48 Mass. App. Ct. 239 | Mass. App. Ct. | 1999
The plaintiffs are fourteen taxpayers domiciled in Plymouth who own property in the vicinity of the Eel River. They have brought a complaint seeking a declaratory judgment that a certificate of compliance issued by the Secretary of Environmental Affairs (Secretary) to the town of Plymouth
The complaint alleged that the town disposes of treated sewage effluent using an outfall pipe which carries the effluent into Plymouth Harbor. The Massachusetts Department of Environmental Protection (DEP) brought suit against the town in 1987, alleging violations of water quality standards. The suit was settled in 1992 by the entry of a consent decree which required the town to achieve compliance with the Massachusetts Clean Waters Act, see G. L. c. 21, §§ 26-53, by the design and construction of a wastewater treatment plant, an effluent disposal facility, and other related facilities.
Efforts to comply with the 1992 consent decree were unsuccessful, and the consent decree was modified in 1994 and called for new studies of the town’s problems. The town proposed a new sewage treatment plant which would dispose of treated sewage through the existing outfall pipe with the remainder to be disposed into the groundwater of the Eel River watershed. On November 1, 1996, the Secretary issued her certificate to the effect that the town’s “Wastewater Treatment Facilities Plan/ Environmental Impact Report Phase IIIA,” as supplemented by
Thereupon the town appropriated funds for the design and construction of the proposed facilities, but on January 11, 1997, a referendum vote overturned the appropriation of funds to build a sewage treatment plant which would dispose of the treated sewage into the Eel River watershed.
The town responded by filing a Notice of Project Change with the Secretary to allow for the re-evaluation of eight alternative sites for the plant. On April 2, 1997, the Secretary issued a certificate requiring the town to prepare a Final Supplemental Environmental Impact Report (FEIR). On April 30, 1997, the town’s FEIR was submitted to the Secretary for review under the Massachusetts Environmental Policy Act (MEPA), and on June 16, 1997, the Secretary issued a certificate stating that the town’s FEIR was in compliance with MEPA.
The town now proposes to construct a sewage treatment plant which disposes of permitted amounts of treated sewage through the existing outfall pipe, with the remainder channeled into the groundwater of the Eel River watershed. The proposed location of the plant is also alleged to be in the immediate vicinity of the properties owned by each of the plaintiffs.
The plaintiffs claim that the Secretary’s certificate, issued under the Secretary’s regulations, was invalid because the town’s FEIR did not comply with MEPA, G. L. c. 30, §§ 61-62H, and its implementing regulations, 301 Code Mass. Regs. §§ 11.01 et seq.
For the purpose of reviewing the allowance of a motion to dismiss, we accept as true the allegations of the complaint, and we draw all reasonable inferences in favor of the opponent of the motion. Fairneny v. Savogran Co., 422 Mass. 469, 470 (1996). On that basis we inquire whether it appears certain that the plaintiffs were not entitled to relief under any facts which could be proved in support of their claim. See Spinner v. Nutt, 417 Mass. 549, 550 (1994).
The complaint alleges that the FEIR submitted to the Secretary for review under MEPA did not respond to the Secretary’s demand, in response to the town’s previous draft FEIR, for additional analysis and disclosure of environmental impacts; failed to contain a plain statement of the major environmental effects of the project and its alternatives; did not address the baseline “no-build” alternative; did not consider the cumulative environmental effects of the projects on other projects in the area; did not adequately quantify the direct and indirect environmental effects of the project; did not identify the means by which negative effects of the project are to be limited; and did not discuss the alternatives to the proposed mitigation measures.
