MEMORANDUM OPINION AND ORDER
Plaintiff Employers Insurance of Wausau brings this four count action against the United States of America, the United States Environmental Protection Agency, and various Environmental Protection Agency officials. 1 Presently before the court is defendants’ motion of judgment on the pleadings. For the reasons set forth below, the federal defendants’ motion is granted.
I. Judgment on the Pleadings Standard 2
A party is entitled to judgment on the pleadings only if that party “clearly establishes that no material issue of fact remains to be resolved and that he or she is entitled to judgment as a matter of law.”
National Fidelity Life Ins. Co. v. Karaganis,
II. Factual Background 3
On August 24, 1987, fire struck and destroyed a building located in Wyandotte, Michigan. The building’s occupant held a policy with plaintiff Employers Insurance of Wausau (“Wausau”), which covered certain perils, including fire, as well as the expense of debris removal resulting from such perils. At the Wyandotte property, this debris included several electrical transformers. In a settlement "with the policyholder, Wausau agreed to have certain fluids and oils drained from the transformers and removed from the site. In April, 1989, seven hundred gallons of fluids were removed from the transformers and transported to an oil recycling facility in Romulus, Michigan, where the fluids were placed in process tanks for recycling.
The following month, it was discovered that the Romulus facility was contaminated with polychlorinated biphenyls (“PCBs”) 4 *1372 and volatile organic compounds (“VOCs”). 5 The source of the PCB contamination was traced to the oil which had been used in the transformers at the Wyandotte building. On September 11, 1989, the Environmental Protection Agency (“EPA”) designated Wausau as a potentially responsible party under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), as amended by the Superfund Amendments and Reauthorization Act of 1986 (“SARA”), 42 U.S.C. § 9601 et seq, 6 and demanded Wausau’s participation in the cleanup. Wausau did not respond, and in November, 1989, the EPA issued a unilateral administrative order directing Wausau and the other involved parties to begin emergency cleanup measures. Wausau strenuously objected, claiming that the EPA’s characterization of Wausau’s role in the transportation and disposal of the fluids was “materially incorrect,” “erroneous, arbitrary and wrongful.” After some further wrangling, the EPA filed an administrative action against Wausau under the Toxic Substance Control Act, 15 U.S.C. § 2601 et seq., in an effort to force Wausau to comply with the order. Without admitting any responsibility, Wausau relented and submitted an Emergency Response Action Plan (“ERAP”), setting forth the manner in which it would comply with the order. The EPA approved Wausau’s ERAP on February 26, 1990.
The Order itself listed thirty-three findings which detailed the various parties’ involvement in the PCB contamination at the Romulus facility. It further specified that “hazardous substances” were present at the site, both due to the PCB contamination and because there existed waste in drums which contained high levels of VOCs. The order therefore called for the disposal and treatment of “[a]ll materials containing hazardous substance, pollutants or contaminants removed pursuant to this Order.” These requirements of the Order were not limited to PCB-contaminated areas.
The ERAP, drafted by Wausau and approved by the EPA, was expressly designed to “comply with the Order to the extent technically feasible under climatic conditions existing at the Site.... ” The ERAP is somewhat more PCB specific, setting forth particular requirements with respect to PCB contamination. However, it also contains several broad statements about Wausau’s obligations at the Site. Finally, the ERAP expressly amended the Order to allow Wau-sau 180 days to complete its cleanup activities.
Following the EPA’s approval of the ERAP, Wausau began its cleanup. However, in several telephone calls and letters to the EPA, Wausau indicated that it did not believe that it would be responsible for cleaning up any non-PCB contamination under the Order and the ERAP. In response, the EPA consistently maintained that both the Order and the ERAP were worded broadly and were not limited to PCB contamination, and that Wausau was required to clean up all hazardous substances located at the Site. However, Wausau persisted in its interpretation of the Order and ERAP, and claimed that it completed the prescribed cleanup on January 24, 1991, some 331 days after approval of the ERAP, or 151 days late. At no time did Wausau submit a written request for an extension of time, as required by the Order.
On March 22,1991, Wausau filed a petition for reimbursement of reasonable response costs pursuant to § 9606(b)(2) of CERCLA. The EPA responded to Wausau’s request by letter dated June 10, 1991, refusing to grant relief on the grounds that Wausau had not fully complied with the requirements of the § 9606 order and the ERAP. Wausau disputed the EPA’s assessment of the work performed, claiming that the cleanup mea *1373 sures listed by the EPA were either complied with or not required by the order or the ERAP. To support its position, Wausau inspected the CIW site on June 24, 1991, and submitted “Post Response Action Compliance Comments” to the EPA on July 9,1991. Nonetheless, the EPA hired an additional contractor to conduct further cleanup measures at the CIW site. The contractor completed the actions required by the administrative order on October 25, 1991.
