OPINION
This appeal asks us to determine whether appellants are obligated under an insurance policy and an indemnification provision in a construction contract to reimburse respondent Engineering and Construction Innovations, Inc. (“ECI”) for expenses ECI incurred in repairing a damaged sewer pipeline. Appellant L.H. Bolduc Company, Inc. (“Bolduc”), the subcontractor of ECI, damaged a sewer pipe during the course of a construction project. After ECI repaired the damage, it sought reimbursement from Bolduc’s insurer, appellant The Travelers Indemnity Company of Connecticut (“Travelers”), under an endorsement to Bolduc’s commercial general liability policy naming ECI as an additional insured for liability “caused by acts or omissions” of Bolduc. Travelers denied coverage. ECI then sued Bolduc and Travelers for negligence and breach of contract to recover the costs ECI paid to repair the pipe. A jury found that Bolduc was not negligent, and awarded ECI zero dollars in damages. Following trial, the district court granted summary judgment in favor of Travelers and Bolduc on ECI’s breach of contract claims, concluding that Travelers and Bol-duc had no obligation to reimburse ECI for damages not caused by Bolduc. The court of appeals reversed, determining that ECI was entitled to coverage as an additional insured without regard to Bol-duc’s fault. The court also concluded that Bolduc was required to indemnify ECI, and that the subcontract between ECI and Bolduc did not violate Minn.Stat. § 337.02 (2012), which prohibits indemnification for the fault of others in construction contracts. Because we conclude that ECI did not qualify as an additional insured with respect to the pipe damage and that Bolduc cannot be required to indemnify ECI without violating Minn. Stat. § 337.02, we reverse.
The Project
The Metropolitan Council Environmental Services (“Met Council”) hired Frontier Pipeline, LLC (“Frontier”) as the general contractor on a construction project involving the installation of an underground sewer pipeline in Hugo. After Frontier installed the pipeline, Frontier subcontracted with respondent ECI to install a lift station and force main access structures at specified locations along the pipeline. An access structure provides access to points where two sections of pipeline meet, and is built to allow sections of the pipe to be connected and to provide manhole access to the pipeline.
The Subcontract
In order to excavate pits to construct the access structures without danger of the walls of the pits collapsing, ECI subcontracted with Bolduc to build “coffer
In January 2007 ECI and Bolduc entered into a subcontract (the “subcontract”) drafted by ECI, which provided that Bolduc would “[fjurnish, drive, and remove six ... sheeting cofferdam[s]” over the pipeline at six locations. Under the subcontract, Bolduc was to drive the sheets “per ECI location.”
Bolduc agreed, under the subcontract, to perform its work “efficiently, properly and promptly, in accordance with the terms and conditions of the General Contract, and in accordance with the schedule and sequence given it by ECI.” Moreover, the subcontract indicated that “[n]o advice, recommendations or assistance that representatives of the Owner or ECI may give to [Bolduc] shall operate to relieve [Bol-duc] from complete responsibility for such work as an independent contractor.”
The subcontract also imposed insurance and indemnification obligations on Bolduc, including the following requirements:
[Bolduc] agrees to protect, indemnify, defend, and hold harmless ECI and Owner, to the fullest extent permitted by law and to the extent of the insurance requirements below, from and against (a) all claims, causes of action, liabilities, obligations, demands, costs, and expenses arising out of injury to any persons or damages to property caused or alleged to have been caused by any act or omission of [Bolduc], its agents, employees or invitees, and (b) all damage, judgments, expenses, and attorney’s fees caused by any act or omission of [Bol-duc] or anyone who performs work or services in the prosecution of the Subcontract. [Bolduc] shall defend any and all suits brought against ECI or Owner on account of any such liability or claims of liability. [Bolduc] agrees to procure and carry until the completion of the Subcontract, worker’s compensation and such other insurance that specifically covers the indemnity obligations under this paragraph, from an insurance carrier which ECI finds financially sound and acceptable, and to name ECI as an additional insured on said policies.
