and Green because the only motion filed on their behalf was a motion to dismiss for improper service which was subsequently cured. Furthermore, the Contractors claim that the district court granted summary judgment dismissing their amend
These two arguments conveniently overlook the Defendants’ supplemental memorandum in support of their motions for summary judgment. This document was filed on May 13, 1991, after the Contractors’ amended complaint, and it specifically addresses the claims in that amended complaint. This document addresses, as a ground for dismissal, the Contractors’ failure to properly serve Page and Green, but it also explicitly discusses various grounds for summary judgment as to all the defendants—including the retaliation claims brought against Page and Green. Therefore, this memorandum served to supplement the original summary judgment motion, and provided the Contractors with notice of the Defendants’ challenges to their amended complaint. Cf. Spickard v. Ribicoff, 211 F.Supp. 555, 558 (W.D.Ky.1962) (granting summary judgment where no motion was filed but the movant submitted a brief in support of summary judgment and the nonmovant treated it as a summary judgment motion).10 Although the district court on July 15, 1991, granted a dismissal as to Page and Green, it also granted summary judgment as to all the defendants based on evidence not contained in the pleadings. Under these circumstances, the district court‘s order to dismiss the complaint as to Page and Green is disregarded, and we instead review the grant of summary judgment as to all defendants—including Page and Green. See
IV. Summary Judgment Claims
The Contractors contend that the district court erred in granting summary judgment
The Contractors first argue that the district court erred in ruling that they were not entitled to declaratory relief arising from the partial suspension of the 8(a) program.12 They contend that because of their minority status they were denied their equal-protection rights, and that the 8(a) program was administered in a discriminatory manner in violation of
The three-month suspension affected only the Corps’ decisions regarding the submission of new projects to the SBA. Such a decision is within the complete discretion of the Corps.
Finally, the Contractors contend that the district court erred in rejecting their Bivens claims for declaratory, injunctive, and monetary relief. Their Bivens claims alleged constitutional torts against Page and Green for denying the Contractors the ability to self-market their services to the Corps.15 Under Bivens, “the victim of a constitutional violation by a federal agent has a right to recover damages against the agent in federal court.” Bush v. Lucas, 647 F.2d 573, 575 (5th Cir. Unit B June 1981), aff‘d, 462 U.S. 367, 103 S.Ct. 2404, 76 L.Ed.2d 648 (1983). Therefore, a Bivens action requires the plaintiff to “claim a deprivation of a constitutional right.” Zernial v. United States, 714 F.2d 431, 435 (5th Cir.1983). This action extends to alleged violations of the First Amendment and to deprivations of Fifth Amendment due process rights. Bush, 462 U.S. 367, 103 S.Ct. 2404 (First Amendment); Butz v. Economou, 438 U.S. 478, 98 S.Ct. 2894, 57 L.Ed.2d 895 (1978) (Fifth Amendment). The Contractors’ Bivens claims are based on two theories: that they have a right to self-marketing and they have been deprived of that right without procedural due process in contravention of the Fifth Amendment; and that this denial of self-marketing is in retaliation against the Contractors, and is an attempt to deny them access to the courts as is their right under the First Amendment.
To succeed on a procedural due process claim, the Contractors must show they had a “cognizable property or liberty interest,” and such a property interest must be “a legitimate claim of entitlement.” Broadway v. Block, 694 F.2d 979, 985 (5th Cir.1982). Here, there exists no legitimate claim of entitlement. The Contractors have no right to access of Corps personnel for this purpose.
The Contractors also contend that the denial of self-marketing is in retaliation for the lawsuit and is designed to chill access to the courts of the United States in violation of the Contractors’ First Amendment rights.16 Because of the preeminent place that the First Amendment occupies in our constitutional jurisprudence, the Contractors need not prove that in being denied the right to self-market, they have been denied a property right or liberty interest or some other independent legal right. See Connick v. Myers, 461 U.S. 138, 103 S.Ct. 1684, 75 L.Ed.2d 708 (1983). But they still must show a constitutional violation. Here, the fact that the contracting officers refused to speak to the Contractors during the pendency of this suit does not indicate that such refusal was made in an effort to chill the Contractors’ access to the courts or to punish them for having brought suit. Rather, such a refusal was made pursuant to an Information Paper that instructed agency procurement officers to avoid contact with contractors during the pendency of their litigation with the agency.17 This paper was issued on February 6, 1990—months before the suspension—and was apparently distributed by the Army‘s general counsel to all defense procurement agencies. It notes that contact should be avoided so that the procurement officer will not inadvertently “give the contractor any ammunition to weaken the Government‘s position. Any such statements may be used by the contractor in litigation and may ultimately lead to the depositions of the officials who make the statements and their subsequent testimony.” A government employee who is a potential witness is not improperly chilling access to the courts or retaliating for use of the judicial system when he refuses to speak to a party concerning a matter that is related to the gravamen of that party‘s litigation against him or his employer. Page and Green did not deny the Contractors their constitutional rights under the First Amendment. There is nothing which would sustain a finding that Page and Green‘s actions—perhaps more accurately, their inactions—were retaliatory or motivated by considerations other than those of the Information Paper or that they were a pretext for unconstitutional retaliation. Consequently, “any assertion that [the officers‘] actions ... were retaliatory can only be speculation.” Bowles v. U.S. Army Corps of Engineers, 841 F.2d 112, 117 (5th Cir.), cert.
