This is a review of an unpublished per curiam decision of the court of appeals, filed on November 8,1988, reversing a judgment entered by the circuit court for Eau Claire county, Judge William D. O'Brien, and remanding the cause for further proceedings. The circuit court granted Eau Claire county's
There are two issues before this court: first, whether Energy Complexes, Inc.'s lawsuit against Eau Claire county is barred by either common-law immunity or statutory immunity under sec. 893.80(4), Stats.; second, if neither common-law nor statutory immunity bars Energy Complexes, Inc.'s lawsuit, whether a disputed issue as to any material fact exists, making it improper for the circuit court to have granted Eau Claire county's motion for summary judgment. We conclude that neither common-law immunity nor statutory immunity under sec. 893.80(4) bars the lawsuit of Energy Complexes, Inc., and that Eau Claire county's motion for summary judgment should not have been granted because a disputed issue of material fact exists. We therefore affirm the decision of the court of appeals that reversed the judgment of the circuit court and remanded the matter for further proceedings.
On April 12, 1983, Eau Claire county (the County) and Energy Complexes, Inc. (ECI) entered into a contract. The contract required ECI to construct, own, and operate a waste-to-energy plant in the city of Eau Claire. The contract required the County to supply the plant with enough waste to make the plant economically feasible and to deliver and sell the steam generated by the plant.
The waste-to-energy project described in the contract would be implemented in three phases: the precon-struсtion financing and planning phase, the construction
The dispute between the County and ECI primarily concerns two provisions of the contract: Article IX, section 3, and Article XIV. Article IX, section 3, which required the County to reimburse ECI for certain costs 3 if the County terminated the cоntract after approving the tipping fee but before the commencement of construction, provides as follows:
County Termination of Agreement Before Construction. If ECI shall meet the tipping fee requirements herein and should the County, for any reason whatsoever, except for ECI's breach of this contract, seek to terminate this Agreement after it has given its approval to ECI relative to the tipping fee, but before construction has commenced, it shall be granted that
option, subject to the qualification that it pay to ECI all costs incurred in the course of pursuing its responsibilities incurred after the signing of this contract but not to include court costs or attorney's fees.
Article XIV, which made any obligation of the County contingent upon the County reaching agreements with Pope and Talbot, Inc. (Pope and Talbot) and the city of Chippewa Falls (Chippewa Falls), provides as follows:
Other Pending Agreements. Any obligations of Eau Claire County shall be contingent upon consummated agreements between Eau Claire County and Pope and Talbot, Inc. for sale and delivery of steam and between the County and the City of Chippewa Falls for delivery of 25 tons per day of refuse.
ECI met the tipping fee requirements mentioned in Article IX, section 3, shortly after the parties signed the contract, and the tipping fee was approved by the County.
The County Board of Supervisors for Eau Claire County considered proposed contracts with Pope and Talbot and Chippewa Falls at three County Board meetings. In the end, a resolution regarding the approval of these proposed contracts and a substitute amendment to this resolution as amended were defeated, thus these proposed contracts were never approved. Apparently, after the August 7, 1984 meeting of the County Board, which was the final meeting at which the proposed contracts were considered, the County made no further efforts to reach agrеements with Pope and Talbot and Chippewa Falls.
On February 7, 1986, ECI commenced a lawsuit against the County in the circuit court for Eau Claire county. The complaint contained four causes of action:
On August 21,1987, the County moved for summary judgment. ECI opposed this motion. In support of their positions, the parties filed briefs and affidavits. The circuit court granted the County's motion for summary judgment and dismissed ECI's comрlaint.
In its memorandum opinion and order for summary judgment, dated December 15,1987, the circuit court set forth its rationale for granting the County's motion for summary judgment. The circuit court first discussed Article XIV, the provision stating that any obligations of the County were contingent upon consummated agreements with Pope and Talbot and Chippewa Falls. The circuit court determined that Article XIV was unambiguous; therefore, the court found it unnecessary to consider extrinsic evidence to interpret the contract. According to the circuit court, because Article XIV stated that any obligation of the County was contingent upon the consummated agreements with Pope and Talbot and Chippewa Falls and because these agreements were never consummated, the County was not liable for the preconstruction costs of ECI.