As for the plaintiffs’ alleged injuries, the complaint alleges that each plaintiff named in the complaint owns real property which is within 2,000-5,000 feet from the proposed sewage treatment plant, and uses the Eel River for numerous recreational purposes such as fishing, boating, and swimming. As to each plaintiff, the complaint alleges that the use and enjoyment of his or her property will be harmed by the offensive odors produced by the sewage treatment and discharge. The complaint further alleges that the proximity of the proposed sewage treatment
The town’s FEIR is not before us, and we accept as true each of the foregoing allegations, as well as all reasonable inferences that may be drawn in support of the probative value of the allegations. So understood, the complaint, on its face, has sufficiently described an inadequate FEIR as measured by the statutory requirements of an environmental impact report, see G. L. c. 30, § 62B, which we set out in the margin,
Given the assumed failure of the town’s FEIR to satisfy the requirements of § 62B and the Secretary’s regulations, the Secretary’s certificate of full compliance with MEPA was also presumptively invalid,
The Secretary’s argument misconceives the principle of standing in a case such as the one before us. Of course, the plaintiffs must show legally cognizable injury. See, e.g., Circle Lounge & Grille, Inc. v. Board of Appeal of Boston, 324 Mass. 427, 430 (1949) (“Commonly a person aggrieved is one whose legal rights have been infringed”). The critical question is, when does an alleged injury become “legally cognizable.” See Villages Dev. Co. v. Secretary of the Exec. Office of Envtl. Affairs, 410 Mass. at 106. In zoning cases, for example, what is legally cognizable may turn on the identification of the “legal rights [which] were intended to be given to the plaintiff by the statute permitting the appeal [from a variance].” Circle Lounge & Grille, Inc. v. Board of Appeal of Boston, 324 Mass. at 431. Thus, in Circle Lounge, the plaintiff, whose land was in a business district, had no standing to complain of the grant of a variance to the defendant whose land was in a residential district. Chief Justice Qua wrote, “[Although a proprietor’s rights under
This analysis, which turns on identifying the rights intended to be protected by the applicable statute or regulation, was more recently discussed in Massachusetts Assn. of Indep. Ins. Agents & Brokers, Inc. v. Commissioner of Ins., 373 Mass. 290, 294 (1977). There, insurance agents and brokers claimed standing to challenge a regulation of the insurance commissioner on the ground that “the plaintiffs might be subject to unfair competition” as a result of the regulation. Id. at 296. The case was brought under c. 231A; no statutory right of appeal was involved. The court held that the plaintiffs had standing
We arrive, then, at the central issue in this case: what is the area of concern of MEPA and the regulations promulgated thereunder, and do the plaintiffs’ alleged injuries fall within that area of concern? We turn to the MEPA statutes.
The primary purpose of MEPA is the avoidance of damage to the environment by requiring all State and local agencies to determine the environmental impact “of all works, projects or activities conducted by them” and to “use all practicable means and measures to minimize damage to the environment.” G. L. c. 30, § 61.
MEPA’s area of concern clearly is the protection of the environment from damage caused by projects having an environmental impact. The administrative vehicle for achieving MEPA’s goals of minimizing and preventing damage to the environment is the environmental impact report. See 301 Code Mass. Regs. § 11.07 which, as discussed above, prescribes the detailed discussion of environmental impacts in nontechnical language. See also 301 Code Mass. Regs. § 11.08 (1993), which provides for the opportunity for public hearings, informal workshops, public meetings, written comments from the public, and publication in the Environmental Monitor of notice of the availability of the draft report.
The administrative process of MEPA, then, and the public’s involvement in that process, are critical to achieving MEPA’s goal of protecting the environment, and claims of the foreseeable degradation both of the environment and of the administrative review process are equally areas of concern of MEPA. Without close adherence to the review process of environmental
The plaintiffs’ alleged injuries and complaints fall squarely within the concerns of MEPA: the foreseeable negative environmental impact of the town’s project, and the failure to comply with material requirements of MEPA’s administrative process. In particular, the complaint alleges that the foreseeable consequences of the town’s allegedly defective FEIR will, if the project goes forward without completing the review process as required by the regulations, cause environmental damage because of noxious odors from the nearby sewage treatment plant and the pollution of the watershed of the Eel River, all of which will result in the deterioration of the value and the use
The judgment is reversed, and the case is remanded to the Superior Court for further proceedings.
So ordered.
In cases seeking declaratory relief regarding administrative action, the plaintiff must show (1) an actual controversy, (2) that he or she has standing, (3) that necessary parties have been joined, and (4) that available administrative remedies have been exhausted. See Villages Dev. Co. v. Secretary of the Exec. Office of Envtl. Affairs, 410 Mass. 100, 106 (1991). Of these four factors, the Secretary only puts in dispute factor two — the absence of standing of the plaintiffs. We confine this opinion, therefore, to a discussion of that issue.
The Secretary required additional disclosures regarding environmental impacts without, apparently, affecting the Secretary’s certificate of full compliance with MEPA. See note 9, infra.