Wausau brought the instant action on July 9, 1991. Following a motion to dismiss, which we granted in part and denied in part,
see Employers Ins. of Wausau v. Bush,
III. Statutory Background
Enacted in 1980, “CERCLA was designed ‘to bring order to the array of partly redundant, partly inadequate federal hazardous substances clean up and ■ compensation laws.’ ”
Voluntary Purchasing Groups, Inc. v. Reilly,
On the other hand, the PRP may proceed with the clean-up, and subsequently petition the EPA for reimbursement of the funds it expended. CERCLA § 9606(b) This alternative was added as part of the SARA amendments of 1986 in order to “encourage potentially responsible parties to conduct a cleanup expeditiously and postpone litigation about responsibility to a later time.”
Bethlehem Steel,
IV. Discussion
A, Procedural Due Process
Wausau maintains that CERCLA is constitutionally infirm, both as applied and on its face. Specifically, Wausau claims that the remedial scheme set up by CERCLA § 9606(b) deprived it of procedural due process, at both the pre-enforcement and post-enforcement stages. We shall consider each of Wausau’s contentions in turn.
1. Pre-Enforcement Review
Wausau claims that it did not have the opportunity for a meaningful hearing pri- or to being compelled to participate in the clean-up. As the Supreme Court noted in
Matthews v. Eldridge,
As defendants point out, the provision for pre-enforcement review under CERCLA has been repeatedly challenged, and courts have uniformly upheld its constitutionality.
See, e.g., Barmet Aluminum Corp. v. Reilly,
The same is true of the second factor listed above. As noted, a PRP which believes that an order issued by the EPA is erroneous can refuse to comply with that order. In order to compel compliance with the order and to collect penalties for failure to comply, the EPA is required to bring an enforcement action pursuant to CERCLA § 9606(b)(1). At this stage, the PRP is entitled to judicial review of the order, including the question of liability.
See
CERCLA § 9613(h)(2);
Gary Steel Supply Co. v. Reagan,
711 E.Supp. 471, 475 (N.D.Ill.1989). Accordingly, a PRP is fully entitled to obtain judicial review of the EPA’s order prior to being deprived of its property.
10
We also observe that this oppor
*1375
tunity for review is not compromised by the potential imposition of penalties at the pre-enforcement stage. First, as defendants note, a good faith defense to the administrative order precludes the application of the penalty provision under CERCLA § 9606(b)(1). Furthermore, CERCLA § 9606(b)(1) expressly makes the imposition of penalties discretionary with the court. As a result, the presence of the penalty provision does not affect the constitutionality of the procedures offered in CERCLA for pre-enforcement review.
See Wagner Seed Co.,
In addition, further procedures would provide limited additional safeguards. The “sufficient cause” basis for non-compliance provides PRPs who believe an order erroneous witli sufficient incentive to refuse to comply and take advantage of the opportunity for judicial review. Furthermore, the addition of the reimbursement provisions of CERCLA § 9606(b)(2) in 1986 clearly mitigates any concern that further procedural safeguards are needed.
See Solid State Circuits,
On the other hand, additional procedural requirements at the pre-enforcement stage would seriously compromise the government’s interest. The primary purpose of CERCLA is the prompt cleanup of hazardous waste sites.
J.V. Peters & Co. v. EPA,
However, Wausau also maintains that the procedures offered are inadequate because the EPA failed to provide it with the documents which supported its conclusion that Wausau was properly named as a PRP. Wausau therefore contends that it was not in a position to determine whether it had “sufficient cause” to refuse to comply with the administrative order. We are unconvinced by Wausau’s arguments for several reasons. First, on a practical level, Wausau was fully aware of the extent of its involvement in the transfer of PCB-eontaminated materials to the Romulus site. Similarly, it was equally able to speak with the other PRPs, one of which was its own insured, to determine the information compiled by the EPA. As a result, we see no basis for Wausau’s argument that the EPA was possessed of information regarding Wausau’s activities leading up to the contamination that Wausau itself did not have or have access to. However, even if the EPA had otherwise unattainable information regarding Wausau’s potential liability, nondisclosure at the pre-enforcement stage did not violate Wausau’s due process rights.