Moreover, the circuit court determined that, because the County Board of Supervisors exercised a legislative function in rejecting the proposed contracts with Pope and Talbot and Chippewa Falls, the County was immune from ECI's lawsuit under sec. 893.80(4), Stats. 5
We conclude that Articles IX and XIV create an ambiguity on the county's liability that the affidavits and depositions on summary judgment did not eliminate. When read together, Articles IX and XIV do not conclusively show that the parties intended Article XIV to absolve the county of its obligations to indemnify ECI for its costs Article IX would otherwise impose. Further, the affidavits the county submitted contain no extrinsic evidence that the parties intended Article XIV to limit the county's obligations to indemnify ECI under Article IX. This factual dispute required further proceedings for resolution.
The court of appeals also addressed the issue of the County's immunity from ECI's lawsuit under sec. 893.80(4), Stats. The court of appeals concluded that sec. 893.80(4) applies only to lawsuits based in tort. Because ECI's lawsuit involved an alleged breach of contract, the court of appeals reasoned that sec. 893.80(4) did not immunize the County's conduct. 6
The court must initially examine the pleadings to determine whether a claim has been stated and whether a material issue of fact is presented. If the complaint states a claim and the pleadings show the existence of factual issues, the court examines the moving party's. . . affidavits or other proof to determine whether the moving party has made a prima facie case for summary judgment under sec. 802.08(2). To make a prima facie case for summary judgment, a moving defendant must show a defense which would defeat the plaintiff. If the moving party has made a prima facie case for summary judgment, the court must examine the affidavits and other proof of the opposing party ... to determine whether there exist disputed material facts, or undisputed material facts from which reasonable alternative inferences may be drawn, sufficient to entitle the opposing party to a trial.
On summary judgment the moving party has the burden to establish the absence of a genuine, that is, disputed, issue as to any material fact. On summary judgment the court does not decide the issue of fact; it decides whether there is a genuine issue of fact. Asummary judgment should not be granted unless the moving party demonstrates a right to a judgment with such clarity as to leave no room for controversy; some courts have said that summary judgment must be denied unless the moving party demonstrates his entitlement to it beyond a reasonable doubt. Doubts as to the existence of a genuine issue of material fact should be resоlved against the party moving for summary judgment.
The papers filed by the moving party are carefully scrutinized. The inferences to be drawn from the underlying facts contained in the moving party's material should be viewed in the light most favorable to the party opposing the motion. If the movant's papers before the court fail to establish clearly that there is no genuine issue as to any material fact, the motion will be denied. If the material presented on the motion is subject to conflicting interpretations or reasonable people might differ as to its significance, it would be improper to grant summary judgment.
Id. at 338-39 (citations omitted). We now apply the procedure set forth in Grams to the facts of this case to determine whether it was proper for the circuit court to grant the County's motion for summary judgment.
Under the procedure set forth in
Grams,
the first issue this court must address is whether the complaint can survive a sec. 802.06(2)(f), Stats., motion to dismiss for failing to state a claim upon which relief can be granted. In
Morgan v. Pennsylvania General Ins. Co.,
For the purpose of testing whether a claim has been stated pursuant to a motion to dismiss under sec. 802.06(2) (f), Stats., the facts pleaded must be takenas admitted. The purpose of the complaint is to give notice of the nature of the claim; and, therefore, it is not necessary for the plaintiff to set out in the complaint all the facts which must eventually be proved to recover. The purpose of a motion to dismiss for failure to state a claim is the same as the purpose of the old demurrer — to test the legal sufficiency of the claim. Because the pleadings are to be liberally construed, a claim should be dismissed as legally insufficient only if "it is quite clear that under no conditions can the plaintiff recover." Clausen and Lowe, The New Wisconsin Rules of Civil Procedure, Chapters 801-803, 59 Marq. L. Rev. 1, 54 (1976). The facts pleaded and all reasonable inferences from the pleadings must be taken as true, but legal conclusions and unreasonable inferences need not be accepted.