[[Image here]]
[Bolduc] agrees to obtain, maintain and pay for such insurance coverage and endorsements as will insure the indemnity provisions and coverage limits above and to furnish ECI certificates of insurance evidencing the aforementioned coverage.
The subcontract identified specific dollar amounts of coverage that the insurance policy was required to provide.
Bolduc obtained commercial general liability insurance from Travelers, which provided coverage during the time period at issue in the amounts required by the sub
That part of any other contract or agreement pertaining to your business ... under which you assume the tort liability of another party to pay for “bodily injury” or “property damage” to a third party or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement.
Bolduc is the named insured under the policy. The policy also includes a Blanket Additional Insured (Contractors) Endorsement, making ECI an additional insured eligible for coverage with respect to certain liabilities specified in the endorsement. The endorsement provides, in relevant part, that:
1. WHO IS AN INSURED — (Section II) is amended to include any person or organization that you[2 ] agree in a “written contract requiring insurance”[3 ] to include as an additional insured on this Coverage Part, but:
al Only with respect to liability for “bodily injury”, “property damage” or “personal injury”; and
b) If, and only to the extent that, the injury or damage is caused by acts or omissions of you or your subcontractor in the performance of “your work” to which the “written contract requiring insurance” applies. The person or organization does not qualify as an additional insured with respect to the independent acts or omissions of such person or organization.
(Footnotes added.)
Damage to the Pipeline
In December 2007 ECI discovered the damage to the underground pipeline that gave rise to this dispute. At one of the cofferdam locations, one of Bolduc’s metal sheets caused damage because it was driven through the edge of the pipe. All parties involved agree that Bolduc drove a sheet into the pipe, and that contact between the sheet and the pipe caused the resulting damage. At the site of the damage, ECI had provided the template and markings designating where Bolduc was to drive the sheeting cofferdams as required by the subcontract.
ECI notified Met Council, Frontier, Bol-duc, and Travelers of the damaged pipe. Frontier, acting on behalf of Met Council, directed ECI to repair the pipe.
In March 2008 ECI submitted a claim to Travelers seeking reimbursement of the pipe repair expenses as an additional insured under the endorsement in Bolduc’s policy. Travelers refused to reimburse ECI, claiming that Bolduc was not the cause of the damage, and therefore ECI’s claim did not fall within the coverage provided by the additional insured endorsement.
The Lawsuit
In August 2008 ECI filed a lawsuit against Bolduc and Travelers. ECI’s complaint alleged that the damage to the pipe was caused by Bolduc’s negligence. ECI also claimed that Bolduc had breached the subcontract by failing to perform its work properly and by failing to indemnify ECI.
Before trial, the parties entered into a stipulation bifurcating the negligence and breach of contract claims. Pursuant to the stipulation, the only issues to be tried to the jury were “(a) ECI’s claim that Bol-duc’s negligence resulted in damage to the pipe at FAS-1 on the Met Council Project, (b) Bolduc’s defense that it was ECI’s negligence that resulted in damage to the pipe, and (c) the amount of damages, if any, to which ECI is entitled if it prevails on its negligence claim.” The parties further agreed that:
ECI’s claims against Bolduc for breach of contract (including but not limited to ECI’s claim that Bolduc breached its obligation to defend and indemnify ECI and obtain insurance to protect ECI), and ECI’s claims against Travelers, shall not be tried ... but shall be preserved in full for determination or resolution by the Court at a later date.... ECI’s claims against Bolduc for breach of contract and ECI’s claims against Travelers shall be resolved on cross-motions for summary judgment. If it is determined that there are disputed issues of material fact, these claims will be tried to the Court without a jury. The parties expressly waive their rights to have these claims decided by a jury.
The stipulation also provided that Travelers would not participate in the trial.