V. Attorneys’ Fees
The Contractors argue that they are entitled to attorneys’ fees under
Section 1988 can serve as the basis for the recovery of attorneys’ fees only if the Contractors can show that they have presented a substantial racial discrimination claim. See Kelly v. City of Leesville, 897 F.2d 172, 177 (5th Cir.1990); McDonald v. Doe, 748 F.2d 1055, 1077 (5th Cir.1984) (noting that section 1988 “was adopted because the actions in which fees are allowed vindicate rights based on the federal constitution or federal statutes. If it is determined that no constitutional right was violated, the predicate for the award of fees vanishes.“). However, as we have discussed above, the Contractors have wholly failed to make out a claim for racial discrimination. At best, the Contractors have alleged that the Corps suspended the 8(a) program for an inadequate reason: their fear that the Fordice decision will lead to further lawsuits or potential liability concerning their participation in the 8(a) program. But, the Corps’ suspension of the program based on its reaction to the Fordice decision does not somehow transmute that motivation into racial discrimination. Even assuming that the Contractors’ actions caused the resumption of the 8(a) program, since the suspension was not based on any racial animus, the Contractors could not recover under section 1988(b) and therefore cannot be considered prevailing parties under that statute. See McQuiston v. Marsh, 707 F.2d 1082, 1085 (9th Cir.1983) (finding that an unsuccessful bidder on a government contract could be a prevailing party under section 2412 based on his claim of bad faith, but not under section 1988 because he could not prevail on his discrimination claim).
The Contractors can recover under the Equal Access to Justice Act codified at section 2412(d)(1)(A) only if they show: (1) that they are a “prevailing party“; (2) that the Government‘s position was not “substantially justified“; and (3) that no “special circumstances make an award unjust.” Perales v. Casillas, 950 F.2d 1066, 1072 (5th Cir.1992).19 The Contractors have not alleged any facts showing that the Defendants’ position was not substantially justified. Since the Defendants’ abeyance was based on the adverse Fordice decision, we find that their position concerning the suspension of the 8(a) program pending further guidance was sub
VI. Change of Venue
The Contractors contend that the district court erred in granting the Defendants’ change of venue motion as to Keeler‘s Cotton Meade project claims. However, the grant of a change of venue motion is an interlocutory order and is not reviewable. See Louisiana Ice Cream Distributors v. Carvel Corp., 821 F.2d 1031, 1033-34 (5th Cir.1987); Garner v. Wolfinbarger, 433 F.2d 117, 120 (5th Cir.1970); Chas. Pfizer & Co. v. Olin Mathieson Chem. Corp., 225 F.2d 718 (5th Cir.1955). Keeler‘s Cotton Meade project claims have been severed from this action and transferred to a different forum. These claims are unreviewable in this appeal.
Conclusion
Based on the foregoing, the district court‘s orders are
AFFIRMED.
Notes
The Contractors also argue that other circuits have held that the SBA is subject to injunctive relief in certain circumstances regardless of the applicability of section 1491(a)(3). See Ulstein Maritime, Ltd. v. United States, 833 F.2d 1052, 1056 (1st Cir.1987), and cases cited therein. However, as noted by Ulstein, this Circuit has “concluded that all injunctive relief directed at the SBA is absolutely prohibited.” Id. We are bound by our prior decisions that such relief is barred. See Valley I, 714 F.2d at 29, Romeo v. United States, 462 F.2d 1036, 1038 (5th Cir.1972), cert. denied, 410 U.S. 928, 93 S.Ct. 1361, 35 L.Ed.2d 589 (1973); Expedient Servs., Inc. v. Weaver, 614 F.2d 56 (5th Cir.1980).
As to the Cotton Meade project, the district court‘s ruling is not before us. Keeler‘s claims concerning this project have not been disposed of, but merely transferred to a different venue. Therefore, the district court‘s ruling denying the Contractors’ partial summary-judgment motion concerning the availability of injunctive relief as to this project is an interlocutory order not subject to appeal at this time. See 10 Charles A. Wright & Arthur R. Miller, Federal Practice and Procedure § 2715 p. 636 (noting that “the denial of a Rule 56 motion is an interlocutory order from which no appeal is available until the entry of judgment“); see also In re Corrugated Container Antitrust Litigation, 694 F.2d 1041 (5th Cir.1983).