Section 802.06(2)(f), Stats., ... is similar to Rule 12(b)(6) of the Federal Rules of Civil Procedure. A claim should not be dismissed under the Wisconsin rule or the federal rule unless it appears to a certainty that no relief can be granted under any set of facts that plaintiff can prove in support of his allegations.
Id. at 731-32 (citations omitted).
This court has held that the complaint fails to state a claim upon which relief may be granted if the defendant is immune from liability for the activity alleged in the complaint.
See, e.g., C.L. v. Olson,
We conclude that neither the common law nor sec. 893.80(4), Stats., immunize the County from ECI's breach of contract lawsuit, even if the contract was terminated because of legislative acts occurring after the contract was signed. The County is correct that at common law a local government body was immune from
tort liability
for its "discretionary" decisions.
See, e.g., Owen v. City of Independence,
[I]t is established that, if a contraсt has been violated by the municipality, the other party thereto may at once sue to recover damages for its breach, or to recover the amount due thereon in the same manner as though the contract had been made with an individual, firm or private corporation.
10 McQuillin, Municipal Corporations, sec. 29.124, p. 560 (3d ed. 1981). See also 1 J. Dillon, Law of Municipal Corporations, sec. 394, p. 387 (1872) ("But with respect to authorized contracts a municipal corporation has the same rights and remedies; and is bound thereby, and may be sued thereon in the same manner аs individuals."); 1A Antieau, Municipal Corporation Law, sec. 10.67, p. 10-154 (1987) ("Local governments are obligated on their contracts the same as private persons and possess no legal immunity when they commit breaches of contract.").
Section 893.80(4), Stats., does not apply to suits involving a local government body's contractual obligations. The County concedes that when sec. 893,80(4) was originally enacted, it only applied to tort actions. The County argues, however, that sec. 893.80(4) was made applicablе to all actions, including contract actions, by amendments in Chapter 285, Laws of 1977. The County's argument must fail in light of the legislative history behind these 1977 amendments. The prefatory note to Chapter 285, Laws of 1977, shows that the intent of the legislature was merely to consolidate and make uniform the statutory procedures for commencing claims against local government entities. We recognized that
Sec. 893.80, when initially enacted by the legislature, applied only to tort claims, but, by ch. 285, Laws of 1977, the procedures were made generally applicable to any claims against the listed governments.
(Emphasis added.) We find no indication that the legislature intended, in making the 1977 changes, to extend the applicability of the immunity provision, sec. 894.80(4), to contract suits. 9
Because we conclude that neither the common law nor sec. 893.80(4), Stats., stand as a bar to ECI's breach of contract lawsuit, the procedure for evaluating summary judgment motions requires us to examine the pleadings to dеtermine whether a material issue of fact is presented. An examination of the pleadings shows that several factual issues exist. Looking at the second cause of action alone, an issue of fact exists as to whether the parties intended that the County's failure to consummate agreements with Pope and Talbot and Chippewa Falls would absolve the County of any obligation regarding the payment of ECI's preconstruction costs.
Having concluded that the pleadings show the existence of factual issues, we examine the material presented on the motion for summary judgment to determine whether there is a disputed issue as to any material fact. The court must deny a motion for summary judgment if it finds a disputed issue as to any material fact. In summary judgment cases involving contract claims,
The County argues that Artiсle XIV is unambiguous and that no ambiguity is created when Article XIV and Article IX, section 3, are read together. According to the County, Article XIV clearly relieves the County of all liability to ECI because the contracts with Pope and Talbot and Chippewa Falls were never consummated. The County thus asserts that, because the contract is unambiguous, it was improper for the court of appeals to examine extrinsic evidence in the affidavits. ECI, on the other hand, agrees with the holding of the court of appeals that Article XIV and Article IX, section 3, create an ambiguity with respect to the County's liability for ECI's preconstruction costs and that the affidavits did not eliminate the ambiguity, leaving the intent of the parties in dispute.