After a 3-day trial, the jury returned a special verdict using a form that had been proposed by Bolduc, and not objected to by ECI. The jury answered two questions. In response to the question “Was [Bolduc] negligent?” the jury answered “No.” According to the special verdict form, the jury did not answer the question “Was [ECI] negligent?” because it had found that Bolduc was not negligent. The spe
Summary Judgment Motions
Following trial, ECI brought motions for summary judgment on its claims against Travelers as well as its breach of contract claims against Bolduc. ECI did not submit a memorandum or any evidence in support of its motions for summary judgment.
Travelers also brought a motion for summary judgment, asking the court to find that the additional insured endorsement did not provide coverage to ECI. Travelers argued that ECI was only entitled to coverage as an additional insured to the extent damage was “ ‘caused by an act or omission’ of Bolduc.” Because a jury determined that Bolduc was not negligent, Travelers urged the court to conclude that the damage to the pipe was not “caused” by Bolduc, and ECI was therefore not entitled to coverage.
In response to Travelers’ motion, ECI asserted that the plain language of the additional insured endorsement provided coverage to ECI “because it is undisputed that Bolduc did, in fact, hit the pipe,” and therefore “the damage was, by definition, caused by Bolduc’s ‘acts or omission.’ ” ECI argued that Travelers’ interpretation of the policy essentially rewrote the policy to include coverage only for Bolduc’s “negligent acts or omissions.” In the alternative, ECI argued that the endorsement was ambiguous, and should be construed in favor of providing coverage.
Bolduc also brought a motion for summary judgment, arguing that the indemnity provision in the subcontract was unenforceable because any obligation to indemnify ECI violated Minn.Stat. § 837.02 (2012). Under Minn.Stat. § 387.02, indemnity of a party to a construction contract other than for liability arising from the promisor’s own wrongful conduct is not enforceable. An exception in Minn.Stat. § 337.05 (2012), however, provides that section 337.02 “do[es] not affect the validity of agreements whereby a promisor agrees to provide specific insurance coverage for the benefit of others.” Bolduc therefore argued that any requirement in the subcontract obligating Bolduc to indemnify ECI that extended beyond the required provision of insurance would be prohibited by Minn.Stat. § 337.02. In the alternative, Bolduc argued that the indemnity provision did not implicate sections 337.02 and 337.05 at all, because the subcontract did not require Bolduc to indemnify ECI for ECI’s own negligence. Bolduc also alleged that it was not in breach of the subcontract because it had obtained the insurance required by the subcontract.
In response to Bolduc’s motion, ECI argued that because Bolduc hit the pipe, “Bolduc is obligated to indemnify ECI to the extent the damages were caused by ‘any act or omission’ on its part, negligent or otherwise.” Moreover, ECI argued that the subcontract did not require Bol-duc to indemnify ECI for its own negligence because “there has never been a judicial determination that ECI was negligent.” Instead, ECI contended that Bol-duc was required to indemnify ECI based on Bolduc’s “act or omission” in breaching the terms of the subcontract requiring Bol-duc to “perform its work in a good and workmanlike manner.”
The district court granted the motions of Bolduc and Travelers in their entirety, dismissing ECI’s claims with prejudice.
The Court of Appeals Opinion
The court of appeals reversed. Eng'g & Constr. Innovations, Inc. v. L.H. Bolduc Co.,
The court of appeals then determined that ECI was an additional insured under the Travelers policy for purposes of the pipe damage. Because the policy limited ECI’s coverage to damage caused by the “acts or omissions of Bolduc,” and not to the “negligent acts or omissions of Bol-duc,” the court concluded that the policy provided coverage for ECI despite the jury verdict finding Bolduc not negligent. Id. at 924. Therefore, the court of appeals reversed the grant of summary judgment in favor of Travelers. Id.
In dissent, Judge Connolly asserted that the majority’s interpretation of the insurance and indemnification clause “invites the mischief that Minn.Stat. § 337.02 ... is designed to avoid.”