See Solid State Circuits,
2. Post-Enforcement Review
Wausau claims that the reimbursement provision of CERCLA § 9606(b)(2) violates due process, both as written and as applied. We reject each of these contentions. Wausau’s claim that the provision is facially unconstitutional is based upon the rule that, where pre-enforcement due process protections are lacking, a deprived party is entitled to “prompt” post-deprivation review.
See, e.g. Industrial Park Development Co. v. EPA
Wausau also raises two arguments in support of its claim that CERCLA § 9606(b)(2) is unconstitutional as applied. Again it claims that the EPA’s failure to disclose liability evidence, this time during the reimbursement process, constituted a violation of due process. However, we recently concluded in the related case
Employers Ins. of Wausau v. Clinton,
We also reject Wausau’s other “as applied” constitutional challenge. As noted above, reimbursement is only available to a PRP which “receives and complies” with the EPA’s order.
See
CERCLA § 9606(b)(2)(A). Wausau contends that, once all work is completed at a given site, 9606(b)(2) reimbursement should be available to any party who participated in the clean-up, regardless of who actually completed the work.
12
This is, of course, contrary to the EPA’s interpretation and application of the provision. It is well established that we must defer to an agency’s interpretation of a statute it administers, as long as that interpretation is reasonable.
Chevron U.S.A, Inc. v. Natural Resource Defense Council, Inc.,
B. Substantive Due Process
The second count of Wausau’s third amended complaint asserts a violation of substantive due process. As we stated in
Universal Sec. Ins. Co. v. Koefoed,
As discussed above, Wausau has failed to establish that the remedial scheme under CERCLA violated Wausau’s procedural due process rights. Wausau can therefore not hang its substantive due process claim on this hook. Likewise, Wausau is unable to show a separate constitutional violation. Of course, Wausau has alleged that the EPA violated both procedural due process and principles of equal protection. Again, however, we rejected Wausau’s procedural due process claim above, and we reject Wausau’s equal protection claim below. Our conclusions with respect to these issues therefore leave Wausau without a basis for its substantive due process claim, even if the EPA’s actions were arbitrary and irrational. .This case is thus similar to both
New Burnham,
and
Koefoed,
in which the courts rejected procedural and/or equal protection claims, thereby eliminating the grounds for a substantive due process claim.
See New Burnham,
C. Equal Protection
In Count III, Wausau claims that the defendants violated the equal protection clause by treating Wausau differently than other PRPs. It is well established that “[i]n order to assert a constitutional claim based on violation of equal protection, a complaining party must assert disparate treatment based on their membership in a particular group.”
New Burnham Prairie Home, Inc. v. Village of Burnham,
D. Administrative Procedure Act
Wausau’s final count seeks review under the Administrative Procedure Act (“APA”), 5 U.S.C. § 700
et seq.
Specifically, Wausau would have us conclude that the EPA’s determination that Wausau was a PRP, and its subsequent actions, were un
*1379
supported by substantial evidence, arbitrary, capricious, and not in accordance with law. Congress enacted the APA to guarantee that individuals could obtain review for actions taken by administrative agencies. However, the APA applies only when “there is no other adequate remedy in a court.” APA § 704. In addition, the APA does not apply “to the extent the relevant statute ‘preelude[s] judicial review.’”
Block v. Community Nutrition Inst.,
(1) An action under section 9607 of this title to recover response costs or damages or for contribution.
(2) An action to enforce an order issued under section 9606(a) of this title or to recover a penalty for violation of such order.
(3) An action for reimbursement under section 9606(b)(2) of this title.
(4) An action under section 9669 of this title (relating to citizens suits) alleging that the removal or remedial action taken under section 9604 of this title or secured under section 9606 of this title was in violation of any requirement of this chapter. Such an action may not be brought with regard to a removal where a remedial action is to be undertaken at the site.
(5) An action under section 9606 of this title in which the United States has moved to compel a remedial action.
CERCLA § 9613(h). It is therefore apparent that CERCLA provides for review of the issue Wausau raises in Count IV, and that CERCLA precludes judicial review of that issue outside the scope of CERCLA § 9613(h). Accordingly, review under the Administrative Procedure Act is inappropriate here. 16 We therefore grant defendants’ motion for judgment on the pleadings with respect to Count IV.
V. Conclusion
For the reasons set forth above, we grant defendants’ motion for judgment on the pleadings. It is so ordered.