We find that the contract between the County and ECI is ambiguous. In
Wausau Underwriters v. Dane County,
Whether a contract is ambiguous is itself a question of law which an aрpellate court decides independently of the trial court's decision. A document is ambiguous if it is reasonably susceptible to more than one meaning.
Id.
at 322 (citations omitted). In this case, Article XIV states that any obligation of the County is contingent upon consummated agreements with Pope and Talbot
Once a contract is found to be ambiguous, extrinsic evidence can be considered in order to determine the parties' intent.
Capital Investments v. Whitehall Packing Co.,
In conclusion, we hold that neither common-law immunity nor statutory immunity under sec. 893.80(4), Stats., bars ECI's lawsuit and that the County's motion for summary judgment should have been denied because the contract is ambiguous and the intent of the parties to the contract is disputed. The trial court must conduct further proceedings to resolve this factual dispute. Moreover, as noted by the court of appeals, the trial court
By the Court — The decision of the court of appeals is affirmed.
Notes
The definition of "tipping fee,” set forth in Article VI of the contract, is the "fee collected at the gate of the facility which shall include $5.00 (in 1985 dollars) as a surcharge for operation of the County Landfill."
The contract also provided that ECI "shall use its best efforts, but shall not be deemed contractually bound," to complete the preconstruction and construction phases within twenty-four months of the execution of the contract.
We hereinafter refer to these costs as "preconstruction costs."
In a stipulation filed on September 14, 1987, the parties agreed to the dismissal of ECI's first cause of action, one of the breach of contract claims.
Section 893.80(4), Stats., provides, in part, as follows:
No suit may be brought against any . . . political corporation, gov-
emmental subdivision or any agency thereof... for acts done in the exercise of legislative, quasi-legislative, judicial or quasi-judicial functions.
The court оf appeals also held that on remand the trial court should determine whether the County violated an implied
See also 2A Moore's Federal Practice, para. 12.07[2.-5], pp. 12-68 to 12-69 (2d ed. 1989) ("A motion under Rule 12(b)(6) should also be granted if an affirmative defense or other bar to relief is apparent from the face of the complaint, such as the official immunity of a defendant. . .."); 5 Wright & Miller, Federal Practice and Procedure: Civil, sec. 1357, pp. 608-09 (1969) ("Other affirmative defenses that have been considered on a motion to dismiss include . . . immunity.").
This court has noted that legislative, quasi-legislative, judicial, or quasi-judicial acts are "essentially equivalent" to discretionary acts.
C.L. v. Olson,
This court's decision in
Felder v. Casey,
In support of its motion for summary judgment, the County submitted the affidavits of Attorney James E. Garvey and Ronald Wampler, County Administrator for Eau Claire County. Wampler's affidavit states that, under Article XIV, the County had absolutely no obligation to ECI if the agreements with Pope and Talbot and Chippewa Falls were not consummated and that such contracts were never consummated. In opposition to the County's motion for summary judgment, ECI submitted the affidavits of Robert Hoff, President of ECI, and Attorney Thomas D. Bell. Hoffs affidavit states that Article XIV relieved the County of any obligation to guarantee a supply of waste and steam revenue if the agreements with either Pope and Talbot or Chippewa Falls could not be consummated; Article XIV was not meant to relieve the County of its responsibility to reimburse ECI for preconstruction costs in the event that these agreements could not be consummated. Moreover, Bell's affidavit and the attached deposition of John Boe contain evidence that Article XIV relieved the County of its obligation to pay ECI's preconstruction costs if either Pope and Talbot or Chippewa Falls refused to come to terms with the County but not if the County refused to come to terms with either group on the ground that the County no longer wanted the waste-to-energy plant built.