Travelers and Bolduc petitioned our court for review, and we granted review on both petitions. This appeal raises two primary issues: (1) whether ECI is entitled to coverage as an additional insured under the Travelers policy for costs incurred in repairing the pipe; and (2) whether ECI is entitled to reimbursement for the pipe repairs from Bolduc under the indemnification provision in the contract.
We review de novo the district court’s grant of summary judgment to Travelers and Bolduc. See Riverview Muir Doran, LLC v. JADT Dev. Grp. LLC,
I.
We turn first to the issue of whether ECI is entitled to coverage as an additional insured under Bolduc’s insurance policy. Travelers argues that ECI does not qualify as an additional insured under the policy with respect to costs ECI incurred in repairing the pipe. First, Travelers argues that because a jury found that Bolduc was not negligent, the pipe damage was not “caused by acts or omissions of [Bolduc],” foreclosing ECI from satisfying the requirements for coverage as an additional insured. Second, Travelers asserts that even if ECI qualifies as an additional insured, ECI did not meet its initial burden of establishing coverage under the policy because ECI was not legally obligated to incur costs in repairing the pipe. ECI disagrees, arguing that it is entitled to coverage.
Interpretation of an insurance policy, and whether a policy provides coverage in a particular situation, are questions of law that we review de novo. Leamington Co. v. Nonprofits’ Ins. Ass’n,
The extent of an insurer’s liability is governed by the language of the insurance policy. Bobich v. Oja,
It is well-established “that the burden of proof rests upon the party claiming coverage under an insurance policy.” Boedigheimer v. Taylor,
In order to recover from Travelers, ECI must show that it is an insured under the policy. See Lott v. State Farm Fire & Cas. Co.,
a) Only with respect to liability for “bodily injury”, “property damage” or “personal injury”; and
b) If, and only to the extent that, the injury or damage is caused by acts or omissions of [Bolduc] in the performance of “[its] work” to which the “written contract requiring insurance” applies. [ECI] does not qualify as an additional insured with respect to the independent acts or omissions of [ECI].
Travelers argues that the sole reasonable interpretation of the endorsement, when read as a whole, is that ECI can only obtain coverage for damages that result from Bolduc’s fault. Travelers further contends that the plain meaning of “acts or omissions” in a liability insurance policy “cannot be divorced from the duty to act or from the standard by which the duty to act is either discharged or breached,” and therefore requires some fault on the part of the acting party before insurance coverage is triggered. Because a jury found Bolduc not negligent with respect to the pipe damage, Travelers asserts that the cost to repair the damage is not “liability ... caused by acts or omissions of [Bol-duc]” and ECI cannot obtain coverage.
ECI, however, argues that its coverage as an additional insured is not dependent upon a finding of Bolduc’s fault. First, ECI argues that the phrase “acts or omissions” is unambiguous, and its plain meaning “contains no requirement of negligence as a precursor to triggering coverage.” Therefore, because it is undisputed that it was the physical act of Bolduc that caused the sheeting cofferdam to come in contact with the pipe, ECI contends that coverage is provided under the policy. Second, ECI argues that even if “acts or omissions” is subject to more than one reasonable interpretation, we must resolve the ambiguity in favor of providing coverage. Finally, ECI asserts that even if some fault or liability must accompany Bolduc’s acts or omissions in order for ECI to qualify as an additional insured, Bolduc was at fault in this case because Bolduc breached the subcontract with ECI by failing to perform its work in a proper manner when it damaged the pipe.
ECI’s argument concerning the scope of coverage provided by the additional insured provision focuses primarily on the meaning of “acts or omissions.” But we do not construe individual words or phrases in insurance policies in isolation. Rather, when determining if an ambiguity truly exists we read the policy as a whole, Henning Nelson Constr. Co. v. Fireman’s Fund Am. Life Ins. Co.,
The language of the additional insured provision indicates that ECI’s coverage under the additional insured endorsement cannot be divorced from the concept of fault. ECI only qualifies as an additional insured under the endorsement if several conditions are met. First, as relevant here, ECI is an additional insured only “with respect to liability for ... ‘property damage.’ ” (Emphasis added). Second, for ECI to be covered under the policy, such liability for damage must have been “caused by acts or omissions of [Bolduc].” Third, ECI cannot be an additional insured with respect to liability caused by “the independent acts or omissions of [ECI].”