During the relevant time period of this case, the 1993 version of the regulations was in effect. The regulations were amended in 1998.
The motion did not state the grounds on which it was brought. Instead, reference was made to an accompanying memorandum of law. That memorandum is not in the record before us. The plaintiffs do not claim that any of the Secretary’s arguments are made for the first time on appeal, and we accept the Secretary’s brief to this court as essentially the argument she made below.
The Secretary makes no argument that the plaintiffs have not complied
The record appendix includes an affidavit of a realtor regarding the diminution in the value of the plaintiffs’ properties that has already occurred. The judge did not convert the Secretary’s motion to dismiss into a motion for summary judgment, and therefore did not consider the affidavit. We follow that path.
General Laws c. 30, § 62B, provides that an “environmental impact report shall contain statements describing the nature and extent of the proposed project and its environmental impact; all measures being utilized to minimize environmental damage; any adverse short-term and long-term environmental consequences which cannot be avoided should the project be undertaken; and reasonable alternatives to the proposed project and their environmental consequences.”
The complaint alleges that notwithstanding the Secretary’s compliance
The court noted that the “ ‘actual controversy’ and standing requirements should be liberally construed in accord with the provisions of G. L. c. 231A, § 9.” Massachusetts Assn. of Indep. Ins. Agents & Brokers, Inc. v. Commissioner of Ins., 373 Mass. at 293.
In Massachusetts Assn. of Indep. Ins. Agents & Brokers, Inc. v. Commissioner of Ins., 373 Mass. at 295, the court refers to the fact that the case involves a regulated industry, but it did so in the context of a regulatory scheme that “shows a clear public interest in the maintenance of a reasonable competitive level,” thereby justifying the recognition of unfair competition as a cognizable injury. Contrast Circle Lounge & Grille, Inc. v. Board of Appeal of Boston, 324 Mass. at 432.
General Laws c. 30, § 61, provides in part, “All agencies, departments, boards, commissions and authorities of the commonwealth- shall review, evaluate, and determine the impact on the natural environment of all works, projects or activities conducted by them and shall use all practicable means and measures to minimize damage to the environment.”
Cummings arose under G. L. c. 214, § 7A, not c. 231A. Section 7A offers a statutory remedy to ten persons domiciled in Massachusetts for claims of “damage to the environment” without the necessity of establishing further the standing of the plaintiffs. The section permits a civil action brought by such persons upon allegations that damage to the environment is occurring or is about to occur. The Superior Court may restrain the person causing or about to cause such damage provided that the offending conduct is a violation of a statute, ordinance, by-law, or regulation. The complaint in this case does not allege an entitlement to the remedies provided by § 7A. Such an attempt would, in any event, be futile. It is settled that § 7A is not available in a suit against the Secretary in connection with her administration of MEPA. See Walpole v. Secretary of the Exec. Office of Envtl. Affairs, 405 Mass. 67, 71 (1989). Walpole also holds that the acts of the Secretary in merely administering MEPA are not subject to review by certiorari under G. L. c. 249, § 4. Id. at 72-73.
What emerges is that § 7A may be seen as offering parallel relief to c. 231A, although the parties will be different.
See note 13, supra, describing the action authorized by G. L. c. 214, § 7A, which is designed to permit judicial intervention in cases where the environmental damage is imminent. There is no claim of imminent damage in this case.
No doubt the plaintiffs could await the imminent construction of the town’s project, and then bring suit against the town under G. L. c. 214, § 7A. If, as we must assume, the plaintiffs’ claims are meritorious, it would make no sense to permit the town to go forward with a complex project that is doomed at the outset. More important is that here, the administrative process has been exhausted, see note 2, supra, and to require the plaintiffs to await the imminent construction of the project would have a serious adverse effect upon the credibility and importance of the administrative review process — a process which, as we have stated, is critical to the desired outcome of protecting the environment.
It is important to emphasize at this point that we have only the bare bones of the record of the controversy before us. We have neither the environmental impact statement nor the Secretary’s certificate, and we have not considered the merits of the plaintiffs’ claims regarding those documents. It may be that a motion for summary judgment on an amplified record, or a trial on the merits, would yield a different understanding of the case. As matters stand, however, we are confined to the narrow issues presented by an appeal from the allowance of a motion to dismiss.