Notes
. Specifically, the suit names Carol M. Browner, as Administrator of the EPA, Valdas V. Adamkus, as Regional Administrator of Region V of the EPA, and William E. Muño, as Acting Director of the Office of Waste Programs Enforcement of the EPA.
. Wausau has asked that we convert defendants' motion for judgment on the pleadings to a motion for summary judgment pursuant to Fed. R.Civ.P. 12(c).
See, e.g. Republic Steel Corp. v. Pa. Eng’g Corp.,
. The factual background is more fully set forth in our recent opinion in the related case
Employers Ins. of Wausau v. Clinton,
. PCBs are a group of chemicals used primarily as coolants in electrical equipment. They are "among the most hazardous man-made chemical substances.”
Environmental Transp. Systems, Inc.
v.
ENSCO, Inc.,
. VOCs are "vapors emitted from substances such as gasoline and solvents.”
Motor Vehicle Mfrs. Ass'n v. New York State Dep't of Envtl. Conservation,
. We shall refer to the relevant sections of CERCLA as "CERCLA §-," using the section numbers employed in the United States Code rather than those used in CERCLA’s internal numbering system.
. In a related action, Wausau challenged the EPA's denial of its petition for reimbursement.
See Employers Ins. of Wausau v. Clinton,
. CERCLA’s definition of “hazardous substances” is broad, and includes hazardous wastes listed under five other federal environmental statutes, including the Resource Conservation and Recovery Act, 42 U.S.C. § 6901 et seq. See CERCLA § 9601(14).
. We note that most of the authority granted under CERCLA is explicitly imparted to the President. However, the President has delegated the administration of CERCLA to the Administrator of the EPA. See Exec. Order No. 12,580, 50 Fed.Reg. 2923 (1987), reprinted in 42 U.S.C. § 9615 note (Supp.1991).
. Wausau’s convoluted argument to the contrary is unconvincing. Wausau notes that the EPA is vested with the authority to bring an enforcement action under' CERCLA §§ 9606(b)(1) and 9613(h)(2). Because the decision to bring such an action is solely within the discretion of the EPA, Wausau argues, a PRP would not be able to obtain review of an order if the EPA refused to bring an enforcement action. While this is certainly true, it is also irrelevant. That is, the only means that the EPA has of forcing a PRP to comply with an order, or of collecting penalties for failure to comply, is through an enforcement action. As a result, no deprivation can possibly occur until the EPA brings such an action, at which time the PRP is also entitled to judicial review. Accordingly, the lack of a hearing prior to the bringing of an *1375 enforcement action is irrelevant, since there is also no deprivation at that time.
. We also note that Solid State Circuits applied CERCLA as it existed before the addition of the reimbursement provision. Thus, the constitutionality of CERCLA does not hinge upon the post-enforcement review available under CERC-LA § 9606(b)(2); rather, that provision merely adds further support to a finding of constitutionality.
. For example, Wausau maintains that it is entitled to consideration of its reimbursement petition, even though it failed to fully comply with the order, since the all the necessary work at the site has been "completed,” albeit by the EPA.
. Indeed, the heart of Wausau's objection is that it was required under the order to clean up non-PCB contaminants, notwithstanding the fact that even the EPA acknowledged that Wausau's potential responsibility, was limited to PCB contamination. In our recent opinion in
Employers Ins. of Wausau v. Clinton,
. New Burnham arose in the context of state-based property rights, thus explaining the reference to the adequacy of state law, as opposed to *1378 federal law, remedies. However, there is no reason that the Seventh Circuit’s requirements would not apply equally to claims based upon federal law. As a result, we will look generally to the sufficiency of procedural remedies to determine whether Wausau’s substantive due process claim will fail or succeed.
. An indication of the limited stock which Wau-sau placed in its substantive due process claim is the fact that its sole response to defendants' motion for judgment on Count II came in a footnote in its Response Memorandum. Of course, in Wausau’s case, this should come as no surprise, since Wausau’s brief is replete with footnotes, totalling thirty-three footnotes over twenty-five pages. Indeed, all but two pages of Wausau's twenty-one page argument include at least one footnote, and ten contain two or more. These footnotes, in turn, range from as little as three to as many as forty-one single spaced lines, in several cases occupying well over half the page. This court frowns on parties who attempt to thwart well-established page limits by crowding substantive arguments into multiple single-spaced footnotes. We will simply give such arguments the respect which their placement indicates they deserve.
. We also note that Wausau has completely failed to respond to defendants' motion for judgment on Count IV, thereby conceding defendants' arguments in support of that motion.
See Valluzzi
v.
United States Postal Service,