With respect to the first requirement, ECI qualifies as an additional insured only if ECI has liability for property damage. If ECI has no liability for property damage, then under the plain language of the additional insured endorsement, ECI is not entitled to coverage. ECI’s liability for property damage could arise only in one of three ways.
First, ECI could have direct liability for property damage. “Direct liability is the imposition of liability when one party. has breached a personal duty ... through his own acts of negligence.” Sutherland v. Barton,
Finally, ECI could be liable for property damage “caused by acts or omissions of
The insurance policy contains a specific exclusion for contractual liability, stating that “[t]his insurance does not apply to ... ‘[b]odily injur/ or ‘property damage’ for which the insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” The exclusion does not apply, however, to contractual agreements under which the insured “assume[s] the tort liability of another party.” Tort liability is defined under the policy as “[a] liability that would be imposed by law in the absence of any contract or agreement.” In other words, the policy only provides coverage for liabilities assumed in a contract to the extent that the contracting party has assumed liability for another’s tortious conduct. Damages resulting from other contractual liabilities — including ECI’s possible assumption of liability in its contract with Frontier for Bolduc’s breach of the subcontract — are plainly excluded from coverage under the policy. Although Travelers did not argue the application of the contractual liability exclusion in the instant case, we conclude that ECI’s interpretation of the additional insured endorsement would be inconsistent with the exclusion language in the policy.
Additional insured clauses do not “enlarge the insurance coverage as defined in the policy[,]” but “merely cause[] the insurance to cover persons other than the named insured within the limits of the policy coverage.” Gudbrandsen v. Pelto,
We therefore conclude that the additional insured endorsement is plainly a vicarious liability provision. Of the three ways in which ECI could become liable for property damage, only one is covered under the additional insured provision and the remainder of the policy. If ECI is directly liable for the property damage, the additional insured provision excludes coverage. If ECI is liable for damage through the assumption of contractual liability for Bol-duc’s acts or omissions, coverage is also excluded under other provisions of the policy. The additional insured endorsement, therefore, only provides coverage if ECI is vicariously liable for property damage “caused by acts or omissions of [Bolduc].” ECI can only be vicariously liable if Bol-duc itself is liable. Because a jury found that Bolduc was not negligent, and that finding has not been appealed, ECI cannot be vicariously liable for Bolduc’s conduct in hitting the pipe, and ECI is not entitled to insurance coverage.
II.
Having concluded that Travelers is not obligated to reimburse ECI because ECI is not an additional insured under the policy, we next consider whether Bolduc has an obligation to reimburse ECI under the indemnification provision in the subcontract.
Determining whether Bolduc is required to indemnify ECI in this case is ultimately a question of statutory interpretation. The objective of statutory interpretation “is to ascertain and effectuate the intention of the legislature.” Minn. Stat. § 645.16 (2012). In statutory interpretation “our first inquiry is whether the statute is ambiguous.” All Parks Alliance for Change v. Uniprop Manufactured Hous. Cmts. Income Fund,
Minnesota Statutes § 337.02 provides, in relevant part, that:
An indemnification agreement contained in, or executed in connection with, a building and construction contract is unenforceable except to the extent that: (1) the underlying injury or damage is attributable to the negligent or otherwise wrongful act or omission, including breach of a specific contractual duty, of the promisor or the promisor’s independent contractors, agents, employees, or delegatees[.]
Section 337.02 therefore renders unenforceable indemnification agreements in which a party assumes responsibility to pay for damages that are not caused by the party’s own wrongful conduct. See Katzner v. Kelleher Constr.,
(a) a promisor agrees to provide specific types and limits of insurance; and
(b) a claim arises within the scope of the specified insurance; and
(c) the promisor did not obtain and keep in force the specified insurance;
then, as to that claim and regardless of section 337.02, the promise shall have indemnification from the promisor to the same extent as the specified insurance.
In a situation in which a promisor has failed to obtain the insurance required under a contract, section 337.05, subdivision
Therefore, when faced with questions about the enforceability of an indemnification provision in a construction contract, we must “consider[] the combined effect of sections 337.02 and 337.05,” and “even though an indemnification provision may be unenforceable under section 337.02, a promise to purchase insurance to cover any negligent acts by the promisee is valid and enforceable.” Katzner,
To determine whether Bolduc can be required to indemnify ECI under the statutory scheme governing indemnification agreements in construction contracts, we first consider whether indemnification in this situation would violate MinmStat. § 337.02 and then whether any indemnification obligation ordinarily barred by section 337.02 is saved by Minn.Stat. § 337.05.
A.
Bolduc argues that under the plain language of the statute, because it was not at fault for the damaged pipe, requiring Bol-duc to indemnify ECI in this situation would run afoul of the prohibition in Minn. Stat. § 337.02. We agree.
Under the plain language of section 337.02, an agreement is unenforceable, unless “the underlying injury or damage is attributable to the negligent or otherwise wrongful act or omission, including breach of a specific contractual duty, of the prom-isor.” Minn.Stat. § 337.02 (emphasis added). Here, the damage to the pipeline was not due to Bolduc’s negligence, wrongful act, or breach of a specific contractual duty. A jury specifically determined that the damage was not attributable to the promisor’s (Bolduc’s) negligence. ECI has never challenged the jury’s verdict. Instead, ECI argues that requiring Bolduc to indemnify ECI does not violate MinmStat. § 337.02 because, in hitting the pipeline, Bolduc breached a contractual duty. Specifically, ECI argues that Bolduc breached its obligation to perform its work “efficiently, properly and promptly,” and by failing to pay for the repairs, breached its agreement to bear “complete responsibility” for its work. We conclude, however, that ECI has waived its argument regarding Bolduc’s contractual liability. ECI moved for summary judgment on all of its breach of contract claims before the district court, and contrary to its assertion, did not preserve any contract claims for a second trial. Indeed, the stipulation of the parties specifies that after trying the negligence issue to the jury, all of the parties’ other claims would be resolved by the district court on cross motions for summary judgment. The court of appeals did not address the district court’s grant of summary judgment determining that Bol-duc had not breached the subcontract by damaging the pipe. And ECI did not petition for review on this issue. See State v.
Even if the claim was not waived, however, ECI has presented no evidence that Bolduc breached the subcontract in performing its work. The district court properly granted summary judgment when it determined, based on the jury’s verdict, that Bolduc had performed its work in accordance with the standard of care prescribed by the contract, and that there was no genuine issue of material fact with regard to the breach of contract claims. In this case, the negligence and breach of contract for performance of work claims both arose out of the same duty; therefore, the jury’s determination on the negligence issue allowed the district court to properly determine that there was no evidence to find Bolduc in breach of its performance of work obligations. See Lesmeister v. Dilly,
B.
Because Bolduc was not at fault for the pipeline damage, any obligation by Bolduc to indemnify ECI would violate MinmStat. § 337.02 unless that obligation was accompanied by a coextensive insurance agreement under Minn.Stat. § 337.05. Having already determined that no insurance coverage is available to ECI under the Travelers’ policy with respect to the pipe damage, any indemnification obligation here is not saved by MinmStat. § 337.05, subd. 1, because any such obligation is not, based on our conclusion in the first section of this opinion, coextensive with an obligation to insure. Therefore, the only way in which Bolduc could indemnify ECI without violating the statutory scheme is if ECI complied with the requirements of MinmStat. § 337.05, subd. 2. Bolduc argues that ECI has waived its only claim that would allow it to recover from Bolduc. If ECI wanted to seek indemnification from Bolduc when Travelers denied its claim, it was required to comply with the statutory language in Minn.Stat. § 337.05, subd. 2. Under section
(a) a promisor agrees to provide specific types and limits of insurance; and
(b) a claim arises within the scope of the specified insurance; and
(c) the promisor did not obtain and keep in force the specified insurance.
Bolduc argues that because this statute clearly lays out the procedure for procuring indemnity when a contract contains an agreement for specific insurance, ECI cannot seek indemnity against Bolduc other than through an argument that Bolduc failed to procure the appropriate insurance. But ECI has waived this claim, and therefore Bolduc argues that it has waived its ability to seek indemnification from Bolduc.
We agree with Bolduc that ECI has waived its claim that Bolduc breached the contract by failing to provide the type of insurance mandated by the contract. This breach of contract claim did not appear in ECI’s original complaint, did not appear in ECI’s motion for summary judgment, and did not appear in its responses to the other parties’ motions for summary judgment. At the hearing before the district court on the summary judgment motions, counsel for Bolduc stated that:
One of the claims that ECI submitted against Bolduc was that Bolduc breached its contract by failing to get additional insured coverage for ECI.... I think ECI concedes at this point in time that the coverage, the additional insured coverage that Bolduc obtained through Travelers satisfies the terms of that contract.”
ECI did not respond. Because ECI waived this claim, we conclude that ECI cannot now reassert this claim on appeal and receive indemnification from Bolduc. Therefore, we conclude that regardless of the scope of the indemnification provision in the contract, any requirement that Bol-duc indemnify ECI is unenforceable because any such requirement would violate Minn.Stat. § 337.02.
Reversed.
Notes
. Under ECI’s subcontract with the general contractor on the project, Frontier, ECI’s scope of work indicated that "[sjurvey and layout of structure locations” would be "by others.” ECI contends that as a result of this language Frontier was responsible for providing ECI with the location of the underground sewer pipeline. Because Frontier was never made a part of the instant lawsuit, the attempts by ECI to place blame upon Frontier are irrelevant to this appeal and speculative at best.
. For purposes of this section of the policy, the words "you” and "your” refer to Bolduc, the named insured in the declaration.
. "Written contract requiring insurance” is defined as:
that part of any written contract or agreement under which you are required to include a person or organization as an additional insured on this Coverage Part, provided that the "bodily injury” and "property damage” occurs and the "personal injury" is caused by an offense committed:
a. After the signing and execution of the contract or agreement by you;
b. While that part of the contract or agreement is in effect; and
c. Before the end of the policy period.
.The contract between Frontier and ECI contains an insurance and indemnity provision identical to the one found in the subcontract between ECI and Bolduc. Frontier and ECI's contract also contains a provision allowing
. In its answer to ECI’s complaint, Bolduc asserted a counterclaim against ECI to recover $45,965 in unpaid costs and services provided to ECI under the subcontract. ECI later agreed that it had paid Bolduc "all but $45,965.53 otherwise owed for work on the project.” ECI therefore "applied this remaining balance to offset a portion of the cost it incurred to repair the damaged pipe.” ECI’s obligation to pay Bolduc under the subcontract is not at issue in this appeal.
. As a preliminary matter, ECI argues that Travelers bears the burden of proof to show that ECI does not qualify as an additional insured under the endorsement. ECI contends that it has demonstrated a prima facie case of coverage because it has shown that "Bolduc (the named insured) admittedly hit (an "act ”) and damaged ("physical damage ”) the Pipe {property).” ECI therefore characterizes the language of the additional insured endorsement as an exclusion and argues that "Travelers now bears the onerous burden of proving that the damage to the Pipe falls within its exclusion and is not covered.” ECI's argument misses the mark because under the additional insured endorsement, provided the requirements of the endorsement are met, ECI becomes an insured in its own right, not derivatively entitled to insurance coverage due to Bolduc’s liability. Therefore, to establish coverage ECI must show that it, not Bolduc, became a named insured through operation of the additional insured endorsement. ECI’s argument would be relevant only if Bolduc had itself paid to repair the pipeline and was seeking to recover those costs under the policy. In that circumstance, Bolduc’s status as a named insured would be essential to establish a prima facie case of coverage. Here, however, ECI must establish that it qualifies as an insured in order to recover under the policy, and the language of the additional insured endorsement is not properly characterized as an exclusion.
. ECI also argues that Bolduc acted wrongfully in breaching the contractual agreement to indemnify ECI. This argument clearly misses the mark because even ECI does not contend that Bolduc’s failure to indemnify ECI was an act that "caused” the property damage to the pipe, giving rise to ECI's insurance claim. ECI also argues that Bolduc breached the portion of the subcontract that "[n]o advice, recommendations or assistance that representatives of the Owner or ECI may give to [Bolduc] shall operate to relieve [Bolduc] from complete responsibility for such work as an independent contractor.” It is also clear that this breach, if any, was not an act that “caused” the property damage under the plain language of the insurance policy. Again, Bolduc’s failure to take responsibility to repair the pipe after the fact is not an act or omission that caused the damage at issue and therefore is outside the scope of the additional insured endorsement.
. We acknowledge that other courts have found additional insured provisions similar to the one at issue here to be ambiguous, see Consolidation Coal Co. v. Liberty Mut. Ins. Co.,
. We note that our interpretation of this additional insured provision is consistent with our interpretation of the phrase "arising out of” in other insurance policies. In construing other policies, we have given the phrase "arising out of” a broad meaning in an additional insured provision, requiring only that a "but for" causal relationship exist between the actions of the named insured and the liability at issue before the additional insured was entitled to coverage. Faber v. Roelofs,
. ECI argues primarily that Bolduc is contractually liable to ECI, and never explains how Bolduc’s contractual liability to ECI rendered ECI liable for the property damage. ECI’s argument is not persuasive because Bolduc’s liability to ECI is plainly not covered under the additional insured endorsement, which provides ECI with coverage only to the extent that ECI itself becomes liable. To establish coverage, therefore, ECI must show that it, not Bolduc, was liable for the property damage to the pipeline.
. Contrary to the assertion of the district court and ECI, determining that ECI cannot receive insurance coverage in this case is not predicated on an erroneous finding that ECI was negligent. ECI is correct that the jury never determined that ECI was negligent, and no amount of speculation regarding the events leading to the pipe's damage will change that fact. But a decision by this court that ECI cannot receive insurance coverage is based on the finding that Bolduc was not negligent, and ECI cannot trigger insurance coverage based on anyone’s fault other than Bolduc’s.
. Because we conclude that the additional insured endorsement does not provide coverage to ECI with respect to the pipe damage, we do not reach Travelers' alternative argument that ECI is not entitled to coverage because it voluntarily incurred the expenses necessary to repair the pipe without establishing a legal obligation to pay.
. We find the opinion of the court of appeals in the present case particularly problematic with respect to enforcement of this statutory scheme, because of the court’s assertion that “the 'narrow exception' [in Minn.Stat. § 337.05] appears to have swallowed the rule” prohibiting indemnification from the in-demnitee's own negligence.
. ECI admits that it is has not appealed to our court the district court’s grant of summary judgment with respect to ECI's contractual claim that Bolduc failed to perform its work in a workmanlike manner. ECI notes in its brief that "the single issue to be addressed is the enforceability of the Indemnity and Insurance Agreement."
. Under the plain language of the statute, it is irrelevant that the jury did not determine which party, if any, was at fault for the pipeline damage. Indemnification violates Minn. Stat. § 337.02 regardless of whether ECI, Frontier, or another party was at fault for the damage.
